Holt Quarry

Metal/Non-Metal, SurfaceDimension Stone NECFranklin, ArkansasMine ID 0302058

Operator Rainbow Stone CompanyController not shownMSHA status Active since Dec 5, 2023

What MSHA has on file for this mine

Citations and orders
24
since Dec 4, 2017 · 24 to the operator, 0 to contractors · 5 marked S&S
Contested citations
None on record
Imminent danger orders, section 107(a)
None on record
MSHA's list starts July 1, 2010
Accident, injury or illness reports
None on record
MSHA's file starts January 2000
Yearly employment and hours
6 years
one row per part of the mine

MSHA records as of Nov 6, 2026. Having MSHA inspection records is common for operating mines. Data and methodology

Inspections

Regular Safety and Health Inspection
Apr 8, 2026Inspectors 1 | Hours on site 3.5

The inspection

BeganINSPECTION_BEGIN_DT
Apr 8, 2026
Closed outINSPECTION_END_DT
Apr 8, 2026
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F03A7D4
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
6

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2026
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Dec 8 to Dec 11, 2025Inspectors 1 | Hours on site 5

The inspection

BeganINSPECTION_BEGIN_DT
Dec 8, 2025
Closed outINSPECTION_END_DT
Dec 11, 2025
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F022A2A
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
5
Total inspection hoursSUM_TOTAL_INSP_HOURS
11.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
May 5, 2025Inspectors 1 | Hours on site 3

The inspection

BeganINSPECTION_BEGIN_DT
May 5, 2025
Closed outINSPECTION_END_DT
May 5, 2025
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F014AFB
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3
Total inspection hoursSUM_TOTAL_INSP_HOURS
8

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jan 29 to Jan 30, 2025Inspectors 1 | Hours on site 8.25

The inspection

BeganINSPECTION_BEGIN_DT
Jan 29, 2025
Closed outINSPECTION_END_DT
Jan 30, 2025
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F003536
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
8.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
9.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Spot Inspection
Sep 24 to Sep 26, 2024Inspectors 1 | Hours on site 12.5

The inspection

BeganINSPECTION_BEGIN_DT
Sep 24, 2024
Closed outINSPECTION_END_DT
Sep 26, 2024
ActivityACTIVITY
Spot Inspection
Activity codeACTIVITY_CODE
E16
Program areaPROGRAM_AREA
M/NM--Spot Inspection
Event numberEVENT_NO
6938780
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
12.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
29

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Compliance Follow-up Inspection
Jul 24, 2024Inspectors 1 | Hours on site 1.25

The inspection

BeganINSPECTION_BEGIN_DT
Jul 24, 2024
Closed outINSPECTION_END_DT
Jul 24, 2024
ActivityACTIVITY
Compliance Follow-up Inspection
Activity codeACTIVITY_CODE
E15
Program areaPROGRAM_AREA
M/NM--Compliance Follow-up Inspection
Event numberEVENT_NO
6938246
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
1.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
3.75
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE
1.25
Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE
3.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (1)

Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jul 8 to Jul 9, 2024Inspectors 1 | Hours on site 5

The inspection

BeganINSPECTION_BEGIN_DT
Jul 8, 2024
Closed outINSPECTION_END_DT
Jul 9, 2024
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F00555A
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
5
Total inspection hoursSUM_TOTAL_INSP_HOURS
14

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Special Emphasis Programs
May 22, 2024Inspectors 1 | Hours on site 0.5

The inspection

BeganINSPECTION_BEGIN_DT
May 22, 2024
Closed outINSPECTION_END_DT
May 22, 2024
ActivityACTIVITY
Special Emphasis Programs
Activity codeACTIVITY_CODE
E17
Program areaPROGRAM_AREA
M/NM--Special Emphasis Programs
Event numberEVENT_NO
6935792
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
0.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
1

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Feb 5 to Feb 6, 2024Inspectors 1 | Hours on site 10.5

The inspection

BeganINSPECTION_BEGIN_DT
Feb 5, 2024
Closed outINSPECTION_END_DT
Feb 6, 2024
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6937331
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
10.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
16.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Spot Inspection
Dec 4 to Dec 11, 2023Inspectors 1 | Hours on site 0

The inspection

BeganINSPECTION_BEGIN_DT
Dec 4, 2023
Closed outINSPECTION_END_DT
Dec 11, 2023
ActivityACTIVITY
Spot Inspection
Activity codeACTIVITY_CODE
E16
Program areaPROGRAM_AREA
M/NM--Spot Inspection
Event numberEVENT_NO
6935746
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Total inspection hoursSUM_TOTAL_INSP_HOURS
5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Holt Farm
Operator IDOPERATOR_ID
0148873
Controller IDCONTROLLER_ID
0130701
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (14)

Hours on siteSUM_TOTAL_ON_SITE_HOURS, Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Dec 4 to Dec 6, 2017Inspectors 1 | Hours on site 5.5

The inspection

BeganINSPECTION_BEGIN_DT
Dec 4, 2017
Closed outINSPECTION_END_DT
Dec 6, 2017
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6739049
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
5.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
11

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Holt Farm
Operator IDOPERATOR_ID
0148873
Controller IDCONTROLLER_ID
0130701
Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Dec 13 to Dec 15, 2016Inspectors 1 | Hours on site 2

The inspection

BeganINSPECTION_BEGIN_DT
Dec 13, 2016
Closed outINSPECTION_END_DT
Dec 15, 2016
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6738610
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
2
Total inspection hoursSUM_TOTAL_INSP_HOURS
5.75

Who and when, as recorded

Mine IDMINE_ID
0302058
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (6)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Operator at the timeOPERATOR_NAME, Operator IDOPERATOR_ID, Controller at the timeCONTROLLER_NAME, Controller IDCONTROLLER_ID

12 inspections and other MSHA visits since Dec 13, 2016; activity names are MSHA's own text. Full list: MSHA Mine Data Retrieval System.

Citations and orders

Issued: Apr 8, 2026
Type: Citation
Standard: 56.4201(a)(2)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
5009164
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 8, 2026
Time issuedVIOLATION_ISSUE_TIME
0815
Date of occurrenceVIOLATION_OCCUR_DT
Apr 8, 2026
30 CFR part and sectionPART_SECTION
56.4201(a)(2)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 8, 2026
Originally due, timeORIG_TERM_DUE_TIME
1300
Latest dueLATEST_TERM_DUE_DT
Apr 8, 2026
Latest due, timeLATEST_TERM_DUE_TIME
1300
TerminatedTERMINATION_DT
Apr 8, 2026
Terminated, timeTERMINATION_TIME
0819
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Bill first printedBILL_PRINT_DT
Jun 4, 2026
Final order dateFINAL_ORDER_ISSUE_DT
Aug 3, 2026
Last actionLAST_ACTION_CD
1stDemandPrinted
Last action dateLAST_ACTION_DT
Sep 18, 2026
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F03A7D4
Inspection beganINSPECTION_BEGIN_DT
Apr 8, 2026
Inspection closed outINSPECTION_END_DT
Apr 8, 2026
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2026
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 8, 2026
Type: Citation
Standard: 41.12
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
5009165
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 8, 2026
Time issuedVIOLATION_ISSUE_TIME
1014
Date of occurrenceVIOLATION_OCCUR_DT
Apr 8, 2026
30 CFR part and sectionPART_SECTION
41.12
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 15, 2026
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Apr 15, 2026
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Apr 16, 2026
Terminated, timeTERMINATION_TIME
1232
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Bill first printedBILL_PRINT_DT
Jun 4, 2026
Final order dateFINAL_ORDER_ISSUE_DT
Aug 3, 2026
Last actionLAST_ACTION_CD
1stDemandPrinted
Last action dateLAST_ACTION_DT
Sep 18, 2026
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F03A7D4
Inspection beganINSPECTION_BEGIN_DT
Apr 8, 2026
Inspection closed outINSPECTION_END_DT
Apr 8, 2026
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2026
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Persons potentially affectedNO_AFFECTED, Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 9, 2025
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
5009101
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 9, 2025
Time issuedVIOLATION_ISSUE_TIME
0927
Date of occurrenceVIOLATION_OCCUR_DT
Dec 9, 2025
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 9, 2025
Originally due, timeORIG_TERM_DUE_TIME
1030
Latest dueLATEST_TERM_DUE_DT
Dec 9, 2025
Latest due, timeLATEST_TERM_DUE_TIME
1030
TerminatedTERMINATION_DT
Dec 9, 2025
Terminated, timeTERMINATION_TIME
0930
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Bill first printedBILL_PRINT_DT
Feb 5, 2026
Final order dateFINAL_ORDER_ISSUE_DT
Mar 12, 2026
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Jun 25, 2026
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
12
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F022A2A
Inspection beganINSPECTION_BEGIN_DT
Dec 8, 2025
Inspection closed outINSPECTION_END_DT
Dec 11, 2025
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (2)

Persons potentially affectedNO_AFFECTED, Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 9, 2025
Type: Citation
Standard: 56.12025
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $165.00
Details

The citation

Citation or order numberVIOLATION_NO
5009100
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 9, 2025
Time issuedVIOLATION_ISSUE_TIME
0801
Date of occurrenceVIOLATION_OCCUR_DT
Dec 9, 2025
30 CFR part and sectionPART_SECTION
56.12025
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 11, 2025
Originally due, timeORIG_TERM_DUE_TIME
0900
Latest dueLATEST_TERM_DUE_DT
Dec 11, 2025
Latest due, timeLATEST_TERM_DUE_TIME
0900
TerminatedTERMINATION_DT
Dec 11, 2025
Terminated, timeTERMINATION_TIME
0733
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
165
Current proposed assessmentAMOUNT_DUE
165
Bill first printedBILL_PRINT_DT
Feb 5, 2026
Final order dateFINAL_ORDER_ISSUE_DT
Mar 12, 2026
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Jun 25, 2026
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
12
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F022A2A
Inspection beganINSPECTION_BEGIN_DT
Dec 8, 2025
Inspection closed outINSPECTION_END_DT
Dec 11, 2025
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 8, 2025
Type: Citation
Standard: 56.14132(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $165.00
Details

The citation

Citation or order numberVIOLATION_NO
5009099
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 8, 2025
Time issuedVIOLATION_ISSUE_TIME
1540
Date of occurrenceVIOLATION_OCCUR_DT
Dec 8, 2025
30 CFR part and sectionPART_SECTION
56.14132(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 9, 2025
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
Dec 9, 2025
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
Dec 11, 2025
Terminated, timeTERMINATION_TIME
0732
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
165
Current proposed assessmentAMOUNT_DUE
165
Bill first printedBILL_PRINT_DT
Feb 5, 2026
Final order dateFINAL_ORDER_ISSUE_DT
Mar 12, 2026
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Jun 25, 2026
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
12
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F022A2A
Inspection beganINSPECTION_BEGIN_DT
Dec 8, 2025
Inspection closed outINSPECTION_END_DT
Dec 11, 2025
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jan 29, 2025
Type: Citation
Standard: 56.12018
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $245.00
Details

The citation

Citation or order numberVIOLATION_NO
5001010
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jan 29, 2025
Time issuedVIOLATION_ISSUE_TIME
1430
Date of occurrenceVIOLATION_OCCUR_DT
Jan 29, 2025
30 CFR part and sectionPART_SECTION
56.12018
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jan 29, 2025
Originally due, timeORIG_TERM_DUE_TIME
1700
Latest dueLATEST_TERM_DUE_DT
Jan 29, 2025
Latest due, timeLATEST_TERM_DUE_TIME
1700
TerminatedTERMINATION_DT
Jan 29, 2025
Terminated, timeTERMINATION_TIME
1530
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
245
Current proposed assessmentAMOUNT_DUE
245
Bill first printedBILL_PRINT_DT
Apr 3, 2025
Final order dateFINAL_ORDER_ISSUE_DT
May 14, 2025
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Aug 28, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
15
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F003536
Inspection beganINSPECTION_BEGIN_DT
Jan 29, 2025
Inspection closed outINSPECTION_END_DT
Jan 30, 2025
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
2

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Sep 25, 2024
Type: Citation
Standard: 62.110
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9791350
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Sep 25, 2024
Time issuedVIOLATION_ISSUE_TIME
1530
Date of occurrenceVIOLATION_OCCUR_DT
Sep 25, 2024
30 CFR part and sectionPART_SECTION
62.110
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 16, 2024
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Nov 6, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Nov 18, 2024
Terminated, timeTERMINATION_TIME
0801
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Oct 31, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Dec 6, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 20, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
6938780
Inspection beganINSPECTION_BEGIN_DT
Sep 24, 2024
Inspection closed outINSPECTION_END_DT
Sep 26, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Sep 25, 2024
Type: Citation
Standard: 62.120
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9791349
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Sep 25, 2024
Time issuedVIOLATION_ISSUE_TIME
1531
Date of occurrenceVIOLATION_OCCUR_DT
Sep 25, 2024
30 CFR part and sectionPART_SECTION
62.120
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 9, 2024
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Oct 9, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Oct 25, 2024
Terminated, timeTERMINATION_TIME
0900
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Oct 31, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Dec 6, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 20, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
6938780
Inspection beganINSPECTION_BEGIN_DT
Sep 24, 2024
Inspection closed outINSPECTION_END_DT
Sep 26, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Sep 24, 2024
Type: Citation
Standard: 56.14207
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9791347
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Sep 24, 2024
Time issuedVIOLATION_ISSUE_TIME
1202
Date of occurrenceVIOLATION_OCCUR_DT
Sep 24, 2024
30 CFR part and sectionPART_SECTION
56.14207
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Sep 24, 2024
Originally due, timeORIG_TERM_DUE_TIME
1215
Latest dueLATEST_TERM_DUE_DT
Sep 24, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1215
TerminatedTERMINATION_DT
Sep 24, 2024
Terminated, timeTERMINATION_TIME
1203
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Oct 31, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Dec 6, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 20, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
6938780
Inspection beganINSPECTION_BEGIN_DT
Sep 24, 2024
Inspection closed outINSPECTION_END_DT
Sep 26, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Sep 24, 2024
Type: Citation
Standard: 56.14107(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9791348
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Sep 24, 2024
Time issuedVIOLATION_ISSUE_TIME
1306
Date of occurrenceVIOLATION_OCCUR_DT
Sep 24, 2024
30 CFR part and sectionPART_SECTION
56.14107(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Sep 25, 2024
Originally due, timeORIG_TERM_DUE_TIME
1400
Latest dueLATEST_TERM_DUE_DT
Sep 25, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1400
TerminatedTERMINATION_DT
Sep 25, 2024
Terminated, timeTERMINATION_TIME
1458
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Oct 31, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Dec 6, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 20, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
6938780
Inspection beganINSPECTION_BEGIN_DT
Sep 24, 2024
Inspection closed outINSPECTION_END_DT
Sep 26, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 8, 2024
Type: Citation
Standard: 56.4101
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9795259
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 8, 2024
Time issuedVIOLATION_ISSUE_TIME
1334
Date of occurrenceVIOLATION_OCCUR_DT
Jul 8, 2024
30 CFR part and sectionPART_SECTION
56.4101
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 8, 2024
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Jul 8, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Jul 8, 2024
Terminated, timeTERMINATION_TIME
1334
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Nov 14, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 6, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F00555A
Inspection beganINSPECTION_BEGIN_DT
Jul 8, 2024
Inspection closed outINSPECTION_END_DT
Jul 9, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 8, 2024
Type: Citation
Standard: 56.14132(b)(1)(i)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9795255
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 8, 2024
Time issuedVIOLATION_ISSUE_TIME
1238
Date of occurrenceVIOLATION_OCCUR_DT
Jul 8, 2024
30 CFR part and sectionPART_SECTION
56.14132(b)(1)(i)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 9, 2024
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Jul 9, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Jul 24, 2024
Terminated, timeTERMINATION_TIME
0954
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Nov 14, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 6, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F00555A
Inspection beganINSPECTION_BEGIN_DT
Jul 8, 2024
Inspection closed outINSPECTION_END_DT
Jul 9, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 8, 2024
Type: Citation
Standard: 56.14132(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9795254
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 8, 2024
Time issuedVIOLATION_ISSUE_TIME
1236
Date of occurrenceVIOLATION_OCCUR_DT
Jul 8, 2024
30 CFR part and sectionPART_SECTION
56.14132(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 9, 2024
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Jul 9, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Jul 24, 2024
Terminated, timeTERMINATION_TIME
0950
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Nov 14, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 6, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F00555A
Inspection beganINSPECTION_BEGIN_DT
Jul 8, 2024
Inspection closed outINSPECTION_END_DT
Jul 9, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 8, 2024
Type: Citation
Standard: 56.14132(b)(1)(i)
S&S: Y
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $535.00
Details

The citation

Citation or order numberVIOLATION_NO
9795257
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 8, 2024
Time issuedVIOLATION_ISSUE_TIME
1312
Date of occurrenceVIOLATION_OCCUR_DT
Jul 8, 2024
30 CFR part and sectionPART_SECTION
56.14132(b)(1)(i)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 8, 2024
Originally due, timeORIG_TERM_DUE_TIME
1327
Latest dueLATEST_TERM_DUE_DT
Jul 8, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1327
TerminatedTERMINATION_DT
Jul 24, 2024
Terminated, timeTERMINATION_TIME
0943
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
535
Current proposed assessmentAMOUNT_DUE
535
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Nov 14, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 6, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F00555A
Inspection beganINSPECTION_BEGIN_DT
Jul 8, 2024
Inspection closed outINSPECTION_END_DT
Jul 9, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 8, 2024
Type: Citation
Standard: 56.14100(b)
S&S: Y
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $535.00
Details

The citation

Citation or order numberVIOLATION_NO
9795258
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 8, 2024
Time issuedVIOLATION_ISSUE_TIME
1322
Date of occurrenceVIOLATION_OCCUR_DT
Jul 8, 2024
30 CFR part and sectionPART_SECTION
56.14100(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 8, 2024
Originally due, timeORIG_TERM_DUE_TIME
1337
Latest dueLATEST_TERM_DUE_DT
Jul 8, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1337
TerminatedTERMINATION_DT
Jul 24, 2024
Terminated, timeTERMINATION_TIME
0942
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
535
Current proposed assessmentAMOUNT_DUE
535
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Nov 14, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 6, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F00555A
Inspection beganINSPECTION_BEGIN_DT
Jul 8, 2024
Inspection closed outINSPECTION_END_DT
Jul 9, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 8, 2024
Type: Citation
Standard: 56.14100(b)
S&S: Y
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $535.00
Details

The citation

Citation or order numberVIOLATION_NO
9795253
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 8, 2024
Time issuedVIOLATION_ISSUE_TIME
1226
Date of occurrenceVIOLATION_OCCUR_DT
Jul 8, 2024
30 CFR part and sectionPART_SECTION
56.14100(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Mill

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 8, 2024
Originally due, timeORIG_TERM_DUE_TIME
1241
Latest dueLATEST_TERM_DUE_DT
Jul 8, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1241
TerminatedTERMINATION_DT
Jul 24, 2024
Terminated, timeTERMINATION_TIME
0947
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
535
Current proposed assessmentAMOUNT_DUE
535
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Nov 14, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 6, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F00555A
Inspection beganINSPECTION_BEGIN_DT
Jul 8, 2024
Inspection closed outINSPECTION_END_DT
Jul 9, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 8, 2024
Type: Citation
Standard: 56.14130(i)
S&S: Y
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $1,188.00
Details

The citation

Citation or order numberVIOLATION_NO
9795256
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 8, 2024
Time issuedVIOLATION_ISSUE_TIME
1302
Date of occurrenceVIOLATION_OCCUR_DT
Jul 8, 2024
30 CFR part and sectionPART_SECTION
56.14130(i)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 8, 2024
Originally due, timeORIG_TERM_DUE_TIME
1317
Latest dueLATEST_TERM_DUE_DT
Jul 8, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1317
TerminatedTERMINATION_DT
Jul 24, 2024
Terminated, timeTERMINATION_TIME
0941
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
1188
Current proposed assessmentAMOUNT_DUE
1188
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Nov 14, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 6, 2025
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
F00555A
Inspection beganINSPECTION_BEGIN_DT
Jul 8, 2024
Inspection closed outINSPECTION_END_DT
Jul 9, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Feb 6, 2024
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9748069
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Feb 6, 2024
Time issuedVIOLATION_ISSUE_TIME
0940
Date of occurrenceVIOLATION_OCCUR_DT
Feb 6, 2024
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Feb 6, 2024
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
Feb 6, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
Feb 6, 2024
Terminated, timeTERMINATION_TIME
1030
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Apr 4, 2024
Final order dateFINAL_ORDER_ISSUE_DT
May 15, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Aug 29, 2024
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
6937331
Inspection beganINSPECTION_BEGIN_DT
Feb 5, 2024
Inspection closed outINSPECTION_END_DT
Feb 6, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
2

Recorded as 0 (3)

Persons potentially affectedNO_AFFECTED, Amount paidAMOUNT_PAID, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Feb 6, 2024
Type: Citation
Standard: 56.12028
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9748068
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Feb 6, 2024
Time issuedVIOLATION_ISSUE_TIME
0905
Date of occurrenceVIOLATION_OCCUR_DT
Feb 6, 2024
30 CFR part and sectionPART_SECTION
56.12028
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Feb 15, 2024
Originally due, timeORIG_TERM_DUE_TIME
0800
Latest dueLATEST_TERM_DUE_DT
Feb 15, 2024
Latest due, timeLATEST_TERM_DUE_TIME
0800
TerminatedTERMINATION_DT
Feb 16, 2024
Terminated, timeTERMINATION_TIME
0931
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Apr 4, 2024
Final order dateFINAL_ORDER_ISSUE_DT
May 15, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Aug 29, 2024
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
6937331
Inspection beganINSPECTION_BEGIN_DT
Feb 5, 2024
Inspection closed outINSPECTION_END_DT
Feb 6, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
2

Recorded as 0 (2)

Amount paidAMOUNT_PAID, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Feb 5, 2024
Type: Citation
Standard: 56.14132(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9748067
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Feb 5, 2024
Time issuedVIOLATION_ISSUE_TIME
1400
Date of occurrenceVIOLATION_OCCUR_DT
Feb 5, 2024
30 CFR part and sectionPART_SECTION
56.14132(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Feb 5, 2024
Originally due, timeORIG_TERM_DUE_TIME
1530
Latest dueLATEST_TERM_DUE_DT
Feb 6, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1000
TerminatedTERMINATION_DT
Feb 6, 2024
Terminated, timeTERMINATION_TIME
0949
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Apr 4, 2024
Final order dateFINAL_ORDER_ISSUE_DT
May 15, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Aug 29, 2024

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
6937331
Inspection beganINSPECTION_BEGIN_DT
Feb 5, 2024
Inspection closed outINSPECTION_END_DT
Feb 6, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
2

Recorded as 0 (3)

Amount paidAMOUNT_PAID, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Feb 5, 2024
Type: Citation
Standard: 56.12002
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9748066
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Feb 5, 2024
Time issuedVIOLATION_ISSUE_TIME
1350
Date of occurrenceVIOLATION_OCCUR_DT
Feb 5, 2024
30 CFR part and sectionPART_SECTION
56.12002
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Feb 5, 2024
Originally due, timeORIG_TERM_DUE_TIME
1530
Latest dueLATEST_TERM_DUE_DT
Feb 5, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1530
TerminatedTERMINATION_DT
Feb 5, 2024
Terminated, timeTERMINATION_TIME
1430
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Bill first printedBILL_PRINT_DT
Apr 4, 2024
Final order dateFINAL_ORDER_ISSUE_DT
May 15, 2024
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Aug 29, 2024

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Rainbow Stone Company
Operator IDVIOLATOR_ID
0119849
Controller IDCONTROLLER_ID
0101845
Inspection eventEVENT_NO
6937331
Inspection beganINSPECTION_BEGIN_DT
Feb 5, 2024
Inspection closed outINSPECTION_END_DT
Feb 6, 2024
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
2

Recorded as 0 (3)

Amount paidAMOUNT_PAID, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 4, 2023
Type: Citation
Standard: 56.1000
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9743732
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 4, 2023
Time issuedVIOLATION_ISSUE_TIME
1500
Date of occurrenceVIOLATION_OCCUR_DT
Dec 4, 2023
30 CFR part and sectionPART_SECTION
56.1000
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 5, 2023
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Dec 5, 2023
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Dec 5, 2023
Terminated, timeTERMINATION_TIME
1101
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Amount paidAMOUNT_PAID
147
Bill first printedBILL_PRINT_DT
Feb 7, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Mar 13, 2024
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 18, 2024

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Holt Farm
Operator IDVIOLATOR_ID
0148873
Controller IDCONTROLLER_ID
0130701
Inspection eventEVENT_NO
6935746
Inspection beganINSPECTION_BEGIN_DT
Dec 4, 2023
Inspection closed outINSPECTION_END_DT
Dec 11, 2023
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (3)

Persons potentially affectedNO_AFFECTED, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 4, 2023
Type: Order
Standard: 46.5(b)
S&S: Y
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $397.00
Details

The citation

Citation or order numberVIOLATION_NO
9743733
TypeCIT_ORD_SAFE
Order
IssuedVIOLATION_ISSUE_DT
Dec 4, 2023
Time issuedVIOLATION_ISSUE_TIME
1515
Date of occurrenceVIOLATION_OCCUR_DT
Dec 4, 2023
30 CFR part and sectionPART_SECTION
46.5(b)
Section of the Act, primarySECTION_OF_ACT_1
104(g)(1)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

TerminatedTERMINATION_DT
Dec 5, 2023
Terminated, timeTERMINATION_TIME
1000
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
397
Current proposed assessmentAMOUNT_DUE
397
Amount paidAMOUNT_PAID
397
Bill first printedBILL_PRINT_DT
Feb 7, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Mar 13, 2024
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 18, 2024

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Holt Farm
Operator IDVIOLATOR_ID
0148873
Controller IDCONTROLLER_ID
0130701
Inspection eventEVENT_NO
6935746
Inspection beganINSPECTION_BEGIN_DT
Dec 4, 2023
Inspection closed outINSPECTION_END_DT
Dec 11, 2023
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (17)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, Originally dueORIG_TERM_DUE_DT, Originally due, timeORIG_TERM_DUE_TIME, Latest dueLATEST_TERM_DUE_DT, Latest due, timeLATEST_TERM_DUE_TIME, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 4, 2017
Type: Citation
Standard: 56.15001
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $118.00
Details

The citation

Citation or order numberVIOLATION_NO
9354487
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 4, 2017
Time issuedVIOLATION_ISSUE_TIME
1405
Date of occurrenceVIOLATION_OCCUR_DT
Dec 4, 2017
30 CFR part and sectionPART_SECTION
56.15001
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 6, 2017
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Dec 6, 2017
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Dec 6, 2017
Terminated, timeTERMINATION_TIME
1550
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
118
Current proposed assessmentAMOUNT_DUE
118
Amount paidAMOUNT_PAID
118
Bill first printedBILL_PRINT_DT
Jan 10, 2018
Final order dateFINAL_ORDER_ISSUE_DT
Feb 24, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jan 30, 2018

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Holt Farm
Operator IDVIOLATOR_ID
0148873
Controller IDCONTROLLER_ID
0130701
Inspection eventEVENT_NO
6739049
Inspection beganINSPECTION_BEGIN_DT
Dec 4, 2017
Inspection closed outINSPECTION_END_DT
Dec 6, 2017
Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

24 citations and orders since Dec 4, 2017: 24 issued to the operator, 0 to contractors working at the mine. Proposed penalty is MSHA's original proposed amount, before any change from a contested case. Citations can be contested, modified or vacated.

Penalties as assessed

Issued: Apr 8, 2026
Citation number: 5009164
Standard: 56.4201(a)(2)
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
5009164
Assessment control numberASSESS_CASE_NO
000642190
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Jul 4, 2026
Citation issuedISSUE_DT
Apr 8, 2026
Date of occurrenceOCCURRENCE_DT
Apr 8, 2026
Final order dateFINAL_ORDER_DT
Aug 3, 2026
Bill first printedBILL_PRINT_DT
Jun 4, 2026
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2026
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 3, 2026
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.4201(a)(2)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Mine Act interestMINEACT_INTEREST_AMT
2.12
Excessive late payment interestEXLATE_INTEREST_AMT
1.19

Penalty points

Violation history pointsPENALTY_POINTS
37
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
8139
Size of mineSIZE_OF_MINE
8139
Controller hours workedCONTROLLER_HRS
9603
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
9603
History period startHISTORY_START_DT
Jan 8, 2025
History period endHISTORY_END_DT
Apr 7, 2026

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F03A7D4
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 8, 2026
Citation number: 5009165
Standard: 41.12
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
5009165
Assessment control numberASSESS_CASE_NO
000642190
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Jul 4, 2026
Citation issuedISSUE_DT
Apr 8, 2026
Date of occurrenceOCCURRENCE_DT
Apr 8, 2026
Final order dateFINAL_ORDER_DT
Aug 3, 2026
Bill first printedBILL_PRINT_DT
Jun 4, 2026
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2026
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 3, 2026
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
41.12
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Mine Act interestMINEACT_INTEREST_AMT
2.12
Excessive late payment interestEXLATE_INTEREST_AMT
1.19

Penalty points

Violation history pointsPENALTY_POINTS
36
Negligence pointsNEGLIGENCE_POINTS
35
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
8139
Size of mineSIZE_OF_MINE
8139
Controller hours workedCONTROLLER_HRS
9603
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
9603
History period startHISTORY_START_DT
Jan 8, 2025
History period endHISTORY_END_DT
Apr 7, 2026

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F03A7D4
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (15)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 9, 2025
Citation number: 5009101
Standard: 50.30(a)
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
5009101
Assessment control numberASSESS_CASE_NO
000635361
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Feb 10, 2026
Citation issuedISSUE_DT
Dec 9, 2025
Date of occurrenceOCCURRENCE_DT
Dec 9, 2025
Final order dateFINAL_ORDER_DT
Mar 12, 2026
Bill first printedBILL_PRINT_DT
Feb 5, 2026
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2026
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 12, 2026
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Mine Act interestMINEACT_INTEREST_AMT
1.79

Penalty points

Violation history pointsPENALTY_POINTS
60
Negligence pointsNEGLIGENCE_POINTS
35
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
12
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
2.4
Operator hours worked at the mineVIOLATOR_MINE_HRS
4488
Size of mineSIZE_OF_MINE
4488
Controller hours workedCONTROLLER_HRS
7793
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
7793
History period startHISTORY_START_DT
Sep 9, 2024
History period endHISTORY_END_DT
Dec 8, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F022A2A
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (16)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 9, 2025
Citation number: 5009100
Standard: 56.12025
Proposed penalty: $165.00
Current assessment: $165.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
5009100
Assessment control numberASSESS_CASE_NO
000635361
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Feb 10, 2026
Citation issuedISSUE_DT
Dec 9, 2025
Date of occurrenceOCCURRENCE_DT
Dec 9, 2025
Final order dateFINAL_ORDER_DT
Mar 12, 2026
Bill first printedBILL_PRINT_DT
Feb 5, 2026
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2026
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 12, 2026
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12025
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
165.00
Current assessmentCURRENT_ASSESSMENT_AMT
165.00
Mine Act interestMINEACT_INTEREST_AMT
1.96

Penalty points

Violation history pointsPENALTY_POINTS
61
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
12
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
2.4
Operator hours worked at the mineVIOLATOR_MINE_HRS
4488
Size of mineSIZE_OF_MINE
4488
Controller hours workedCONTROLLER_HRS
7793
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
7793
History period startHISTORY_START_DT
Sep 9, 2024
History period endHISTORY_END_DT
Dec 8, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F022A2A
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 8, 2025
Citation number: 5009099
Standard: 56.14132(a)
Proposed penalty: $165.00
Current assessment: $165.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
5009099
Assessment control numberASSESS_CASE_NO
000635361
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Feb 10, 2026
Citation issuedISSUE_DT
Dec 8, 2025
Date of occurrenceOCCURRENCE_DT
Dec 8, 2025
Final order dateFINAL_ORDER_DT
Mar 12, 2026
Bill first printedBILL_PRINT_DT
Feb 5, 2026
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2026
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 12, 2026
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14132(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
165.00
Current assessmentCURRENT_ASSESSMENT_AMT
165.00
Mine Act interestMINEACT_INTEREST_AMT
1.96

Penalty points

Violation history pointsPENALTY_POINTS
61
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
12
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
2.4
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
1
Repeat violations per inspection dayRPID
0.2
Operator hours worked at the mineVIOLATOR_MINE_HRS
4488
Size of mineSIZE_OF_MINE
4488
Controller hours workedCONTROLLER_HRS
7793
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
7793
History period startHISTORY_START_DT
Sep 8, 2024
History period endHISTORY_END_DT
Dec 7, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F022A2A
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (11)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jan 29, 2025
Citation number: 5001010
Standard: 56.12018
Proposed penalty: $245.00
Current assessment: $245.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
5001010
Assessment control numberASSESS_CASE_NO
000617495
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Apr 14, 2025
Citation issuedISSUE_DT
Jan 29, 2025
Date of occurrenceOCCURRENCE_DT
Jan 29, 2025
Final order dateFINAL_ORDER_DT
May 14, 2025
Bill first printedBILL_PRINT_DT
Apr 3, 2025
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
May 14, 2025
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12018
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
245.00
Current assessmentCURRENT_ASSESSMENT_AMT
245.00
Mine Act interestMINEACT_INTEREST_AMT
2.57

Penalty points

Violation history pointsPENALTY_POINTS
66
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
15
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6
Violations per inspection dayVPID
2.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
4488
Size of mineSIZE_OF_MINE
4488
Controller hours workedCONTROLLER_HRS
7793
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
7793
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Jan 28, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F003536
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Sep 25, 2024
Citation number: 9791350
Standard: 62.110
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9791350
Assessment control numberASSESS_CASE_NO
000609227
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Nov 6, 2024
Citation issuedISSUE_DT
Sep 25, 2024
Date of occurrenceOCCURRENCE_DT
Sep 25, 2024
Final order dateFINAL_ORDER_DT
Dec 6, 2024
Bill first printedBILL_PRINT_DT
Oct 31, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 6, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
62.110
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
1.71

Penalty points

Violation history pointsPENALTY_POINTS
41
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Sep 24, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6938780
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (14)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Sep 25, 2024
Citation number: 9791349
Standard: 62.120
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9791349
Assessment control numberASSESS_CASE_NO
000609227
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Nov 6, 2024
Citation issuedISSUE_DT
Sep 25, 2024
Date of occurrenceOCCURRENCE_DT
Sep 25, 2024
Final order dateFINAL_ORDER_DT
Dec 6, 2024
Bill first printedBILL_PRINT_DT
Oct 31, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 6, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
62.120
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
1.71

Penalty points

Violation history pointsPENALTY_POINTS
41
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Sep 24, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6938780
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (14)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Sep 24, 2024
Citation number: 9791347
Standard: 56.14207
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9791347
Assessment control numberASSESS_CASE_NO
000609227
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Nov 6, 2024
Citation issuedISSUE_DT
Sep 24, 2024
Date of occurrenceOCCURRENCE_DT
Sep 24, 2024
Final order dateFINAL_ORDER_DT
Dec 6, 2024
Bill first printedBILL_PRINT_DT
Oct 31, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 6, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14207
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
1.71

Penalty points

Violation history pointsPENALTY_POINTS
41
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Sep 23, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6938780
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (14)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Sep 24, 2024
Citation number: 9791348
Standard: 56.14107(a)
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9791348
Assessment control numberASSESS_CASE_NO
000609227
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Nov 6, 2024
Citation issuedISSUE_DT
Sep 24, 2024
Date of occurrenceOCCURRENCE_DT
Sep 24, 2024
Final order dateFINAL_ORDER_DT
Dec 6, 2024
Bill first printedBILL_PRINT_DT
Oct 31, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 6, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14107(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
1.71

Penalty points

Violation history pointsPENALTY_POINTS
41
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Sep 23, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6938780
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (14)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 8, 2024
Citation number: 9795254
Standard: 56.14132(a)
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9795254
Assessment control numberASSESS_CASE_NO
000604068
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Oct 17, 2024
Citation issuedISSUE_DT
Jul 8, 2024
Date of occurrenceOCCURRENCE_DT
Jul 8, 2024
Final order dateFINAL_ORDER_DT
Nov 14, 2024
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Nov 14, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14132(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
2.41
Excessive late payment interestEXLATE_INTEREST_AMT
1.43

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1.33
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
1
Repeat violations per inspection dayRPID
0.333
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Jul 7, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F00555A
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (11)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 8, 2024
Citation number: 9795253
Standard: 56.14100(b)
Proposed penalty: $535.00
Current assessment: $535.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9795253
Assessment control numberASSESS_CASE_NO
000604068
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Oct 17, 2024
Citation issuedISSUE_DT
Jul 8, 2024
Date of occurrenceOCCURRENCE_DT
Jul 8, 2024
Final order dateFINAL_ORDER_DT
Nov 14, 2024
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Nov 14, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
535.00
Current assessmentCURRENT_ASSESSMENT_AMT
535.00
Mine Act interestMINEACT_INTEREST_AMT
8.79
Excessive late payment interestEXLATE_INTEREST_AMT
5.19

Penalty points

Violation history pointsPENALTY_POINTS
76
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Jul 7, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F00555A
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 8, 2024
Citation number: 9795259
Standard: 56.4101
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9795259
Assessment control numberASSESS_CASE_NO
000604068
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Oct 17, 2024
Citation issuedISSUE_DT
Jul 8, 2024
Date of occurrenceOCCURRENCE_DT
Jul 8, 2024
Final order dateFINAL_ORDER_DT
Nov 14, 2024
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Nov 14, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.4101
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
2.41
Excessive late payment interestEXLATE_INTEREST_AMT
1.43

Penalty points

Violation history pointsPENALTY_POINTS
41
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Jul 7, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F00555A
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 8, 2024
Citation number: 9795257
Standard: 56.14132(b)(1)(i)
Proposed penalty: $535.00
Current assessment: $535.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9795257
Assessment control numberASSESS_CASE_NO
000604068
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Oct 17, 2024
Citation issuedISSUE_DT
Jul 8, 2024
Date of occurrenceOCCURRENCE_DT
Jul 8, 2024
Final order dateFINAL_ORDER_DT
Nov 14, 2024
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Nov 14, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14132(b)(1)(i)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
535.00
Current assessmentCURRENT_ASSESSMENT_AMT
535.00
Mine Act interestMINEACT_INTEREST_AMT
8.79
Excessive late payment interestEXLATE_INTEREST_AMT
5.19

Penalty points

Violation history pointsPENALTY_POINTS
76
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Jul 7, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F00555A
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 8, 2024
Citation number: 9795255
Standard: 56.14132(b)(1)(i)
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9795255
Assessment control numberASSESS_CASE_NO
000604068
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Oct 17, 2024
Citation issuedISSUE_DT
Jul 8, 2024
Date of occurrenceOCCURRENCE_DT
Jul 8, 2024
Final order dateFINAL_ORDER_DT
Nov 14, 2024
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Nov 14, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14132(b)(1)(i)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
2.41
Excessive late payment interestEXLATE_INTEREST_AMT
1.43

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Jul 7, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F00555A
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 8, 2024
Citation number: 9795258
Standard: 56.14100(b)
Proposed penalty: $535.00
Current assessment: $535.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9795258
Assessment control numberASSESS_CASE_NO
000604068
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Oct 17, 2024
Citation issuedISSUE_DT
Jul 8, 2024
Date of occurrenceOCCURRENCE_DT
Jul 8, 2024
Final order dateFINAL_ORDER_DT
Nov 14, 2024
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Nov 14, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
535.00
Current assessmentCURRENT_ASSESSMENT_AMT
535.00
Mine Act interestMINEACT_INTEREST_AMT
8.79
Excessive late payment interestEXLATE_INTEREST_AMT
5.19

Penalty points

Violation history pointsPENALTY_POINTS
76
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Jul 7, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F00555A
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 8, 2024
Citation number: 9795256
Standard: 56.14130(i)
Proposed penalty: $1,188.00
Current assessment: $1,188.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9795256
Assessment control numberASSESS_CASE_NO
000604068
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Oct 17, 2024
Citation issuedISSUE_DT
Jul 8, 2024
Date of occurrenceOCCURRENCE_DT
Jul 8, 2024
Final order dateFINAL_ORDER_DT
Nov 14, 2024
Bill first printedBILL_PRINT_DT
Oct 3, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Nov 14, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14130(i)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
1188.00
Current assessmentCURRENT_ASSESSMENT_AMT
1188.00
Mine Act interestMINEACT_INTEREST_AMT
19.53
Excessive late payment interestEXLATE_INTEREST_AMT
11.52

Penalty points

Violation history pointsPENALTY_POINTS
86
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Jul 7, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F00555A
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Feb 6, 2024
Citation number: 9748068
Standard: 56.12028
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9748068
Assessment control numberASSESS_CASE_NO
000596575
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Apr 15, 2024
Citation issuedISSUE_DT
Feb 6, 2024
Date of occurrenceOCCURRENCE_DT
Feb 6, 2024
Final order dateFINAL_ORDER_DT
May 15, 2024
Bill first printedBILL_PRINT_DT
Apr 4, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2024
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
May 15, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12028
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
1.54

Penalty points

Violation history pointsPENALTY_POINTS
26
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Feb 5, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6937331
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (16)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Feb 6, 2024
Citation number: 9748069
Standard: 50.30(a)
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9748069
Assessment control numberASSESS_CASE_NO
000596575
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Apr 15, 2024
Citation issuedISSUE_DT
Feb 6, 2024
Date of occurrenceOCCURRENCE_DT
Feb 6, 2024
Final order dateFINAL_ORDER_DT
May 15, 2024
Bill first printedBILL_PRINT_DT
Apr 4, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2024
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
May 15, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
1.54

Penalty points

Violation history pointsPENALTY_POINTS
35
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Feb 5, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6937331
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (19)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Feb 5, 2024
Citation number: 9748067
Standard: 56.14132(a)
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9748067
Assessment control numberASSESS_CASE_NO
000596575
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Apr 15, 2024
Citation issuedISSUE_DT
Feb 5, 2024
Date of occurrenceOCCURRENCE_DT
Feb 5, 2024
Final order dateFINAL_ORDER_DT
May 15, 2024
Bill first printedBILL_PRINT_DT
Apr 4, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2024
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
May 15, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14132(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
1.54

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Feb 4, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6937331
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (17)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Feb 5, 2024
Citation number: 9748066
Standard: 56.12002
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9748066
Assessment control numberASSESS_CASE_NO
000596575
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Apr 15, 2024
Citation issuedISSUE_DT
Feb 5, 2024
Date of occurrenceOCCURRENCE_DT
Feb 5, 2024
Final order dateFINAL_ORDER_DT
May 15, 2024
Bill first printedBILL_PRINT_DT
Apr 4, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2024
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
May 15, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12002
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
1.54

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
160
Size of mineSIZE_OF_MINE
160
Controller hours workedCONTROLLER_HRS
2318
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2318
History period startHISTORY_START_DT
Dec 5, 2023
History period endHISTORY_END_DT
Feb 4, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Rainbow Stone Company
IDVIOLATOR_ID
0119849
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 5, 2023
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6937331
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (17)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 4, 2023
Citation number: 9743733
Standard: 46.5(b)
Proposed penalty: $397.00
Current assessment: $397.00
Paid against proposed penalty: $397.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9743733
Assessment control numberASSESS_CASE_NO
000593710
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 7, 2024
Citation issuedISSUE_DT
Dec 4, 2023
Date of occurrenceOCCURRENCE_DT
Dec 4, 2023
Final order dateFINAL_ORDER_DT
Mar 13, 2024
Bill first printedBILL_PRINT_DT
Feb 7, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2024
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 13, 2024
Citation typeCITATION_TYPE_CD
Order
30 CFR standardCFR_STANDARD_CD
46.5(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(g)(1)
Significant and substantialSIG_SUB_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
397.00
Current assessmentCURRENT_ASSESSMENT_AMT
397.00
Mine Act interestMINEACT_INTEREST_AMT
4.70
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
397.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
4.70

Penalty points

Violation history pointsPENALTY_POINTS
71
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

History period startHISTORY_START_DT
Sep 4, 2022
History period endHISTORY_END_DT
Dec 3, 2023

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Holt Farm
IDVIOLATOR_ID
0148873
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 22, 2016
Operator end at the mine, as assessedVIOLATOR_END_DT
Dec 4, 2023
Inspection eventEVENT_NBR
6935746
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (19)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator hours worked at the mineVIOLATOR_MINE_HRS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Size of mineSIZE_OF_MINE, Controller hours workedCONTROLLER_HRS, Controller tonnageCONTROLLER_PRODUCTION_AMT, Size of controlling entitySIZE_OF_CONTROLLING_ENTITY

Recorded as N (2)

Good faith reduction appliedGOOD_FAITH_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 4, 2023
Citation number: 9743732
Standard: 56.1000
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $147.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9743732
Assessment control numberASSESS_CASE_NO
000593710
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 7, 2024
Citation issuedISSUE_DT
Dec 4, 2023
Date of occurrenceOCCURRENCE_DT
Dec 4, 2023
Final order dateFINAL_ORDER_DT
Mar 13, 2024
Bill first printedBILL_PRINT_DT
Feb 7, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2024
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 13, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.1000
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
1.74
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
147.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
1.74

Penalty points

Violation history pointsPENALTY_POINTS
35
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

History period startHISTORY_START_DT
Sep 4, 2022
History period endHISTORY_END_DT
Dec 3, 2023

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Holt Farm
IDVIOLATOR_ID
0148873
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 22, 2016
Operator end at the mine, as assessedVIOLATOR_END_DT
Dec 4, 2023
Inspection eventEVENT_NBR
6935746
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (22)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator hours worked at the mineVIOLATOR_MINE_HRS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Size of mineSIZE_OF_MINE, Controller hours workedCONTROLLER_HRS, Controller tonnageCONTROLLER_PRODUCTION_AMT, Size of controlling entitySIZE_OF_CONTROLLING_ENTITY

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 4, 2017
Citation number: 9354487
Standard: 56.15001
Proposed penalty: $118.00
Current assessment: $118.00
Paid against proposed penalty: $118.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9354487
Assessment control numberASSESS_CASE_NO
000456274
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jan 30, 2018
Citation issuedISSUE_DT
Dec 4, 2017
Date of occurrenceOCCURRENCE_DT
Dec 4, 2017
Final order dateFINAL_ORDER_DT
Feb 24, 2018
Bill first printedBILL_PRINT_DT
Jan 10, 2018
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.15001
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
118.00
Current assessmentCURRENT_ASSESSMENT_AMT
118.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
118.00

Penalty points

Violation history pointsPENALTY_POINTS
26
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
60
Size of mineSIZE_OF_MINE
60
Controller hours workedCONTROLLER_HRS
60
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
60
History period startHISTORY_START_DT
Dec 22, 2016
History period endHISTORY_END_DT
Dec 3, 2017

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Holt Farm
IDVIOLATOR_ID
0148873
Operator start at the mine, as assessedVIOLATOR_START_DT
Dec 22, 2016
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6739049
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (17)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

24 assessed citations and orders. Amounts are MSHA's per-citation values; case status is MSHA's own (Closed, Invalid, Printed or Received).

Employment and hours worked

Year: 2026
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 1,557
Details

The report

YearCALENDAR_YR
2026
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
1557
Average hours per employeeAVG_EMPLOYEE_HOURS
1557

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2026
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 4
Hours worked: 5,080
Details

The report

YearCALENDAR_YR
2026
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
4
Hours workedANNUAL_HRS
5080
Average hours per employeeAVG_EMPLOYEE_HOURS
1270

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2025
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 3,197
Details

The report

YearCALENDAR_YR
2025
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
3197
Average hours per employeeAVG_EMPLOYEE_HOURS
3197

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2025
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 4
Hours worked: 8,139
Details

The report

YearCALENDAR_YR
2025
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
4
Hours workedANNUAL_HRS
8139
Average hours per employeeAVG_EMPLOYEE_HOURS
2035

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2024
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 1,642
Details

The report

YearCALENDAR_YR
2024
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
1642
Average hours per employeeAVG_EMPLOYEE_HOURS
1642

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2024
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 4
Hours worked: 4,488
Details

The report

YearCALENDAR_YR
2024
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
4
Hours workedANNUAL_HRS
4488
Average hours per employeeAVG_EMPLOYEE_HOURS
1122

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2023
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 20
Details

The report

YearCALENDAR_YR
2023
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
20
Average hours per employeeAVG_EMPLOYEE_HOURS
20

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2023
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 2
Hours worked: 40
Details

The report

YearCALENDAR_YR
2023
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
2
Hours workedANNUAL_HRS
40
Average hours per employeeAVG_EMPLOYEE_HOURS
20

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2020
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 3
Details

The report

YearCALENDAR_YR
2020
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
3
Average hours per employeeAVG_EMPLOYEE_HOURS
3

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2020
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 2
Hours worked: 60
Details

The report

YearCALENDAR_YR
2020
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
2
Hours workedANNUAL_HRS
60
Average hours per employeeAVG_EMPLOYEE_HOURS
30

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2019
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 5
Details

The report

YearCALENDAR_YR
2019
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
5
Average hours per employeeAVG_EMPLOYEE_HOURS
5

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2019
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 1
Hours worked: 16
Details

The report

YearCALENDAR_YR
2019
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
16
Average hours per employeeAVG_EMPLOYEE_HOURS
16

Mine

Mine IDMINE_ID
0302058
Mine name in this fileCURR_MINE_NM
Holt Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

What the operator reported to MSHA for the 6 most recent years, one row per part of the mine, as MSHA files them. Rows are not added together.

Mine details

MSHA field office
Little Rock AR Field Office
Nearest town
Ozark
Days worked per week
5
Hours per shift
8
Production shifts per day
1
Maintenance shifts per day
0
Employees, current record
2
Tailing ponds
0
103(i) spot inspection status
Never Had 103I Status
Safety committee
N
Portable operation
N
Every field in MSHA's mine record

The mine

Mine nameCURRENT_MINE_NAME
Holt Quarry
Mine IDMINE_ID
0302058
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Mine typeCURRENT_MINE_TYPE
Surface
Current statusCURRENT_MINE_STATUS
Active
Status sinceCURRENT_STATUS_DT
Dec 5, 2023
Legal entity typeCOMPANY_TYPE
Corporation

Operator and controller

OperatorCURRENT_OPERATOR_NAME
Rainbow Stone Company
Operator IDCURRENT_OPERATOR_ID
0119849
Controller IDCURRENT_CONTROLLER_ID
0101845
Start of the operating periodCURRENT_CONTROLLER_BEGIN_DT
Dec 5, 2023

Location and MSHA office

StateSTATE
AR
Bureau of Mines state codeBOM_STATE_CD
03
FIPS county codeFIPS_CNTY_CD
047
FIPS county nameFIPS_CNTY_NM
Franklin
Nearest townNEAREST_TOWN
Ozark
MSHA districtDISTRICT
M5
MSHA office codeOFFICE_CD
M5871
MSHA officeOFFICE_NAME
Little Rock AR Field Office
Driving miles from the MSHA officeMILES_FROM_OFFICE
122
Most recent assessment control numberASSESS_CTRL_NO
000642190

Commodity

Primary commodity (SIC)PRIMARY_SIC
Dimension Stone NEC
Primary commodity codePRIMARY_SIC_CD
141100
Primary SIC codePRIMARY_SIC_CD_1
1411
Primary SIC suffixPRIMARY_SIC_CD_SFX
00
Primary industry groupPRIMARY_CANVASS
Stone
Primary industry group codePRIMARY_CANVASS_CD
6

Operations, from the Mine Information Form

Days operating per weekDAYS_PER_WEEK
5
Hours per shiftHOURS_PER_SHIFT
8
Production shifts per dayPROD_SHIFTS_PER_DAY
1
Workers employedNO_EMPLOYEES
2
MSHA restricted from enforcing Part 48 trainingPART48_TRAINING
Y
103(i) statusCURRENT_103I
Never Had 103I Status

Recorded as 0 (2)

Maintenance-only shifts per dayMAINT_SHIFTS_PER_DAY, Tailing pondsNO_TAILING_PONDS

Recorded as N (5)

Portable minePORTABLE_OPERATION, Pillar recovery usedPILLAR_RECOVERY_USED, Highwall miner usedHIGHWALL_MINER_USED, Multiple pitsMULTIPLE_PITS, Safety committeeSAFETY_COMMITTEE_IND

Not recorded by MSHA (15)

Portable mine FIPS state codePORTABLE_FIPS_ST_CD, ControllerCURRENT_CONTROLLER_NAME, Congressional districtCONG_DIST_CD, Secondary commodity (SIC)SECONDARY_SIC, Secondary commodity codeSECONDARY_SIC_CD, Secondary SIC codeSECONDARY_SIC_CD_1, Secondary SIC suffixSECONDARY_SIC_CD_SFX, Secondary industry groupSECONDARY_CANVASS, Secondary industry group codeSECONDARY_CANVASS_CD, Average mining height, inchesAVG_MINE_HEIGHT, Mine gas categoryMINE_GAS_CATEGORY_CD, Methane liberation, cu ft per 24 hMETHANE_LIBERATION, Producing pitsNO_PRODUCING_PITS, Non-producing pitsNO_NONPRODUCING_PITS, 103(i) status sinceCURRENT_103I_DT

Operator and controller history

Operator: Rainbow Stone Company
From: Dec 5, 2023
To: No end date
Controller: Not shown
From : Sep 14, 2011
To : No end date
Details

Operator

OperatorOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Operator fromOPERATOR_START_DT
Dec 5, 2023

Controller

Controller IDCONTROLLER_ID
0101845
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Sep 14, 2011

Mine

Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine status at this pointMINE_STATUS
Active
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (3)

Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

Operator: Rainbow Stone Company
From: Dec 5, 2023
To: No end date
Controller: Not shown
From : Sep 14, 2011
To : No end date
Details

Operator

OperatorOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Operator fromOPERATOR_START_DT
Dec 5, 2023

Controller

Controller IDCONTROLLER_ID
0101845
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Sep 14, 2011

Mine

Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine status at this pointMINE_STATUS
Active
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (3)

Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

Operator: Rainbow Stone Company
From: Dec 5, 2023
To: No end date
Controller: Not shown
From : Sep 14, 2011
To : No end date
Details

Operator

OperatorOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Operator fromOPERATOR_START_DT
Dec 5, 2023

Controller

Controller IDCONTROLLER_ID
0101845
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Sep 14, 2011

Mine

Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine status at this pointMINE_STATUS
Active
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (3)

Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

Operator: Rainbow Stone Company
From: Dec 5, 2023
To: No end date
Controller: Not shown
From : Sep 14, 2011
To : No end date
Details

Operator

OperatorOPERATOR_NAME
Rainbow Stone Company
Operator IDOPERATOR_ID
0119849
Operator fromOPERATOR_START_DT
Dec 5, 2023

Controller

Controller IDCONTROLLER_ID
0101845
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Sep 14, 2011

Mine

Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine status at this pointMINE_STATUS
Active
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (3)

Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

Operator: Holt Farm
From: Dec 22, 2016
To: Dec 4, 2023
Controller: Not shown
From : Dec 22, 2016
To : No end date
Details

Operator

OperatorOPERATOR_NAME
Holt Farm
Operator IDOPERATOR_ID
0148873
Operator fromOPERATOR_START_DT
Dec 22, 2016
Operator toOPERATOR_END_DT
Dec 4, 2023

Controller

Controller IDCONTROLLER_ID
0130701
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Dec 22, 2016

Mine

Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Mine status at this pointMINE_STATUS
Active
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (2)

ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

As MSHA records it, newest operator first.

Address of record

Rainbow Stone Company·Contact title Owner/Operator·Street not recorded, Subiaco AR 72865

MSHA says an address of record "does not represent the actual mine location."

Every field in the address record

Address

Business nameBUSINESS_NAME
Rainbow Stone Company
Contact titleCONTACT_TITLE
Owner/Operator
CityCITY
Subiaco
StateSTATE_ABBR
AR
State nameSTATE
Arkansas
ZIP codeZIP_CD
72865
CountryCOUNTRY
USA
FIPS state codeFIPS_STATE_CD
05

Mine

Mine IDMINE_ID
0302058
Mine name in this fileMINE_NAME
Holt Quarry
Nearest townNEAREST_TOWN
Ozark
Mine typeMINE_TYPE_CD
Surface
Mine statusMINE_STATUS
Active
Status sinceMINE_STATUS_DT
Dec 5, 2023
Primary commodity (SIC)PRIMARY_SIC_CD
Dimension Stone NEC
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (4)

StreetSTREET, PO boxPO_BOX, ProvincePROVINCE, Foreign postal codePOSTAL_CD

Sources. MSHA open government data files: Mines, Inspections, Violations, AssessedViolations, ContestedViolations, 107(a)OrdersIssued, Accidents, MinesProdYearly, ControllerOperatorHistory, AddressOfRecord. Field labels are shortened from MSHA's definition files, with MSHA's column name beside each. MSHA Mine Data Retrieval System·MSHA fatality report search·MSHA open government data

These are U.S. Department of Labor, Mine Safety and Health Administration records, reproduced as published. Citations can be contested, modified or vacated, and records that are contested or not yet final are included. SafetyRecord.org is not a consumer reporting agency. MSHA records as of Nov 6, 2026. Data and methodology