Metal/Non-Metal, SurfaceConstruction Sand and GravelFairbanks North Star, AlaskaMine ID 5001662

Operator H C Redi-Mix LLCController not shownMSHA status Intermittent since Jun 9, 2003

What MSHA has on file for this mine

Citations and orders
90
since Aug 17, 2000 · 90 to the operator, 0 to contractors · 30 marked S&S
Imminent danger orders, section 107(a)
None on record
MSHA's list starts July 1, 2010
Yearly employment and hours
8 years
one row per part of the mine

MSHA records as of Nov 6, 2026. Having MSHA inspection records is common for operating mines. Data and methodology

Inspections

Regular Safety and Health Inspection
Jun 24 to Jun 25, 2026Inspectors 1 | Hours on site 4.5

The inspection

BeganINSPECTION_BEGIN_DT
Jun 24, 2026
Closed outINSPECTION_END_DT
Jun 25, 2026
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F0399E7
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
10.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2026
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 9 to Jun 10, 2025Inspectors 1 | Hours on site 3

The inspection

BeganINSPECTION_BEGIN_DT
Jun 9, 2025
Closed outINSPECTION_END_DT
Jun 10, 2025
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F01A045
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3
Total inspection hoursSUM_TOTAL_INSP_HOURS
5.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 5 to Jun 6, 2024Inspectors 1 | Hours on site 3

The inspection

BeganINSPECTION_BEGIN_DT
Jun 5, 2024
Closed outINSPECTION_END_DT
Jun 6, 2024
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6876596
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3
Total inspection hoursSUM_TOTAL_INSP_HOURS
11

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Oct 6, 2022Inspectors 1 | Hours on site 3

The inspection

BeganINSPECTION_BEGIN_DT
Oct 6, 2022
Closed outINSPECTION_END_DT
Oct 6, 2022
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1124194
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3
Total inspection hoursSUM_TOTAL_INSP_HOURS
15

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jul 28, 2022Inspectors 1 | Hours on site 5.5

The inspection

BeganINSPECTION_BEGIN_DT
Jul 28, 2022
Closed outINSPECTION_END_DT
Jul 28, 2022
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6876216
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
5.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
10.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Oct 9, 2020Inspectors 1 | Hours on site 4

The inspection

BeganINSPECTION_BEGIN_DT
Oct 9, 2020
Closed outINSPECTION_END_DT
Oct 9, 2020
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1153995
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4
Total inspection hoursSUM_TOTAL_INSP_HOURS
9

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 29, 2020Inspectors 1 | Hours on site 8

The inspection

BeganINSPECTION_BEGIN_DT
Jun 29, 2020
Closed outINSPECTION_END_DT
Jun 29, 2020
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1146673
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
8
Total inspection hoursSUM_TOTAL_INSP_HOURS
11

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 3, 2019Inspectors 1 | Hours on site 2.75

The inspection

BeganINSPECTION_BEGIN_DT
Jun 3, 2019
Closed outINSPECTION_END_DT
Jun 3, 2019
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1146491
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
2.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
5.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2019
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Oct 3, 2017Inspectors 1 | Hours on site 3.5

The inspection

BeganINSPECTION_BEGIN_DT
Oct 3, 2017
Closed outINSPECTION_END_DT
Oct 3, 2017
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1146249
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
15.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
May 12 to May 15, 2017Inspectors 1 | Hours on site 10.5

The inspection

BeganINSPECTION_BEGIN_DT
May 12, 2017
Closed outINSPECTION_END_DT
May 15, 2017
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1153758
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
10.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
22.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Sep 9 to Oct 1, 2015Inspectors 1 | Hours on site 13.75

The inspection

BeganINSPECTION_BEGIN_DT
Sep 9, 2015
Closed outINSPECTION_END_DT
Oct 1, 2015
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6663816
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
13.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Sep 16 to Oct 1, 2014Inspectors 1 | Hours on site 10.5

The inspection

BeganINSPECTION_BEGIN_DT
Sep 16, 2014
Closed outINSPECTION_END_DT
Oct 1, 2014
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1157993
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
10.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
29.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2014
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jul 16, 2014Inspectors 1 | Hours on site 4

The inspection

BeganINSPECTION_BEGIN_DT
Jul 16, 2014
Closed outINSPECTION_END_DT
Jul 16, 2014
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6656217
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4
Total inspection hoursSUM_TOTAL_INSP_HOURS
6

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2014
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Non-Injury Accident Investigation
Nov 7 to Nov 14, 2013Inspectors 1 | Hours on site 6.5

The inspection

BeganINSPECTION_BEGIN_DT
Nov 7, 2013
Closed outINSPECTION_END_DT
Nov 14, 2013
ActivityACTIVITY
Non-Injury Accident Investigation
Activity codeACTIVITY_CODE
E08
Program areaPROGRAM_AREA
M/NM--Non-Injury Accident Investigation
Event numberEVENT_NO
1140446
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
6.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
29

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2013
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 21 to Jun 24, 2013Inspectors 1 | Hours on site 4.5

The inspection

BeganINSPECTION_BEGIN_DT
Jun 21, 2013
Closed outINSPECTION_END_DT
Jun 24, 2013
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1146074
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
12.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2013
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2013
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jul 27 to Jul 28, 2012Inspectors 1 | Hours on site 7

The inspection

BeganINSPECTION_BEGIN_DT
Jul 27, 2012
Closed outINSPECTION_END_DT
Jul 28, 2012
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1153432
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
7
Total inspection hoursSUM_TOTAL_INSP_HOURS
15

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2012
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2012
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 4 to Jun 6, 2011Inspectors 1 | Hours on site 4.25

The inspection

BeganINSPECTION_BEGIN_DT
Jun 4, 2011
Closed outINSPECTION_END_DT
Jun 6, 2011
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1140879
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
7

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2011
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2011
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 11 to Jun 12, 2010Inspectors 1 | Hours on site 8.25

The inspection

BeganINSPECTION_BEGIN_DT
Jun 11, 2010
Closed outINSPECTION_END_DT
Jun 12, 2010
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1140941
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
8.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
31.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2010
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2010
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 22 to Jun 23, 2009Inspectors 1 | Hours on site 7.75

The inspection

BeganINSPECTION_BEGIN_DT
Jun 22, 2009
Closed outINSPECTION_END_DT
Jun 23, 2009
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1140587
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
7.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
12.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2009
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2009
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 10 to Jun 11, 2008Inspectors 1 | Hours on site 10

The inspection

BeganINSPECTION_BEGIN_DT
Jun 10, 2008
Closed outINSPECTION_END_DT
Jun 11, 2008
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1140331
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
10
Total inspection hoursSUM_TOTAL_INSP_HOURS
19.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2008
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2008
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Aug 27 to Aug 28, 2007Inspectors 1 | Hours on site 22

The inspection

BeganINSPECTION_BEGIN_DT
Aug 27, 2007
Closed outINSPECTION_END_DT
Aug 28, 2007
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1124896
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
22
Total inspection hoursSUM_TOTAL_INSP_HOURS
23.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2007
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2007
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

103 (g) Written Notification Hazard Complaint Inspectio
May 30 to Jun 2, 2006Inspectors 0 | Hours on site 0

The inspection

BeganINSPECTION_BEGIN_DT
May 30, 2006
Closed outINSPECTION_END_DT
Jun 2, 2006
ActivityACTIVITY
103 (g) Written Notification Hazard Complaint Inspectio
Activity codeACTIVITY_CODE
E03
Program areaPROGRAM_AREA
M/NM--103 (g) Written Notification Hazard Complaint Inspecti
Event numberEVENT_NO
1124671
Inspector's office codeINSPECT_OFFICE_CD
M7861

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2006
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2006
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (16)

InspectorsNBR_INSPECTOR, Hours on siteSUM_TOTAL_ON_SITE_HOURS, Total inspection hoursSUM_TOTAL_INSP_HOURS, Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Part 50 Audit
Aug 12, 2005Inspectors 1 | Hours on site 3

The inspection

BeganINSPECTION_BEGIN_DT
Aug 12, 2005
Closed outINSPECTION_END_DT
Aug 12, 2005
ActivityACTIVITY
Part 50 Audit
Activity codeACTIVITY_CODE
E25
Program areaPROGRAM_AREA
M/NM--Part 50 Audit
Event numberEVENT_NO
1124273
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3
Total inspection hoursSUM_TOTAL_INSP_HOURS
4.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2005
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2005
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jul 8 to Jul 11, 2005Inspectors 1 | Hours on site 11.25

The inspection

BeganINSPECTION_BEGIN_DT
Jul 8, 2005
Closed outINSPECTION_END_DT
Jul 11, 2005
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1124258
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
11.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
13.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2005
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2005
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

MISCELLANEOUS INSPECTION/INVESTIGATION
Jul 15 to Jul 16, 2004Inspectors 1 | Hours on site 7

The inspection

BeganINSPECTION_BEGIN_DT
Jul 15, 2004
Closed outINSPECTION_END_DT
Jul 16, 2004
ActivityACTIVITY
MISCELLANEOUS INSPECTION/INVESTIGATION
Activity codeACTIVITY_CODE
37
Program areaPROGRAM_AREA
M/NM--MISCELLANEOUS INSPECTION/INVESTIGATION
Event numberEVENT_NO
1124001
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7861
Hours on siteSUM_TOTAL_ON_SITE_HOURS
7
Total inspection hoursSUM_TOTAL_INSP_HOURS
12

Who and when, as recorded

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Calendar yearCAL_YR
2004
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2004
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

25 most recent of 30 inspections and other MSHA visits since Aug 15, 2000; activity names are MSHA's own text. Full list: MSHA Mine Data Retrieval System.

Citations and orders

Issued: Jun 5, 2024
Type: Citation
Standard: 56.14112(b)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9687815
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 5, 2024
Time issuedVIOLATION_ISSUE_TIME
1405
Date of occurrenceVIOLATION_OCCUR_DT
Jun 5, 2024
30 CFR part and sectionPART_SECTION
56.14112(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 5, 2024
Originally due, timeORIG_TERM_DUE_TIME
1700
Latest dueLATEST_TERM_DUE_DT
Jun 5, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1700
TerminatedTERMINATION_DT
Jun 5, 2024
Terminated, timeTERMINATION_TIME
1455
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Amount paidAMOUNT_PAID
147
Bill first printedBILL_PRINT_DT
Oct 2, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Dec 3, 2024
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Feb 19, 2025

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6876596
Inspection beganINSPECTION_BEGIN_DT
Jun 5, 2024
Inspection closed outINSPECTION_END_DT
Jun 6, 2024
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jun 5, 2024
Type: Citation
Standard: 56.4201(a)(2)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9687817
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 5, 2024
Time issuedVIOLATION_ISSUE_TIME
1500
Date of occurrenceVIOLATION_OCCUR_DT
Jun 5, 2024
30 CFR part and sectionPART_SECTION
56.4201(a)(2)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 6, 2024
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
Jun 6, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
Jun 6, 2024
Terminated, timeTERMINATION_TIME
0730
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Amount paidAMOUNT_PAID
147
Bill first printedBILL_PRINT_DT
Oct 2, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Dec 3, 2024
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Feb 19, 2025

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6876596
Inspection beganINSPECTION_BEGIN_DT
Jun 5, 2024
Inspection closed outINSPECTION_END_DT
Jun 6, 2024
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jun 5, 2024
Type: Citation
Standard: 56.14130(g)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9687816
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 5, 2024
Time issuedVIOLATION_ISSUE_TIME
1340
Date of occurrenceVIOLATION_OCCUR_DT
Jun 5, 2024
30 CFR part and sectionPART_SECTION
56.14130(g)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 5, 2024
Originally due, timeORIG_TERM_DUE_TIME
1350
Latest dueLATEST_TERM_DUE_DT
Jun 5, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1350
TerminatedTERMINATION_DT
Jun 5, 2024
Terminated, timeTERMINATION_TIME
1345
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Amount paidAMOUNT_PAID
147
Bill first printedBILL_PRINT_DT
Oct 2, 2024
Final order dateFINAL_ORDER_ISSUE_DT
Dec 3, 2024
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Feb 19, 2025

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6876596
Inspection beganINSPECTION_BEGIN_DT
Jun 5, 2024
Inspection closed outINSPECTION_END_DT
Jun 6, 2024
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Oct 6, 2022
Type: Citation
Standard: 56.4201(b)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9615977
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Oct 6, 2022
Time issuedVIOLATION_ISSUE_TIME
1130
Date of occurrenceVIOLATION_OCCUR_DT
Oct 6, 2022
30 CFR part and sectionPART_SECTION
56.4201(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 6, 2022
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
Oct 6, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
Oct 6, 2022
Terminated, timeTERMINATION_TIME
1145
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Amount paidAMOUNT_PAID
133
Bill first printedBILL_PRINT_DT
Nov 30, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Jan 12, 2023
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Dec 28, 2022
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1124194
Inspection beganINSPECTION_BEGIN_DT
Oct 6, 2022
Inspection closed outINSPECTION_END_DT
Oct 6, 2022
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (1)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 28, 2022
Type: Citation
Standard: 56.12006
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9615234
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 28, 2022
Time issuedVIOLATION_ISSUE_TIME
1538
Date of occurrenceVIOLATION_OCCUR_DT
Jul 28, 2022
30 CFR part and sectionPART_SECTION
56.12006
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 28, 2022
Originally due, timeORIG_TERM_DUE_TIME
1700
Latest dueLATEST_TERM_DUE_DT
Jul 28, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1700
TerminatedTERMINATION_DT
Jul 28, 2022
Terminated, timeTERMINATION_TIME
1638
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Amount paidAMOUNT_PAID
133
Bill first printedBILL_PRINT_DT
Aug 31, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Oct 13, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 29, 2022

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6876216
Inspection beganINSPECTION_BEGIN_DT
Jul 28, 2022
Inspection closed outINSPECTION_END_DT
Jul 28, 2022
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 28, 2022
Type: Citation
Standard: 56.12032
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9615233
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 28, 2022
Time issuedVIOLATION_ISSUE_TIME
1536
Date of occurrenceVIOLATION_OCCUR_DT
Jul 28, 2022
30 CFR part and sectionPART_SECTION
56.12032
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Aug 2, 2022
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
Aug 2, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
Aug 1, 2022
Terminated, timeTERMINATION_TIME
0858
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Amount paidAMOUNT_PAID
133
Bill first printedBILL_PRINT_DT
Aug 31, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Oct 13, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 29, 2022

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6876216
Inspection beganINSPECTION_BEGIN_DT
Jul 28, 2022
Inspection closed outINSPECTION_END_DT
Jul 28, 2022
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Oct 9, 2020
Type: Citation
Standard: 56.14206(b)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $123.00
Details

The citation

Citation or order numberVIOLATION_NO
6392548
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Oct 9, 2020
Time issuedVIOLATION_ISSUE_TIME
1023
Date of occurrenceVIOLATION_OCCUR_DT
Oct 9, 2020
30 CFR part and sectionPART_SECTION
56.14206(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 9, 2020
Originally due, timeORIG_TERM_DUE_TIME
1030
Latest dueLATEST_TERM_DUE_DT
Oct 9, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1030
TerminatedTERMINATION_DT
Oct 9, 2020
Terminated, timeTERMINATION_TIME
1328
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
123
Current proposed assessmentAMOUNT_DUE
123
Amount paidAMOUNT_PAID
123
Bill first printedBILL_PRINT_DT
Dec 2, 2020
Final order dateFINAL_ORDER_ISSUE_DT
Jan 17, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jan 5, 2021
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1153995
Inspection beganINSPECTION_BEGIN_DT
Oct 9, 2020
Inspection closed outINSPECTION_END_DT
Oct 9, 2020
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
1

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jun 29, 2020
Type: Citation
Standard: 46.3(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $123.00
Details

The citation

Citation or order numberVIOLATION_NO
9435852
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 29, 2020
Time issuedVIOLATION_ISSUE_TIME
1230
Date of occurrenceVIOLATION_OCCUR_DT
Jun 29, 2020
30 CFR part and sectionPART_SECTION
46.3(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 10, 2020
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
Aug 28, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
Aug 7, 2020
Terminated, timeTERMINATION_TIME
0520
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
123
Current proposed assessmentAMOUNT_DUE
123
Amount paidAMOUNT_PAID
123
Bill first printedBILL_PRINT_DT
Sep 2, 2020
Final order dateFINAL_ORDER_ISSUE_DT
Oct 12, 2020
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 24, 2020
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1146673
Inspection beganINSPECTION_BEGIN_DT
Jun 29, 2020
Inspection closed outINSPECTION_END_DT
Jun 29, 2020
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jun 29, 2020
Type: Citation
Standard: 56.12004
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $123.00
Details

The citation

Citation or order numberVIOLATION_NO
9435851
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 29, 2020
Time issuedVIOLATION_ISSUE_TIME
0959
Date of occurrenceVIOLATION_OCCUR_DT
Jun 29, 2020
30 CFR part and sectionPART_SECTION
56.12004
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 29, 2020
Originally due, timeORIG_TERM_DUE_TIME
1100
Latest dueLATEST_TERM_DUE_DT
Jun 29, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1100
TerminatedTERMINATION_DT
Jun 29, 2020
Terminated, timeTERMINATION_TIME
1000
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
123
Current proposed assessmentAMOUNT_DUE
123
Amount paidAMOUNT_PAID
123
Bill first printedBILL_PRINT_DT
Sep 2, 2020
Final order dateFINAL_ORDER_ISSUE_DT
Oct 12, 2020
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 24, 2020
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1146673
Inspection beganINSPECTION_BEGIN_DT
Jun 29, 2020
Inspection closed outINSPECTION_END_DT
Jun 29, 2020
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jun 29, 2020
Type: Citation
Standard: 56.12008
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $123.00
Details

The citation

Citation or order numberVIOLATION_NO
9435850
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 29, 2020
Time issuedVIOLATION_ISSUE_TIME
0910
Date of occurrenceVIOLATION_OCCUR_DT
Jun 29, 2020
30 CFR part and sectionPART_SECTION
56.12008
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 29, 2020
Originally due, timeORIG_TERM_DUE_TIME
1700
Latest dueLATEST_TERM_DUE_DT
Jun 29, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1700
TerminatedTERMINATION_DT
Jun 29, 2020
Terminated, timeTERMINATION_TIME
1654
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
123
Current proposed assessmentAMOUNT_DUE
123
Amount paidAMOUNT_PAID
123
Bill first printedBILL_PRINT_DT
Sep 2, 2020
Final order dateFINAL_ORDER_ISSUE_DT
Oct 12, 2020
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 24, 2020
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1146673
Inspection beganINSPECTION_BEGIN_DT
Jun 29, 2020
Inspection closed outINSPECTION_END_DT
Jun 29, 2020
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jun 3, 2019
Type: Citation
Standard: 56.12008
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $121.00
Details

The citation

Citation or order numberVIOLATION_NO
6392998
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 3, 2019
Time issuedVIOLATION_ISSUE_TIME
1245
Date of occurrenceVIOLATION_OCCUR_DT
Jun 3, 2019
30 CFR part and sectionPART_SECTION
56.12008
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 3, 2019
Originally due, timeORIG_TERM_DUE_TIME
1400
Latest dueLATEST_TERM_DUE_DT
Jun 3, 2019
Latest due, timeLATEST_TERM_DUE_TIME
1400
TerminatedTERMINATION_DT
Jun 3, 2019
Terminated, timeTERMINATION_TIME
1300
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
121
Current proposed assessmentAMOUNT_DUE
121
Amount paidAMOUNT_PAID
121
Bill first printedBILL_PRINT_DT
Jul 31, 2019
Final order dateFINAL_ORDER_ISSUE_DT
Sep 6, 2019
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Aug 20, 2019

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1146491
Inspection beganINSPECTION_BEGIN_DT
Jun 3, 2019
Inspection closed outINSPECTION_END_DT
Jun 3, 2019
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2019
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Oct 3, 2017
Type: Citation
Standard: 56.20003(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $116.00
Details

The citation

Citation or order numberVIOLATION_NO
6392934
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Oct 3, 2017
Time issuedVIOLATION_ISSUE_TIME
0944
Date of occurrenceVIOLATION_OCCUR_DT
Oct 3, 2017
30 CFR part and sectionPART_SECTION
56.20003(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 3, 2017
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Oct 3, 2017
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Oct 3, 2017
Terminated, timeTERMINATION_TIME
1159
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
116
Current proposed assessmentAMOUNT_DUE
116
Amount paidAMOUNT_PAID
116
Bill first printedBILL_PRINT_DT
Nov 29, 2017
Final order dateFINAL_ORDER_ISSUE_DT
Jan 29, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Dec 31, 2017
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1146249
Inspection beganINSPECTION_BEGIN_DT
Oct 3, 2017
Inspection closed outINSPECTION_END_DT
Oct 3, 2017
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
1

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: May 12, 2017
Type: Citation
Standard: 56.16005
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $116.00
Details

The citation

Citation or order numberVIOLATION_NO
8601781
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
May 12, 2017
Time issuedVIOLATION_ISSUE_TIME
1302
Date of occurrenceVIOLATION_OCCUR_DT
May 12, 2017
30 CFR part and sectionPART_SECTION
56.16005
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
May 13, 2017
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
May 13, 2017
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
May 12, 2017
Terminated, timeTERMINATION_TIME
1503
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
116
Current proposed assessmentAMOUNT_DUE
116
Amount paidAMOUNT_PAID
116
Bill first printedBILL_PRINT_DT
Jun 28, 2017
Final order dateFINAL_ORDER_ISSUE_DT
Aug 4, 2017
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 12, 2017
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1153758
Inspection beganINSPECTION_BEGIN_DT
May 12, 2017
Inspection closed outINSPECTION_END_DT
May 15, 2017
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: May 12, 2017
Type: Citation
Standard: 56.16006
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $116.00
Details

The citation

Citation or order numberVIOLATION_NO
8601780
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
May 12, 2017
Time issuedVIOLATION_ISSUE_TIME
1458
Date of occurrenceVIOLATION_OCCUR_DT
May 12, 2017
30 CFR part and sectionPART_SECTION
56.16006
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
May 13, 2017
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
May 13, 2017
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
May 15, 2017
Terminated, timeTERMINATION_TIME
1139
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
116
Current proposed assessmentAMOUNT_DUE
116
Amount paidAMOUNT_PAID
116
Bill first printedBILL_PRINT_DT
Jun 28, 2017
Final order dateFINAL_ORDER_ISSUE_DT
Aug 4, 2017
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 12, 2017
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1153758
Inspection beganINSPECTION_BEGIN_DT
May 12, 2017
Inspection closed outINSPECTION_END_DT
May 15, 2017
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Sep 9, 2015
Type: Citation
Standard: 56.14107(a)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8873402
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Sep 9, 2015
Time issuedVIOLATION_ISSUE_TIME
1120
Date of occurrenceVIOLATION_OCCUR_DT
Sep 9, 2015
30 CFR part and sectionPART_SECTION
56.14107(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Sep 9, 2015
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Sep 9, 2015
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Sep 10, 2015
Terminated, timeTERMINATION_TIME
1225
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
Nov 4, 2015
Final order dateFINAL_ORDER_ISSUE_DT
Dec 17, 2015
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 25, 2015
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6663816
Inspection beganINSPECTION_BEGIN_DT
Sep 9, 2015
Inspection closed outINSPECTION_END_DT
Oct 1, 2015
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Sep 9, 2015
Type: Citation
Standard: 56.11012
S&S: Y
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $108.00
Details

The citation

Citation or order numberVIOLATION_NO
8873400
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Sep 9, 2015
Time issuedVIOLATION_ISSUE_TIME
1050
Date of occurrenceVIOLATION_OCCUR_DT
Sep 9, 2015
30 CFR part and sectionPART_SECTION
56.11012
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Sep 9, 2015
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Sep 9, 2015
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Sep 10, 2015
Terminated, timeTERMINATION_TIME
1500
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
108
Current proposed assessmentAMOUNT_DUE
108
Amount paidAMOUNT_PAID
108
Bill first printedBILL_PRINT_DT
Nov 4, 2015
Final order dateFINAL_ORDER_ISSUE_DT
Dec 17, 2015
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 25, 2015
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6663816
Inspection beganINSPECTION_BEGIN_DT
Sep 9, 2015
Inspection closed outINSPECTION_END_DT
Oct 1, 2015
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (3)

Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Sep 9, 2015
Type: Citation
Standard: 56.12004
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8873403
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Sep 9, 2015
Time issuedVIOLATION_ISSUE_TIME
1205
Date of occurrenceVIOLATION_OCCUR_DT
Sep 9, 2015
30 CFR part and sectionPART_SECTION
56.12004
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Sep 9, 2015
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Sep 9, 2015
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Sep 10, 2015
Terminated, timeTERMINATION_TIME
1705
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
Nov 4, 2015
Final order dateFINAL_ORDER_ISSUE_DT
Dec 17, 2015
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 25, 2015
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6663816
Inspection beganINSPECTION_BEGIN_DT
Sep 9, 2015
Inspection closed outINSPECTION_END_DT
Oct 1, 2015
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Sep 9, 2015
Type: Citation
Standard: 56.15005
S&S: Y
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $2,700.00
Details

The citation

Citation or order numberVIOLATION_NO
8873401
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Sep 9, 2015
Time issuedVIOLATION_ISSUE_TIME
1100
Date of occurrenceVIOLATION_OCCUR_DT
Sep 9, 2015
30 CFR part and sectionPART_SECTION
56.15005
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence
Special assessmentSPECIAL_ASSESS
Y

Abatement

Originally dueORIG_TERM_DUE_DT
Sep 9, 2015
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Sep 9, 2015
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Sep 22, 2015
Terminated, timeTERMINATION_TIME
1450
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
2700
Current proposed assessmentAMOUNT_DUE
2700
Amount paidAMOUNT_PAID
2700
Bill first printedBILL_PRINT_DT
Jan 7, 2016
Final order dateFINAL_ORDER_ISSUE_DT
Feb 18, 2016
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jan 28, 2016
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6663816
Inspection beganINSPECTION_BEGIN_DT
Sep 9, 2015
Inspection closed outINSPECTION_END_DT
Oct 1, 2015
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (2)

Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Sep 22, 2014
Type: Citation
Standard: 56.4101
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8789652
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Sep 22, 2014
Time issuedVIOLATION_ISSUE_TIME
1020
Date of occurrenceVIOLATION_OCCUR_DT
Sep 22, 2014
30 CFR part and sectionPART_SECTION
56.4101
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Sep 22, 2014
Originally due, timeORIG_TERM_DUE_TIME
1630
Latest dueLATEST_TERM_DUE_DT
Sep 22, 2014
Latest due, timeLATEST_TERM_DUE_TIME
1630
TerminatedTERMINATION_DT
Sep 22, 2014
Terminated, timeTERMINATION_TIME
1200
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
Oct 29, 2014
Final order dateFINAL_ORDER_ISSUE_DT
Dec 4, 2014
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 18, 2014
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1157993
Inspection beganINSPECTION_BEGIN_DT
Sep 16, 2014
Inspection closed outINSPECTION_END_DT
Oct 1, 2014
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2014
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 16, 2014
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8766680
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 16, 2014
Time issuedVIOLATION_ISSUE_TIME
1140
Date of occurrenceVIOLATION_OCCUR_DT
Jul 16, 2014
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 16, 2014
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
Jul 16, 2014
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
Jul 16, 2014
Terminated, timeTERMINATION_TIME
1200
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
Sep 3, 2014
Final order dateFINAL_ORDER_ISSUE_DT
Oct 8, 2014
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 30, 2014
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6656217
Inspection beganINSPECTION_BEGIN_DT
Jul 16, 2014
Inspection closed outINSPECTION_END_DT
Jul 16, 2014
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2014
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 16, 2014
Type: Citation
Standard: 56.14107(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8766679
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 16, 2014
Time issuedVIOLATION_ISSUE_TIME
1035
Date of occurrenceVIOLATION_OCCUR_DT
Jul 16, 2014
30 CFR part and sectionPART_SECTION
56.14107(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 16, 2014
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
Jul 16, 2014
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
Jul 16, 2014
Terminated, timeTERMINATION_TIME
1230
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
Sep 3, 2014
Final order dateFINAL_ORDER_ISSUE_DT
Oct 8, 2014
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 30, 2014
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
6656217
Inspection beganINSPECTION_BEGIN_DT
Jul 16, 2014
Inspection closed outINSPECTION_END_DT
Jul 16, 2014
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2014
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Nov 7, 2013
Type: Citation
Standard: 50.10(d)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
6392501
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Nov 7, 2013
Time issuedVIOLATION_ISSUE_TIME
1200
Date of occurrenceVIOLATION_OCCUR_DT
Nov 7, 2013
30 CFR part and sectionPART_SECTION
50.10(d)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Nov 7, 2013
Originally due, timeORIG_TERM_DUE_TIME
1210
Latest dueLATEST_TERM_DUE_DT
Nov 7, 2013
Latest due, timeLATEST_TERM_DUE_TIME
1210
TerminatedTERMINATION_DT
Nov 7, 2013
Terminated, timeTERMINATION_TIME
1210
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
Jan 2, 2014
Final order dateFINAL_ORDER_ISSUE_DT
Mar 1, 2014
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Feb 6, 2014
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1140446
Inspection beganINSPECTION_BEGIN_DT
Nov 7, 2013
Inspection closed outINSPECTION_END_DT
Nov 14, 2013
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2013
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jun 21, 2013
Type: Citation
Standard: 56.12008
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
6478184
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 21, 2013
Time issuedVIOLATION_ISSUE_TIME
1500
Date of occurrenceVIOLATION_OCCUR_DT
Jun 21, 2013
30 CFR part and sectionPART_SECTION
56.12008
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 21, 2013
Originally due, timeORIG_TERM_DUE_TIME
1730
Latest dueLATEST_TERM_DUE_DT
Jun 21, 2013
Latest due, timeLATEST_TERM_DUE_TIME
1730
TerminatedTERMINATION_DT
Jun 22, 2013
Terminated, timeTERMINATION_TIME
1100
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
Jul 31, 2013
Final order dateFINAL_ORDER_ISSUE_DT
Sep 5, 2013
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Aug 27, 2013
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1146074
Inspection beganINSPECTION_BEGIN_DT
Jun 21, 2013
Inspection closed outINSPECTION_END_DT
Jun 24, 2013
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2013
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2013
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 27, 2012
Type: Citation
Standard: 56.14100(a)
S&S: Y
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $243.00
Details

The citation

Citation or order numberVIOLATION_NO
8601278
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 27, 2012
Time issuedVIOLATION_ISSUE_TIME
1321
Date of occurrenceVIOLATION_OCCUR_DT
Jul 27, 2012
30 CFR part and sectionPART_SECTION
56.14100(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 27, 2012
Originally due, timeORIG_TERM_DUE_TIME
1330
Latest dueLATEST_TERM_DUE_DT
Jul 27, 2012
Latest due, timeLATEST_TERM_DUE_TIME
1330
TerminatedTERMINATION_DT
Jul 27, 2012
Terminated, timeTERMINATION_TIME
1330
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
243
Current proposed assessmentAMOUNT_DUE
243
Amount paidAMOUNT_PAID
243
Bill first printedBILL_PRINT_DT
Aug 29, 2012
Final order dateFINAL_ORDER_ISSUE_DT
Oct 5, 2012
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 26, 2012
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1153432
Inspection beganINSPECTION_BEGIN_DT
Jul 27, 2012
Inspection closed outINSPECTION_END_DT
Jul 28, 2012
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2012
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2012
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (3)

Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 27, 2012
Type: Citation
Standard: 56.14115(b)
S&S: Y
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $243.00
Details

The citation

Citation or order numberVIOLATION_NO
8601280
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 27, 2012
Time issuedVIOLATION_ISSUE_TIME
1353
Date of occurrenceVIOLATION_OCCUR_DT
Jul 27, 2012
30 CFR part and sectionPART_SECTION
56.14115(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 27, 2012
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Jul 27, 2012
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Jul 27, 2012
Terminated, timeTERMINATION_TIME
1430
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
243
Current proposed assessmentAMOUNT_DUE
243
Amount paidAMOUNT_PAID
243
Bill first printedBILL_PRINT_DT
Aug 29, 2012
Final order dateFINAL_ORDER_ISSUE_DT
Oct 5, 2012
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 26, 2012
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
H C Redi-Mix LLC
Operator IDVIOLATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Inspection eventEVENT_NO
1153432
Inspection beganINSPECTION_BEGIN_DT
Jul 27, 2012
Inspection closed outINSPECTION_END_DT
Jul 28, 2012
Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2012
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2012
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (3)

Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

90 citations and orders since Aug 17, 2000: 90 issued to the operator, 0 to contractors working at the mine; the 25 most recent are listed. Proposed penalty is MSHA's original proposed amount, before any change from a contested case. Citations can be contested, modified or vacated.

Penalties as assessed

Issued: Jun 5, 2024
Citation number: 9687817
Standard: 56.4201(a)(2)
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $147.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9687817
Assessment control numberASSESS_CASE_NO
000604026
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Feb 18, 2025
Citation issuedISSUE_DT
Jun 5, 2024
Date of occurrenceOCCURRENCE_DT
Jun 5, 2024
Final order dateFINAL_ORDER_DT
Dec 3, 2024
Bill first printedBILL_PRINT_DT
Oct 2, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 3, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.4201(a)(2)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
0.87
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
147.00

Penalty points

Violation history pointsPENALTY_POINTS
26
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
2150
Size of mineSIZE_OF_MINE
2150
Controller hours workedCONTROLLER_HRS
2150
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2150
History period startHISTORY_START_DT
Mar 5, 2023
History period endHISTORY_END_DT
Jun 4, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6876596
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (16)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jun 5, 2024
Citation number: 9687816
Standard: 56.14130(g)
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $147.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9687816
Assessment control numberASSESS_CASE_NO
000604026
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Feb 18, 2025
Citation issuedISSUE_DT
Jun 5, 2024
Date of occurrenceOCCURRENCE_DT
Jun 5, 2024
Final order dateFINAL_ORDER_DT
Dec 3, 2024
Bill first printedBILL_PRINT_DT
Oct 2, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 3, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14130(g)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
0.87
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
147.00

Penalty points

Violation history pointsPENALTY_POINTS
26
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
2150
Size of mineSIZE_OF_MINE
2150
Controller hours workedCONTROLLER_HRS
2150
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2150
History period startHISTORY_START_DT
Mar 5, 2023
History period endHISTORY_END_DT
Jun 4, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6876596
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (16)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jun 5, 2024
Citation number: 9687815
Standard: 56.14112(b)
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $147.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9687815
Assessment control numberASSESS_CASE_NO
000604026
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Feb 18, 2025
Citation issuedISSUE_DT
Jun 5, 2024
Date of occurrenceOCCURRENCE_DT
Jun 5, 2024
Final order dateFINAL_ORDER_DT
Dec 3, 2024
Bill first printedBILL_PRINT_DT
Oct 2, 2024
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 3, 2024
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14112(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Mine Act interestMINEACT_INTEREST_AMT
0.87
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
147.00

Penalty points

Violation history pointsPENALTY_POINTS
31
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
2150
Size of mineSIZE_OF_MINE
2150
Controller hours workedCONTROLLER_HRS
2150
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2150
History period startHISTORY_START_DT
Mar 5, 2023
History period endHISTORY_END_DT
Jun 4, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6876596
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (16)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Oct 6, 2022
Citation number: 9615977
Standard: 56.4201(b)
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $133.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9615977
Assessment control numberASSESS_CASE_NO
000567465
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Dec 28, 2022
Citation issuedISSUE_DT
Oct 6, 2022
Date of occurrenceOCCURRENCE_DT
Oct 6, 2022
Final order dateFINAL_ORDER_DT
Jan 12, 2023
Bill first printedBILL_PRINT_DT
Nov 30, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2023
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jan 12, 2023
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.4201(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
133.00

Penalty points

Violation history pointsPENALTY_POINTS
26
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Operator hours worked at the mineVIOLATOR_MINE_HRS
675
Size of mineSIZE_OF_MINE
675
Controller hours workedCONTROLLER_HRS
4964
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4964
History period startHISTORY_START_DT
Jul 6, 2021
History period endHISTORY_END_DT
Oct 5, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1124194
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (16)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 28, 2022
Citation number: 9615233
Standard: 56.12032
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $133.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9615233
Assessment control numberASSESS_CASE_NO
000561961
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 29, 2022
Citation issuedISSUE_DT
Jul 28, 2022
Date of occurrenceOCCURRENCE_DT
Jul 28, 2022
Final order dateFINAL_ORDER_DT
Oct 13, 2022
Bill first printedBILL_PRINT_DT
Aug 31, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 13, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12032
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
133.00

Penalty points

Violation history pointsPENALTY_POINTS
51
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
675
Size of mineSIZE_OF_MINE
675
Controller hours workedCONTROLLER_HRS
4964
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4964
History period startHISTORY_START_DT
Apr 28, 2021
History period endHISTORY_END_DT
Jul 27, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6876216
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (17)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 28, 2022
Citation number: 9615234
Standard: 56.12006
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $133.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9615234
Assessment control numberASSESS_CASE_NO
000561961
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 29, 2022
Citation issuedISSUE_DT
Jul 28, 2022
Date of occurrenceOCCURRENCE_DT
Jul 28, 2022
Final order dateFINAL_ORDER_DT
Oct 13, 2022
Bill first printedBILL_PRINT_DT
Aug 31, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 13, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12006
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
133.00

Penalty points

Violation history pointsPENALTY_POINTS
51
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
675
Size of mineSIZE_OF_MINE
675
Controller hours workedCONTROLLER_HRS
4964
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4964
History period startHISTORY_START_DT
Apr 28, 2021
History period endHISTORY_END_DT
Jul 27, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6876216
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (17)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Oct 9, 2020
Citation number: 6392548
Standard: 56.14206(b)
Proposed penalty: $123.00
Current assessment: $123.00
Paid against proposed penalty: $123.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
6392548
Assessment control numberASSESS_CASE_NO
000526240
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jan 5, 2021
Citation issuedISSUE_DT
Oct 9, 2020
Date of occurrenceOCCURRENCE_DT
Oct 9, 2020
Final order dateFINAL_ORDER_DT
Jan 17, 2021
Bill first printedBILL_PRINT_DT
Dec 2, 2020
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jan 17, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14206(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
123.00
Current assessmentCURRENT_ASSESSMENT_AMT
123.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
123.00

Penalty points

Violation history pointsPENALTY_POINTS
41
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
0.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
1369
Size of mineSIZE_OF_MINE
1369
Controller hours workedCONTROLLER_HRS
12202
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
12202
History period startHISTORY_START_DT
Jul 9, 2019
History period endHISTORY_END_DT
Oct 8, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1153995
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jun 29, 2020
Citation number: 9435850
Standard: 56.12008
Proposed penalty: $123.00
Current assessment: $123.00
Paid against proposed penalty: $123.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9435850
Assessment control numberASSESS_CASE_NO
000521092
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 24, 2020
Citation issuedISSUE_DT
Jun 29, 2020
Date of occurrenceOCCURRENCE_DT
Jun 29, 2020
Final order dateFINAL_ORDER_DT
Oct 12, 2020
Bill first printedBILL_PRINT_DT
Sep 2, 2020
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2020
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 12, 2020
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12008
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
123.00
Current assessmentCURRENT_ASSESSMENT_AMT
123.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
123.00

Penalty points

Violation history pointsPENALTY_POINTS
41
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1
Violations per inspection dayVPID
1
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
1
Repeat violations per inspection dayRPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
1369
Size of mineSIZE_OF_MINE
1369
Controller hours workedCONTROLLER_HRS
12202
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
12202
History period startHISTORY_START_DT
Mar 29, 2019
History period endHISTORY_END_DT
Jun 28, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1146673
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jun 29, 2020
Citation number: 9435852
Standard: 46.3(a)
Proposed penalty: $123.00
Current assessment: $123.00
Paid against proposed penalty: $123.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9435852
Assessment control numberASSESS_CASE_NO
000521092
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 24, 2020
Citation issuedISSUE_DT
Jun 29, 2020
Date of occurrenceOCCURRENCE_DT
Jun 29, 2020
Final order dateFINAL_ORDER_DT
Oct 12, 2020
Bill first printedBILL_PRINT_DT
Sep 2, 2020
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2020
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 12, 2020
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
46.3(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
123.00
Current assessmentCURRENT_ASSESSMENT_AMT
123.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
123.00

Penalty points

Violation history pointsPENALTY_POINTS
20
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
1369
Size of mineSIZE_OF_MINE
1369
Controller hours workedCONTROLLER_HRS
12202
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
12202
History period startHISTORY_START_DT
Mar 29, 2019
History period endHISTORY_END_DT
Jun 28, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1146673
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (17)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jun 29, 2020
Citation number: 9435851
Standard: 56.12004
Proposed penalty: $123.00
Current assessment: $123.00
Paid against proposed penalty: $123.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9435851
Assessment control numberASSESS_CASE_NO
000521092
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 24, 2020
Citation issuedISSUE_DT
Jun 29, 2020
Date of occurrenceOCCURRENCE_DT
Jun 29, 2020
Final order dateFINAL_ORDER_DT
Oct 12, 2020
Bill first printedBILL_PRINT_DT
Sep 2, 2020
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2020
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 12, 2020
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12004
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
123.00
Current assessmentCURRENT_ASSESSMENT_AMT
123.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
123.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
1369
Size of mineSIZE_OF_MINE
1369
Controller hours workedCONTROLLER_HRS
12202
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
12202
History period startHISTORY_START_DT
Mar 29, 2019
History period endHISTORY_END_DT
Jun 28, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1146673
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jun 3, 2019
Citation number: 6392998
Standard: 56.12008
Proposed penalty: $121.00
Current assessment: $121.00
Paid against proposed penalty: $121.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
6392998
Assessment control numberASSESS_CASE_NO
000496476
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Aug 20, 2019
Citation issuedISSUE_DT
Jun 3, 2019
Date of occurrenceOCCURRENCE_DT
Jun 3, 2019
Final order dateFINAL_ORDER_DT
Sep 6, 2019
Bill first printedBILL_PRINT_DT
Jul 31, 2019
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2019
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Sep 6, 2019
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12008
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
121.00
Current assessmentCURRENT_ASSESSMENT_AMT
121.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
121.00

Penalty points

Violation history pointsPENALTY_POINTS
41
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
3307
Size of mineSIZE_OF_MINE
3307
Controller hours workedCONTROLLER_HRS
5827
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
5827
History period startHISTORY_START_DT
Mar 3, 2018
History period endHISTORY_END_DT
Jun 2, 2019

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1146491
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (17)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Oct 3, 2017
Citation number: 6392934
Standard: 56.20003(a)
Proposed penalty: $116.00
Current assessment: $116.00
Paid against proposed penalty: $116.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
6392934
Assessment control numberASSESS_CASE_NO
000453517
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Dec 29, 2017
Citation issuedISSUE_DT
Oct 3, 2017
Date of occurrenceOCCURRENCE_DT
Oct 3, 2017
Final order dateFINAL_ORDER_DT
Jan 29, 2018
Bill first printedBILL_PRINT_DT
Nov 29, 2017
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jan 29, 2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.20003(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
116.00
Current assessmentCURRENT_ASSESSMENT_AMT
116.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
116.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
0.67
Operator hours worked at the mineVIOLATOR_MINE_HRS
1466
Size of mineSIZE_OF_MINE
1466
Controller hours workedCONTROLLER_HRS
1466
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
1466
History period startHISTORY_START_DT
Jul 3, 2016
History period endHISTORY_END_DT
Oct 2, 2017

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1146249
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: May 12, 2017
Citation number: 8601780
Standard: 56.16006
Proposed penalty: $116.00
Current assessment: $116.00
Paid against proposed penalty: $116.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8601780
Assessment control numberASSESS_CASE_NO
000442421
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 12, 2017
Citation issuedISSUE_DT
May 12, 2017
Date of occurrenceOCCURRENCE_DT
May 12, 2017
Final order dateFINAL_ORDER_DT
Aug 4, 2017
Bill first printedBILL_PRINT_DT
Jun 28, 2017
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2017
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 4, 2017
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.16006
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
116.00
Current assessmentCURRENT_ASSESSMENT_AMT
116.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
116.00

Penalty points

Violation history pointsPENALTY_POINTS
41
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
1466
Size of mineSIZE_OF_MINE
1466
Controller hours workedCONTROLLER_HRS
1466
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
1466
History period startHISTORY_START_DT
Feb 12, 2016
History period endHISTORY_END_DT
May 11, 2017

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1153758
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (16)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: May 12, 2017
Citation number: 8601781
Standard: 56.16005
Proposed penalty: $116.00
Current assessment: $116.00
Paid against proposed penalty: $116.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8601781
Assessment control numberASSESS_CASE_NO
000442421
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 12, 2017
Citation issuedISSUE_DT
May 12, 2017
Date of occurrenceOCCURRENCE_DT
May 12, 2017
Final order dateFINAL_ORDER_DT
Aug 4, 2017
Bill first printedBILL_PRINT_DT
Jun 28, 2017
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2017
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 4, 2017
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.16005
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
116.00
Current assessmentCURRENT_ASSESSMENT_AMT
116.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
116.00

Penalty points

Violation history pointsPENALTY_POINTS
26
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
1466
Size of mineSIZE_OF_MINE
1466
Controller hours workedCONTROLLER_HRS
1466
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
1466
History period startHISTORY_START_DT
Feb 12, 2016
History period endHISTORY_END_DT
May 11, 2017

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1153758
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (16)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Sep 9, 2015
Citation number: 8873403
Standard: 56.12004
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8873403
Assessment control numberASSESS_CASE_NO
000395770
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 25, 2015
Citation issuedISSUE_DT
Sep 9, 2015
Date of occurrenceOCCURRENCE_DT
Sep 9, 2015
Final order dateFINAL_ORDER_DT
Dec 17, 2015
Bill first printedBILL_PRINT_DT
Nov 4, 2015
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2016
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 17, 2015
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12004
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
51
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
1404
Size of mineSIZE_OF_MINE
1404
Controller hours workedCONTROLLER_HRS
2840
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2840
History period startHISTORY_START_DT
Jun 9, 2014
History period endHISTORY_END_DT
Sep 8, 2015

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6663816
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Sep 9, 2015
Citation number: 8873400
Standard: 56.11012
Proposed penalty: $108.00
Current assessment: $108.00
Paid against proposed penalty: $108.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8873400
Assessment control numberASSESS_CASE_NO
000395770
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 25, 2015
Citation issuedISSUE_DT
Sep 9, 2015
Date of occurrenceOCCURRENCE_DT
Sep 9, 2015
Final order dateFINAL_ORDER_DT
Dec 17, 2015
Bill first printedBILL_PRINT_DT
Nov 4, 2015
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2016
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 17, 2015
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.11012
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
108.00
Current assessmentCURRENT_ASSESSMENT_AMT
108.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
108.00

Penalty points

Violation history pointsPENALTY_POINTS
61
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
1404
Size of mineSIZE_OF_MINE
1404
Controller hours workedCONTROLLER_HRS
2840
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2840
History period startHISTORY_START_DT
Jun 9, 2014
History period endHISTORY_END_DT
Sep 8, 2015

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6663816
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Sep 9, 2015
Citation number: 8873401
Standard: 56.15005
Proposed penalty: $2,700.00
Current assessment: $2,700.00
Paid against proposed penalty: $2,700.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8873401
Assessment control numberASSESS_CASE_NO
000400946
Assessment typeASSESS_TYPE_CD
Special
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jan 27, 2016
Citation issuedISSUE_DT
Sep 9, 2015
Date of occurrenceOCCURRENCE_DT
Sep 9, 2015
Final order dateFINAL_ORDER_DT
Feb 18, 2016
Bill first printedBILL_PRINT_DT
Jan 7, 2016
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2016
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Feb 18, 2016
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.15005
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
2700.00
Current assessmentCURRENT_ASSESSMENT_AMT
2700.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
2700.00

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
1404
Size of mineSIZE_OF_MINE
1404
Controller hours workedCONTROLLER_HRS
2840
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2840
History period startHISTORY_START_DT
Jun 9, 2014
History period endHISTORY_END_DT
Sep 8, 2015

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6663816
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (8)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (12)

Mine Act sectionMINE_ACT_SECTION_CD, Violation history pointsPENALTY_POINTS, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Negligence pointsNEGLIGENCE_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS

Issued: Sep 9, 2015
Citation number: 8873402
Standard: 56.14107(a)
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8873402
Assessment control numberASSESS_CASE_NO
000395770
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 25, 2015
Citation issuedISSUE_DT
Sep 9, 2015
Date of occurrenceOCCURRENCE_DT
Sep 9, 2015
Final order dateFINAL_ORDER_DT
Dec 17, 2015
Bill first printedBILL_PRINT_DT
Nov 4, 2015
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2016
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 17, 2015
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14107(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
31
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
1
Repeat violations per inspection dayRPID
0.333
Operator hours worked at the mineVIOLATOR_MINE_HRS
1404
Size of mineSIZE_OF_MINE
1404
Controller hours workedCONTROLLER_HRS
2840
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
2840
History period startHISTORY_START_DT
Jun 9, 2014
History period endHISTORY_END_DT
Sep 8, 2015

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6663816
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Sep 22, 2014
Citation number: 8789652
Standard: 56.4101
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8789652
Assessment control numberASSESS_CASE_NO
000365896
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 18, 2014
Citation issuedISSUE_DT
Sep 22, 2014
Date of occurrenceOCCURRENCE_DT
Sep 22, 2014
Final order dateFINAL_ORDER_DT
Dec 4, 2014
Bill first printedBILL_PRINT_DT
Oct 29, 2014
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2015
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 4, 2014
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.4101
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
0.67
Operator hours worked at the mineVIOLATOR_MINE_HRS
4869
Size of mineSIZE_OF_MINE
4869
Controller hours workedCONTROLLER_HRS
8972
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
8972
History period startHISTORY_START_DT
Jun 22, 2013
History period endHISTORY_END_DT
Sep 21, 2014

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1157993
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 16, 2014
Citation number: 8766680
Standard: 50.30(a)
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8766680
Assessment control numberASSESS_CASE_NO
000360311
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 30, 2014
Citation issuedISSUE_DT
Jul 16, 2014
Date of occurrenceOCCURRENCE_DT
Jul 16, 2014
Final order dateFINAL_ORDER_DT
Oct 8, 2014
Bill first printedBILL_PRINT_DT
Sep 3, 2014
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2014
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 8, 2014
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
20
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
0.67
Operator hours worked at the mineVIOLATOR_MINE_HRS
4869
Size of mineSIZE_OF_MINE
4869
Controller hours workedCONTROLLER_HRS
8972
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
8972
History period startHISTORY_START_DT
Apr 16, 2013
History period endHISTORY_END_DT
Jul 15, 2014

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6656217
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (17)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 16, 2014
Citation number: 8766679
Standard: 56.14107(a)
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8766679
Assessment control numberASSESS_CASE_NO
000360311
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 30, 2014
Citation issuedISSUE_DT
Jul 16, 2014
Date of occurrenceOCCURRENCE_DT
Jul 16, 2014
Final order dateFINAL_ORDER_DT
Oct 8, 2014
Bill first printedBILL_PRINT_DT
Sep 3, 2014
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2014
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 8, 2014
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14107(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
41
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
0.67
Operator hours worked at the mineVIOLATOR_MINE_HRS
4869
Size of mineSIZE_OF_MINE
4869
Controller hours workedCONTROLLER_HRS
8972
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
8972
History period startHISTORY_START_DT
Apr 16, 2013
History period endHISTORY_END_DT
Jul 15, 2014

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6656217
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Nov 7, 2013
Citation number: 6392501
Standard: 50.10(d)
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
6392501
Assessment control numberASSESS_CASE_NO
000340374
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Feb 5, 2014
Citation issuedISSUE_DT
Nov 7, 2013
Date of occurrenceOCCURRENCE_DT
Nov 7, 2013
Final order dateFINAL_ORDER_DT
Mar 1, 2014
Bill first printedBILL_PRINT_DT
Jan 2, 2014
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2014
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 1, 2014
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.10(d)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1
Violations per inspection dayVPID
4
Operator hours worked at the mineVIOLATOR_MINE_HRS
3138
Size of mineSIZE_OF_MINE
3138
Controller hours workedCONTROLLER_HRS
3526
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
3526
History period startHISTORY_START_DT
Aug 7, 2012
History period endHISTORY_END_DT
Nov 6, 2013

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1140446
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (17)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jun 21, 2013
Citation number: 6478184
Standard: 56.12008
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
6478184
Assessment control numberASSESS_CASE_NO
000328811
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Aug 27, 2013
Citation issuedISSUE_DT
Jun 21, 2013
Date of occurrenceOCCURRENCE_DT
Jun 21, 2013
Final order dateFINAL_ORDER_DT
Sep 5, 2013
Bill first printedBILL_PRINT_DT
Jul 31, 2013
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2013
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Sep 5, 2013
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12008
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
51
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
1.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
3138
Size of mineSIZE_OF_MINE
3138
Controller hours workedCONTROLLER_HRS
3526
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
3526
History period startHISTORY_START_DT
Mar 21, 2012
History period endHISTORY_END_DT
Jun 20, 2013

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1146074
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 27, 2012
Citation number: 8601279
Standard: 56.14105
Proposed penalty: $807.00
Current assessment: $807.00
Paid against proposed penalty: $807.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8601279
Assessment control numberASSESS_CASE_NO
000305455
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 14, 2012
Citation issuedISSUE_DT
Jul 27, 2012
Date of occurrenceOCCURRENCE_DT
Jul 27, 2012
Final order dateFINAL_ORDER_DT
Dec 7, 2012
Bill first printedBILL_PRINT_DT
Oct 31, 2012
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2013
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 7, 2012
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14105
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
807.00
Current assessmentCURRENT_ASSESSMENT_AMT
807.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
807.00

Penalty points

Violation history pointsPENALTY_POINTS
86
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
3780
Size of mineSIZE_OF_MINE
3780
Controller hours workedCONTROLLER_HRS
5015
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
5015
History period startHISTORY_START_DT
Apr 27, 2011
History period endHISTORY_END_DT
Jul 26, 2012

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1153432
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 27, 2012
Citation number: 8601280
Standard: 56.14115(b)
Proposed penalty: $243.00
Current assessment: $243.00
Paid against proposed penalty: $243.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8601280
Assessment control numberASSESS_CASE_NO
000299302
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 14, 2012
Citation issuedISSUE_DT
Jul 27, 2012
Date of occurrenceOCCURRENCE_DT
Jul 27, 2012
Final order dateFINAL_ORDER_DT
Oct 5, 2012
Bill first printedBILL_PRINT_DT
Aug 29, 2012
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2012
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 5, 2012
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14115(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
243.00
Current assessmentCURRENT_ASSESSMENT_AMT
243.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
243.00

Penalty points

Violation history pointsPENALTY_POINTS
71
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
3780
Size of mineSIZE_OF_MINE
3780
Controller hours workedCONTROLLER_HRS
5015
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
5015
History period startHISTORY_START_DT
Apr 27, 2011
History period endHISTORY_END_DT
Jul 26, 2012

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
H C Redi-Mix Inc.
IDVIOLATOR_ID
0050477
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 29, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
1153432
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7861

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

25 most recent of 90 assessed citations and orders. Amounts are MSHA's per-citation values; case status is MSHA's own (Closed, Invalid, Printed or Received).

Contested citations and decisions

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.14107(a)
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392310
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.14107(a)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Permanent
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Permanent
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.12025
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392336
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12025
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.12013(b)
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392326
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12013(b)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.12025
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392316
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12025
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-204M
Standard: 56.11003
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392315
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-204M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.11003
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.12013(b)
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392325
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12013(b)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-204M
Standard: 56.4104(b)
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392322
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-204M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.4104(b)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
LostDays
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
LostDays
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-204M
Standard: 56.14101(a)(2)
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392333
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-204M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.14101(a)(2)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
LostDays
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
LostDays
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-204M
Standard: 56.12018
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392321
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-204M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12018
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.12028
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392335
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12028
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.12025
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392324
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12025
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-204M
Standard: 56.12013(b)
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392323
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-204M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12013(b)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.14112(b)
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392327
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.14112(b)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.15002
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392311
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.15002
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
LostDays
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
LostDays
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.12025
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392317
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12025
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-204M
Standard: 56.14132(a)
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392332
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-204M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.14132(a)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
LostDays
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
LostDays
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-204M
Standard: 56.12032
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392320
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-204M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12032
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.12025
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392337
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12025
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.12013(b)
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392318
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12013(b)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.12013(b)
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392314
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12013(b)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.14107(a)
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392329
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.14107(a)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.9300(a)
Proposed penalty: $228.00
Penalty after decision: $228.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392330
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
228.00
Penalty after the decisionDECISION_PENALTY_AMT
228.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.9300(a)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
LostDays
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
LostDays
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.14107(a)
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392331
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.14107(a)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-204M
Standard: 56.12005
Proposed penalty: $60.00
Penalty after decision: $60.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392319
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-204M
Assessment typeASSESS_TYPE_CODE
Single
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
60.00
Penalty after the decisionDECISION_PENALTY_AMT
60.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.12005
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 18, 2007
Citation issued: Jun 1, 2006
Docket: WEST 2007-203M
Standard: 56.18002(a)
Proposed penalty: $375.00
Penalty after decision: $375.00
Decided: Aug 6, 2007
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
6392334
Citation issuedCITATION_ISSUE_DT
Jun 1, 2006
Hearing request receivedCONTEST_DT
Jan 18, 2007
Docket numberDOCKET_NO
WEST 2007-203M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Aug 6, 2007
Petition filedPETITION_FILED_DT
Apr 9, 2007

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
375.00
Penalty after the decisionDECISION_PENALTY_AMT
375.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.18002(a)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
S&S when decidedDECISION_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Fatal
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR902
MSHA representative officeMSHA_REP_OFFICE_NAME
Seattle

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC

Other fields

ISSUING_FIELD_OFFICE
M7861

Not recorded by MSHA (3)

Petition duePETITION_DUE_DT, Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

25 most recent of 28 contested citations and orders; decision types are MSHA's own text.

Reported injuries, illnesses and accidents

Reports by degree of injury, as MSHA records it. FATALITY rows are left out of this breakdown: MSHA leaves deaths it finds unrelated to mining out of its fatality statistics, so a count of these reports can differ from MSHA's figures. See MSHA's fatality report search.

ACCIDENT ONLY
1
Date: Nov 4, 2013
Degree of injury: ACCIDENT ONLY
Classification: FIRE
Accident type: Accident type, without injuries
Days lost: 0
Details

The report

Document numberDOCUMENT_NO
220133170003
DateACCIDENT_DT
Nov 4, 2013
TimeACCIDENT_TIME
1047
Shift beganSHIFT_BEGIN_TIME
0700
Degree of injuryDEGREE_INJURY
ACCIDENT ONLY
Degree of injury codeDEGREE_INJURY_CD
00
ClassificationCLASSIFICATION
FIRE
Classification codeCLASSIFICATION_CD
08
Accident typeACCIDENT_TYPE
Accident type, without injuries
Accident type codeACCIDENT_TYPE_CD
44
Immediately reportable typeIMMED_NOTIFY
MINE FIRE
Immediately reportable codeIMMED_NOTIFY_CD
06
MSHA investigation beganINVEST_BEGIN_DT
Nov 7, 2013

Injury

Activity at the timeACTIVITY
NO VALUE FOUND
Activity codeACTIVITY_CD
?
Source of injuryINJURY_SOURCE
NO VALUE FOUND
Source of injury codeINJURY_SOURCE_CD
?
Nature of injuryNATURE_INJURY
NO VALUE FOUND
Nature of injury codeNATURE_INJURY_CD
?
Part of bodyINJ_BODY_PART
NO VALUE FOUND
Part of body codeINJ_BODY_PART_CD
?

Where, and equipment

Location in the mineSUBUNIT
STRIP, QUARY, OPEN PIT
Location codeSUBUNIT_CD
03
Underground locationUG_LOCATION
NO VALUE FOUND
Underground location codeUG_LOCATION_CD
?
Underground mining methodUG_MINING_METHOD
NO VALUE FOUND
Underground mining method codeUG_MINING_METHOD_CD
?
Equipment involvedMINING_EQUIP
Shovel, Power shovel, Backhoe, Trackhoe, Dragline - Big Muskie
Equipment codeMINING_EQUIP_CD
60
Equipment manufacturerEQUIP_MFR_NAME
Not on this list
Equipment manufacturer codeEQUIP_MFR_CD
119
Equipment model numberEQUIP_MODEL_NO
650
FIPS state codeFIPS_STATE_CD
02

Who and period

Operator at the timeOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Controller IDCONTROLLER_ID
0040850
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2013
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (4)

Reportable injuries or illnessesNO_INJURIES, Schedule charge, daysSCHEDULE_CHARGE, Days of restricted workDAYS_RESTRICT, Days lostDAYS_LOST

Not recorded by MSHA (5)

Returned to Duty document numberCLOSED_DOC_NO, Permanently transferred or terminatedTRANS_TERM, Returned to workRETURN_TO_WORK_DT, Controller at the timeCONTROLLER_NAME, Contractor IDCONTRACTOR_ID

1 report filed on MSHA Form 7000-1; categories are MSHA's own text.

Employment and hours worked

Year: 2026
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 1,540
Details

The report

YearCALENDAR_YR
2026
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
1540
Average hours per employeeAVG_EMPLOYEE_HOURS
1540

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2026
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 1
Hours worked: 1,540
Details

The report

YearCALENDAR_YR
2026
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
1540
Average hours per employeeAVG_EMPLOYEE_HOURS
1540

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2025
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 1,550
Details

The report

YearCALENDAR_YR
2025
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
1550
Average hours per employeeAVG_EMPLOYEE_HOURS
1550

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2025
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 1
Hours worked: 1,540
Details

The report

YearCALENDAR_YR
2025
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
1540
Average hours per employeeAVG_EMPLOYEE_HOURS
1540

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2024
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 34
Details

The report

YearCALENDAR_YR
2024
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
34
Average hours per employeeAVG_EMPLOYEE_HOURS
34

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2024
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 1
Hours worked: 840
Details

The report

YearCALENDAR_YR
2024
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
840
Average hours per employeeAVG_EMPLOYEE_HOURS
840

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2023
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 8
Details

The report

YearCALENDAR_YR
2023
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
8
Average hours per employeeAVG_EMPLOYEE_HOURS
8

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2023
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 2
Hours worked: 2,150
Details

The report

YearCALENDAR_YR
2023
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
2
Hours workedANNUAL_HRS
2150
Average hours per employeeAVG_EMPLOYEE_HOURS
1075

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2022
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 75
Details

The report

YearCALENDAR_YR
2022
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
75
Average hours per employeeAVG_EMPLOYEE_HOURS
75

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2022
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 3
Hours worked: 1,434
Details

The report

YearCALENDAR_YR
2022
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
1434
Average hours per employeeAVG_EMPLOYEE_HOURS
478

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2021
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 70
Details

The report

YearCALENDAR_YR
2021
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
70
Average hours per employeeAVG_EMPLOYEE_HOURS
70

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2021
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 3
Hours worked: 675
Details

The report

YearCALENDAR_YR
2021
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
675
Average hours per employeeAVG_EMPLOYEE_HOURS
225

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2020
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 94
Details

The report

YearCALENDAR_YR
2020
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
94
Average hours per employeeAVG_EMPLOYEE_HOURS
94

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2020
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 1
Hours worked: 1,504
Details

The report

YearCALENDAR_YR
2020
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
1504
Average hours per employeeAVG_EMPLOYEE_HOURS
1504

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2019
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 190
Details

The report

YearCALENDAR_YR
2019
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
190
Average hours per employeeAVG_EMPLOYEE_HOURS
190

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2019
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 1
Hours worked: 1,369
Details

The report

YearCALENDAR_YR
2019
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
1369
Average hours per employeeAVG_EMPLOYEE_HOURS
1369

Mine

Mine IDMINE_ID
5001662
Mine name in this fileCURR_MINE_NM
H C Redi-Mix LLC
StateSTATE_ABBR
AK
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

What the operator reported to MSHA for the 8 most recent years, one row per part of the mine, as MSHA files them. Rows are not added together.

Mine details

MSHA field office
Anchorage AK Field Office
Nearest town
FAIRBANKS
Days worked per week
5
Hours per shift
8
Production shifts per day
1
Maintenance shifts per day
0
Employees, current record
2
Tailing ponds
0
103(i) spot inspection status
Never Had 103I Status
Safety committee
N
Portable operation
N
Every field in MSHA's mine record

The mine

Mine nameCURRENT_MINE_NAME
H C Redi-Mix LLC
Mine IDMINE_ID
5001662
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Mine typeCURRENT_MINE_TYPE
Surface
Current statusCURRENT_MINE_STATUS
Intermittent
Status sinceCURRENT_STATUS_DT
Jun 9, 2003
Legal entity typeCOMPANY_TYPE
Other

Operator and controller

OperatorCURRENT_OPERATOR_NAME
H C Redi-Mix LLC
Operator IDCURRENT_OPERATOR_ID
0050477
Controller IDCURRENT_CONTROLLER_ID
0040850
Start of the operating periodCURRENT_CONTROLLER_BEGIN_DT
Sep 29, 2001

Location and MSHA office

StateSTATE
AK
Bureau of Mines state codeBOM_STATE_CD
50
FIPS county codeFIPS_CNTY_CD
090
FIPS county nameFIPS_CNTY_NM
Fairbanks North Star
Congressional districtCONG_DIST_CD
01
Nearest townNEAREST_TOWN
FAIRBANKS
MSHA districtDISTRICT
M7
MSHA office codeOFFICE_CD
M7861
MSHA officeOFFICE_NAME
Anchorage AK Field Office
Most recent assessment control numberASSESS_CTRL_NO
000604026

Commodity

Primary commodity (SIC)PRIMARY_SIC
Construction Sand and Gravel
Primary commodity codePRIMARY_SIC_CD
144200
Primary SIC codePRIMARY_SIC_CD_1
1442
Primary SIC suffixPRIMARY_SIC_CD_SFX
00
Primary industry groupPRIMARY_CANVASS
SandAndGravel
Primary industry group codePRIMARY_CANVASS_CD
5

Operations, from the Mine Information Form

Days operating per weekDAYS_PER_WEEK
5
Hours per shiftHOURS_PER_SHIFT
8
Production shifts per dayPROD_SHIFTS_PER_DAY
1
Workers employedNO_EMPLOYEES
2
MSHA restricted from enforcing Part 48 trainingPART48_TRAINING
Y
103(i) statusCURRENT_103I
Never Had 103I Status

Recorded as 0 (3)

Driving miles from the MSHA officeMILES_FROM_OFFICE, Maintenance-only shifts per dayMAINT_SHIFTS_PER_DAY, Tailing pondsNO_TAILING_PONDS

Recorded as N (5)

Portable minePORTABLE_OPERATION, Pillar recovery usedPILLAR_RECOVERY_USED, Highwall miner usedHIGHWALL_MINER_USED, Multiple pitsMULTIPLE_PITS, Safety committeeSAFETY_COMMITTEE_IND

Not recorded by MSHA (14)

Portable mine FIPS state codePORTABLE_FIPS_ST_CD, ControllerCURRENT_CONTROLLER_NAME, Secondary commodity (SIC)SECONDARY_SIC, Secondary commodity codeSECONDARY_SIC_CD, Secondary SIC codeSECONDARY_SIC_CD_1, Secondary SIC suffixSECONDARY_SIC_CD_SFX, Secondary industry groupSECONDARY_CANVASS, Secondary industry group codeSECONDARY_CANVASS_CD, Average mining height, inchesAVG_MINE_HEIGHT, Mine gas categoryMINE_GAS_CATEGORY_CD, Methane liberation, cu ft per 24 hMETHANE_LIBERATION, Producing pitsNO_PRODUCING_PITS, Non-producing pitsNO_NONPRODUCING_PITS, 103(i) status sinceCURRENT_103I_DT

Operator and controller history

Operator: H C Redi-Mix LLC
From: Sep 29, 2001
To: No end date
Controller: Not shown
From : Sep 29, 2001
To : No end date
Details

Operator

OperatorOPERATOR_NAME
H C Redi-Mix LLC
Operator IDOPERATOR_ID
0050477
Operator fromOPERATOR_START_DT
Sep 29, 2001

Controller

Controller IDCONTROLLER_ID
0040850
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Sep 29, 2001

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine status at this pointMINE_STATUS
Intermittent
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (3)

Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

Operator: Alaska Redi-Mix Inc
From: Aug 1, 2000
To: Sep 28, 2001
Controller: Not shown
From : Aug 1, 2000
To : No end date
Details

Operator

OperatorOPERATOR_NAME
Alaska Redi-Mix Inc
Operator IDOPERATOR_ID
L17770
Operator fromOPERATOR_START_DT
Aug 1, 2000
Operator toOPERATOR_END_DT
Sep 28, 2001

Controller

Controller IDCONTROLLER_ID
M13556
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Aug 1, 2000

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Mine status at this pointMINE_STATUS
Intermittent
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (2)

ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

As MSHA records it, newest operator first.

Address of record

H C Redi-Mix LLC·Contact title President·Street not recorded, Fairbanks AK 99708

MSHA says an address of record "does not represent the actual mine location."

Every field in the address record

Address

Business nameBUSINESS_NAME
H C Redi-Mix LLC
Contact titleCONTACT_TITLE
President
CityCITY
Fairbanks
StateSTATE_ABBR
AK
State nameSTATE
Alaska
ZIP codeZIP_CD
99708
CountryCOUNTRY
USA
FIPS state codeFIPS_STATE_CD
02

Mine

Mine IDMINE_ID
5001662
Mine name in this fileMINE_NAME
H C Redi-Mix LLC
Nearest townNEAREST_TOWN
FAIRBANKS
Mine typeMINE_TYPE_CD
Surface
Mine statusMINE_STATUS
Intermittent
Status sinceMINE_STATUS_DT
Jun 9, 2003
Primary commodity (SIC)PRIMARY_SIC_CD
Construction Sand and Gravel
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (4)

StreetSTREET, PO boxPO_BOX, ProvincePROVINCE, Foreign postal codePOSTAL_CD

Sources. MSHA open government data files: Mines, Inspections, Violations, AssessedViolations, ContestedViolations, 107(a)OrdersIssued, Accidents, MinesProdYearly, ControllerOperatorHistory, AddressOfRecord. Field labels are shortened from MSHA's definition files, with MSHA's column name beside each. MSHA Mine Data Retrieval System·MSHA fatality report search·MSHA open government data

These are U.S. Department of Labor, Mine Safety and Health Administration records, reproduced as published. Citations can be contested, modified or vacated, and records that are contested or not yet final are included. SafetyRecord.org is not a consumer reporting agency. MSHA records as of Nov 6, 2026. Data and methodology