H C Contractors Crusher
Metal/Non-Metal, Surface·Construction Sand and Gravel·Fairbanks North Star, Alaska·Mine ID 5001890
Operator H C Contractors, Inc·Controller Ukpeagvik Inupiat Corporation; William J Hoople Trust dated 2-25-09·MSHA status Intermittent since Sep 7, 2018
What MSHA has on file for this mine
MSHA records as of Nov 6, 2026. Having MSHA inspection records is common for operating mines. Data and methodology
Inspections
Mine Idle ActivityMay 7 to May 8, 2026Inspectors 1 | Hours on site 1.5Began: May 7, 2026Ended: May 8, 2026Activity: Mine Idle ActivityInspectors: 1Hours on site: 1.5Details
The inspection
- BeganINSPECTION_BEGIN_DT
- May 7, 2026
- Closed outINSPECTION_END_DT
- May 8, 2026
- ActivityACTIVITY
- Mine Idle Activity
- Activity codeACTIVITY_CODE
- E28
- Program areaPROGRAM_AREA
- M/NM--Mine Idle Activity
- Event numberEVENT_NO
- F02C1A8
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 1.5
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 2.5
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller at the timeCONTROLLER_NAME
- Ukpeagvik Inupiat Corporation; William J Hoople Trust dated 2-25-09
- Controller IDCONTROLLER_ID
- 0182020
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2026
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2026
- MSHA fiscal quarterFISCAL_QTR
- 3
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (2)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE
Regular Safety and Health InspectionAug 16 to Aug 17, 2025Inspectors 1 | Hours on site 3.5Began: Aug 16, 2025Ended: Aug 17, 2025Activity: Regular Safety and Health InspectionInspectors: 1Hours on site: 3.5Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Aug 16, 2025
- Closed outINSPECTION_END_DT
- Aug 17, 2025
- ActivityACTIVITY
- Regular Safety and Health Inspection
- Activity codeACTIVITY_CODE
- E01
- Program areaPROGRAM_AREA
- M/NM--Regular Safety and Health Inspection
- Event numberEVENT_NO
- F018836
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 3.5
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 11.5
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller at the timeCONTROLLER_NAME
- Ukpeagvik Inupiat Corporation; William J Hoople Trust dated 2-25-09
- Controller IDCONTROLLER_ID
- 0182020
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2025
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2025
- MSHA fiscal quarterFISCAL_QTR
- 4
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (2)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE
Regular Safety and Health InspectionAug 12, 2024Inspectors 1 | Hours on site 1.75Began: Aug 12, 2024Ended: Aug 12, 2024Activity: Regular Safety and Health InspectionInspectors: 1Hours on site: 1.75Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Aug 12, 2024
- Closed outINSPECTION_END_DT
- Aug 12, 2024
- ActivityACTIVITY
- Regular Safety and Health Inspection
- Activity codeACTIVITY_CODE
- E01
- Program areaPROGRAM_AREA
- M/NM--Regular Safety and Health Inspection
- Event numberEVENT_NO
- F009F81
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 1.75
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 6.75
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller at the timeCONTROLLER_NAME
- Ukpeagvik Inupiat Corporation; William J Hoople Trust dated 2-25-09
- Controller IDCONTROLLER_ID
- 0182020
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2024
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2024
- MSHA fiscal quarterFISCAL_QTR
- 4
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (2)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE
Special Emphasis ProgramsAug 12, 2023Inspectors 1 | Hours on site 0.75Began: Aug 12, 2023Ended: Aug 12, 2023Activity: Special Emphasis ProgramsInspectors: 1Hours on site: 0.75Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Aug 12, 2023
- Closed outINSPECTION_END_DT
- Aug 12, 2023
- ActivityACTIVITY
- Special Emphasis Programs
- Activity codeACTIVITY_CODE
- E17
- Program areaPROGRAM_AREA
- M/NM--Special Emphasis Programs
- Event numberEVENT_NO
- 6876494
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 0.75
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 0.75
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2023
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2023
- MSHA fiscal quarterFISCAL_QTR
- 4
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (3)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME
Regular Safety and Health InspectionAug 11 to Aug 12, 2023Inspectors 1 | Hours on site 7.75Began: Aug 11, 2023Ended: Aug 12, 2023Activity: Regular Safety and Health InspectionInspectors: 1Hours on site: 7.75Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Aug 11, 2023
- Closed outINSPECTION_END_DT
- Aug 12, 2023
- ActivityACTIVITY
- Regular Safety and Health Inspection
- Activity codeACTIVITY_CODE
- E01
- Program areaPROGRAM_AREA
- M/NM--Regular Safety and Health Inspection
- Event numberEVENT_NO
- 6876493
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 7.75
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 16.5
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2023
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2023
- MSHA fiscal quarterFISCAL_QTR
- 4
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (3)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME
Regular Safety and Health InspectionJul 27 to Jul 28, 2022Inspectors 1 | Hours on site 3Began: Jul 27, 2022Ended: Jul 28, 2022Activity: Regular Safety and Health InspectionInspectors: 1Hours on site: 3Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Jul 27, 2022
- Closed outINSPECTION_END_DT
- Jul 28, 2022
- ActivityACTIVITY
- Regular Safety and Health Inspection
- Activity codeACTIVITY_CODE
- E01
- Program areaPROGRAM_AREA
- M/NM--Regular Safety and Health Inspection
- Event numberEVENT_NO
- 6876214
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 3
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 13
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2022
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2022
- MSHA fiscal quarterFISCAL_QTR
- 4
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (3)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME
Verbal Hazard Complaint InspectionsJun 7 to Jun 8, 2022Inspectors 1 | Hours on site 1Began: Jun 7, 2022Ended: Jun 8, 2022Activity: Verbal Hazard Complaint InspectionsInspectors: 1Hours on site: 1Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Jun 7, 2022
- Closed outINSPECTION_END_DT
- Jun 8, 2022
- ActivityACTIVITY
- Verbal Hazard Complaint Inspections
- Activity codeACTIVITY_CODE
- E04
- Program areaPROGRAM_AREA
- M/NM--Verbal Hazard Complaint Inspections
- Event numberEVENT_NO
- 1124147
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 1
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 8.5
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2022
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2022
- MSHA fiscal quarterFISCAL_QTR
- 3
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (3)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME
Mine Idle ActivityJul 15 to Jul 17, 2021Inspectors 1 | Hours on site 0.5Began: Jul 15, 2021Ended: Jul 17, 2021Activity: Mine Idle ActivityInspectors: 1Hours on site: 0.5Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Jul 15, 2021
- Closed outINSPECTION_END_DT
- Jul 17, 2021
- ActivityACTIVITY
- Mine Idle Activity
- Activity codeACTIVITY_CODE
- E28
- Program areaPROGRAM_AREA
- M/NM--Mine Idle Activity
- Event numberEVENT_NO
- 1146538
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 0.5
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 1
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2021
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2021
- MSHA fiscal quarterFISCAL_QTR
- 4
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (3)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME
Regular Safety and Health InspectionJun 25 to Jul 4, 2020Inspectors 1 | Hours on site 10.5Began: Jun 25, 2020Ended: Jul 4, 2020Activity: Regular Safety and Health InspectionInspectors: 1Hours on site: 10.5Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Closed outINSPECTION_END_DT
- Jul 4, 2020
- ActivityACTIVITY
- Regular Safety and Health Inspection
- Activity codeACTIVITY_CODE
- E01
- Program areaPROGRAM_AREA
- M/NM--Regular Safety and Health Inspection
- Event numberEVENT_NO
- 1153973
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 10.5
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 33.75
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 4
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (3)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME
Regular Safety and Health InspectionJul 16 to Jul 18, 2019Inspectors 1 | Hours on site 4.5Began: Jul 16, 2019Ended: Jul 18, 2019Activity: Regular Safety and Health InspectionInspectors: 1Hours on site: 4.5Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Jul 16, 2019
- Closed outINSPECTION_END_DT
- Jul 18, 2019
- ActivityACTIVITY
- Regular Safety and Health Inspection
- Activity codeACTIVITY_CODE
- E01
- Program areaPROGRAM_AREA
- M/NM--Regular Safety and Health Inspection
- Event numberEVENT_NO
- 1124502
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 4.5
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 17.5
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2019
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2019
- MSHA fiscal quarterFISCAL_QTR
- 4
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (3)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME
Mine Idle ActivityAug 14, 2010Inspectors 1 | Hours on site 0.5Began: Aug 14, 2010Ended: Aug 14, 2010Activity: Mine Idle ActivityInspectors: 1Hours on site: 0.5Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Aug 14, 2010
- Closed outINSPECTION_END_DT
- Aug 14, 2010
- ActivityACTIVITY
- Mine Idle Activity
- Activity codeACTIVITY_CODE
- E28
- Program areaPROGRAM_AREA
- M/NM--Mine Idle Activity
- Event numberEVENT_NO
- 1140959
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 0.5
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 8.5
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2010
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2010
- MSHA fiscal quarterFISCAL_QTR
- 4
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (3)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME
Regular Safety and Health InspectionJun 27 to Jun 30, 2009Inspectors 1 | Hours on site 11.25Began: Jun 27, 2009Ended: Jun 30, 2009Activity: Regular Safety and Health InspectionInspectors: 1Hours on site: 11.25Details
The inspection
- BeganINSPECTION_BEGIN_DT
- Jun 27, 2009
- Closed outINSPECTION_END_DT
- Jun 30, 2009
- ActivityACTIVITY
- Regular Safety and Health Inspection
- Activity codeACTIVITY_CODE
- E01
- Program areaPROGRAM_AREA
- M/NM--Regular Safety and Health Inspection
- Event numberEVENT_NO
- 1140781
- InspectorsNBR_INSPECTOR
- 1
- Inspector's office codeINSPECT_OFFICE_CD
- M7861
- Hours on siteSUM_TOTAL_ON_SITE_HOURS
- 11.25
- Total inspection hoursSUM_TOTAL_INSP_HOURS
- 17.25
Who and when, as recorded
- Operator at the timeOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Mine IDMINE_ID
- 5001890
- Calendar yearCAL_YR
- 2009
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2009
- MSHA fiscal quarterFISCAL_QTR
- 3
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Recorded as 0 (13)
Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER
Recorded as N (10)
Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA
Not recorded by MSHA (3)
Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME
12 inspections and other MSHA visits since Jun 27, 2009; activity names are MSHA's own text. Full list: MSHA Mine Data Retrieval System.
Citations and orders
Issued: May 7, 2026Type: CitationStandard: 56.1000S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: None recordedDetails
The citation
- Citation or order numberVIOLATION_NO
- 9687717
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- May 7, 2026
- Time issuedVIOLATION_ISSUE_TIME
- 1315
- Date of occurrenceVIOLATION_OCCUR_DT
- May 7, 2026
- 30 CFR part and sectionPART_SECTION
- 56.1000
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- NoLikelihood
- Expected injury or illnessINJ_ILLNESS
- NoLostDays
- NegligenceNEGLIGENCE
- ModNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- May 14, 2026
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- May 14, 2026
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- May 7, 2026
- Terminated, timeTERMINATION_TIME
- 1607
- Termination typeTERMINATION_TYPE
- Terminated
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller at the timeCONTROLLER_NAME
- Ukpeagvik Inupiat Corporation; William J Hoople Trust dated 2-25-09
- Controller IDCONTROLLER_ID
- 0182020
- Inspection eventEVENT_NO
- F02C1A8
- Inspection beganINSPECTION_BEGIN_DT
- May 7, 2026
- Inspection closed outINSPECTION_END_DT
- May 8, 2026
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2026
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2026
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as 0 (1)
Persons potentially affectedNO_AFFECTED
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (21)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Proposed penaltyPROPOSED_PENALTY, Current proposed assessmentAMOUNT_DUE, Amount paidAMOUNT_PAID, Bill first printedBILL_PRINT_DT, Final order dateFINAL_ORDER_ISSUE_DT, Last actionLAST_ACTION_CD, Last action dateLAST_ACTION_DT, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Contractor IDCONTRACTOR_ID
Issued: Aug 16, 2025Type: CitationStandard: 56.14107(a)S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: None recordedDetails
The citation
- Citation or order numberVIOLATION_NO
- 9687579
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Aug 16, 2025
- Time issuedVIOLATION_ISSUE_TIME
- 1433
- Date of occurrenceVIOLATION_OCCUR_DT
- Aug 16, 2025
- 30 CFR part and sectionPART_SECTION
- 56.14107(a)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Permanent
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Aug 16, 2025
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Aug 16, 2025
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Aug 16, 2025
- Terminated, timeTERMINATION_TIME
- 1545
- Termination typeTERMINATION_TYPE
- Terminated
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller at the timeCONTROLLER_NAME
- Ukpeagvik Inupiat Corporation; William J Hoople Trust dated 2-25-09
- Controller IDCONTROLLER_ID
- 0182020
- Inspection eventEVENT_NO
- F018836
- Inspection beganINSPECTION_BEGIN_DT
- Aug 16, 2025
- Inspection closed outINSPECTION_END_DT
- Aug 17, 2025
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2025
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2025
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (21)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Proposed penaltyPROPOSED_PENALTY, Current proposed assessmentAMOUNT_DUE, Amount paidAMOUNT_PAID, Bill first printedBILL_PRINT_DT, Final order dateFINAL_ORDER_ISSUE_DT, Last actionLAST_ACTION_CD, Last action dateLAST_ACTION_DT, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Contractor IDCONTRACTOR_ID
Issued: Aug 12, 2024Type: CitationStandard: 56.4201(a)(2)S&S: NNegligence: LowNegligenceIssued to: OperatorProposed penalty: $147.00Details
The citation
- Citation or order numberVIOLATION_NO
- 9687852
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Aug 12, 2024
- Time issuedVIOLATION_ISSUE_TIME
- 1723
- Date of occurrenceVIOLATION_OCCUR_DT
- Aug 12, 2024
- 30 CFR part and sectionPART_SECTION
- 56.4201(a)(2)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- LostDays
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- LowNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Aug 12, 2024
- Originally due, timeORIG_TERM_DUE_TIME
- 1800
- Latest dueLATEST_TERM_DUE_DT
- Aug 12, 2024
- Latest due, timeLATEST_TERM_DUE_TIME
- 1800
- TerminatedTERMINATION_DT
- Aug 12, 2024
- Terminated, timeTERMINATION_TIME
- 1730
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 147
- Current proposed assessmentAMOUNT_DUE
- 147
- Amount paidAMOUNT_PAID
- 147
- Bill first printedBILL_PRINT_DT
- Oct 3, 2024
- Final order dateFINAL_ORDER_ISSUE_DT
- Nov 14, 2024
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Nov 10, 2024
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 8
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 2
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller at the timeCONTROLLER_NAME
- Ukpeagvik Inupiat Corporation; William J Hoople Trust dated 2-25-09
- Controller IDCONTROLLER_ID
- 0182020
- Inspection eventEVENT_NO
- F009F81
- Inspection beganINSPECTION_BEGIN_DT
- Aug 12, 2024
- Inspection closed outINSPECTION_END_DT
- Aug 12, 2024
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2024
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2024
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (12)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID
Issued: Aug 11, 2023Type: CitationStandard: 56.14112(b)S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $143.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6563331
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Aug 11, 2023
- Time issuedVIOLATION_ISSUE_TIME
- 1539
- Date of occurrenceVIOLATION_OCCUR_DT
- Aug 11, 2023
- 30 CFR part and sectionPART_SECTION
- 56.14112(b)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Permanent
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- ModNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Aug 11, 2023
- Originally due, timeORIG_TERM_DUE_TIME
- 1800
- Latest dueLATEST_TERM_DUE_DT
- Aug 11, 2023
- Latest due, timeLATEST_TERM_DUE_TIME
- 1800
- TerminatedTERMINATION_DT
- Aug 11, 2023
- Terminated, timeTERMINATION_TIME
- 1550
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 143
- Current proposed assessmentAMOUNT_DUE
- 143
- Amount paidAMOUNT_PAID
- 143
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Final order dateFINAL_ORDER_ISSUE_DT
- Nov 11, 2023
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Nov 5, 2023
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 6876493
- Inspection beganINSPECTION_BEGIN_DT
- Aug 11, 2023
- Inspection closed outINSPECTION_END_DT
- Aug 12, 2023
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2023
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2023
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Aug 11, 2023Type: CitationStandard: 56.18002(a)S&S: YNegligence: ModNegligenceIssued to: OperatorProposed penalty: $182.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6563332
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Aug 11, 2023
- Time issuedVIOLATION_ISSUE_TIME
- 1650
- Date of occurrenceVIOLATION_OCCUR_DT
- Aug 11, 2023
- 30 CFR part and sectionPART_SECTION
- 56.18002(a)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- Significant and substantialSIG_SUB
- Y
- LikelihoodLIKELIHOOD
- Reasonably
- Expected injury or illnessINJ_ILLNESS
- LostDays
- Persons potentially affectedNO_AFFECTED
- 5
- NegligenceNEGLIGENCE
- ModNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Aug 12, 2023
- Originally due, timeORIG_TERM_DUE_TIME
- 0630
- Latest dueLATEST_TERM_DUE_DT
- Aug 12, 2023
- Latest due, timeLATEST_TERM_DUE_TIME
- 0630
- TerminatedTERMINATION_DT
- Aug 12, 2023
- Terminated, timeTERMINATION_TIME
- 1219
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 182
- Current proposed assessmentAMOUNT_DUE
- 182
- Amount paidAMOUNT_PAID
- 182
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Final order dateFINAL_ORDER_ISSUE_DT
- Nov 11, 2023
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Nov 5, 2023
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 6876493
- Inspection beganINSPECTION_BEGIN_DT
- Aug 11, 2023
- Inspection closed outINSPECTION_END_DT
- Aug 12, 2023
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2023
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2023
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as N (4)
From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Aug 11, 2023Type: CitationStandard: 56.20003(a)S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $143.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6563330
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Aug 11, 2023
- Time issuedVIOLATION_ISSUE_TIME
- 1518
- Date of occurrenceVIOLATION_OCCUR_DT
- Aug 11, 2023
- 30 CFR part and sectionPART_SECTION
- 56.20003(a)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- LostDays
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- ModNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Aug 11, 2023
- Originally due, timeORIG_TERM_DUE_TIME
- 1530
- Latest dueLATEST_TERM_DUE_DT
- Aug 11, 2023
- Latest due, timeLATEST_TERM_DUE_TIME
- 1530
- TerminatedTERMINATION_DT
- Aug 11, 2023
- Terminated, timeTERMINATION_TIME
- 1528
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 143
- Current proposed assessmentAMOUNT_DUE
- 143
- Amount paidAMOUNT_PAID
- 143
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Final order dateFINAL_ORDER_ISSUE_DT
- Nov 11, 2023
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Nov 5, 2023
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 6876493
- Inspection beganINSPECTION_BEGIN_DT
- Aug 11, 2023
- Inspection closed outINSPECTION_END_DT
- Aug 12, 2023
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2023
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2023
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Aug 11, 2023Type: CitationStandard: 56.12008S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $143.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6563327
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Aug 11, 2023
- Time issuedVIOLATION_ISSUE_TIME
- 1403
- Date of occurrenceVIOLATION_OCCUR_DT
- Aug 11, 2023
- 30 CFR part and sectionPART_SECTION
- 56.12008
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Fatal
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- ModNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Aug 12, 2023
- Originally due, timeORIG_TERM_DUE_TIME
- 1200
- Latest dueLATEST_TERM_DUE_DT
- Aug 12, 2023
- Latest due, timeLATEST_TERM_DUE_TIME
- 1200
- TerminatedTERMINATION_DT
- Aug 12, 2023
- Terminated, timeTERMINATION_TIME
- 1217
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 143
- Current proposed assessmentAMOUNT_DUE
- 143
- Amount paidAMOUNT_PAID
- 143
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Final order dateFINAL_ORDER_ISSUE_DT
- Nov 11, 2023
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Nov 5, 2023
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 6876493
- Inspection beganINSPECTION_BEGIN_DT
- Aug 11, 2023
- Inspection closed outINSPECTION_END_DT
- Aug 12, 2023
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2023
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2023
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Aug 11, 2023Type: CitationStandard: 56.9300(a)S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $143.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6563325
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Aug 11, 2023
- Time issuedVIOLATION_ISSUE_TIME
- 1259
- Date of occurrenceVIOLATION_OCCUR_DT
- Aug 11, 2023
- 30 CFR part and sectionPART_SECTION
- 56.9300(a)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Permanent
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Aug 11, 2023
- Originally due, timeORIG_TERM_DUE_TIME
- 1800
- Latest dueLATEST_TERM_DUE_DT
- Aug 11, 2023
- Latest due, timeLATEST_TERM_DUE_TIME
- 1800
- TerminatedTERMINATION_DT
- Aug 11, 2023
- Terminated, timeTERMINATION_TIME
- 1655
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 143
- Current proposed assessmentAMOUNT_DUE
- 143
- Amount paidAMOUNT_PAID
- 143
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Final order dateFINAL_ORDER_ISSUE_DT
- Nov 11, 2023
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Nov 5, 2023
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 6876493
- Inspection beganINSPECTION_BEGIN_DT
- Aug 11, 2023
- Inspection closed outINSPECTION_END_DT
- Aug 12, 2023
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2023
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2023
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Aug 11, 2023Type: CitationStandard: 56.12032S&S: NNegligence: LowNegligenceIssued to: OperatorProposed penalty: $143.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6563328
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Aug 11, 2023
- Time issuedVIOLATION_ISSUE_TIME
- 1415
- Date of occurrenceVIOLATION_OCCUR_DT
- Aug 11, 2023
- 30 CFR part and sectionPART_SECTION
- 56.12032
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Fatal
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- LowNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Aug 11, 2023
- Originally due, timeORIG_TERM_DUE_TIME
- 1800
- Latest dueLATEST_TERM_DUE_DT
- Aug 11, 2023
- Latest due, timeLATEST_TERM_DUE_TIME
- 1800
- TerminatedTERMINATION_DT
- Aug 11, 2023
- Terminated, timeTERMINATION_TIME
- 1500
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 143
- Current proposed assessmentAMOUNT_DUE
- 143
- Amount paidAMOUNT_PAID
- 143
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Final order dateFINAL_ORDER_ISSUE_DT
- Nov 11, 2023
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Nov 5, 2023
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 6876493
- Inspection beganINSPECTION_BEGIN_DT
- Aug 11, 2023
- Inspection closed outINSPECTION_END_DT
- Aug 12, 2023
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2023
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2023
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Aug 11, 2023Type: CitationStandard: 56.4201(a)(2)S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $143.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6563329
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Aug 11, 2023
- Time issuedVIOLATION_ISSUE_TIME
- 1501
- Date of occurrenceVIOLATION_OCCUR_DT
- Aug 11, 2023
- 30 CFR part and sectionPART_SECTION
- 56.4201(a)(2)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- LostDays
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- ModNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Aug 11, 2023
- Originally due, timeORIG_TERM_DUE_TIME
- 1525
- Latest dueLATEST_TERM_DUE_DT
- Aug 11, 2023
- Latest due, timeLATEST_TERM_DUE_TIME
- 1525
- TerminatedTERMINATION_DT
- Aug 11, 2023
- Terminated, timeTERMINATION_TIME
- 1510
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 143
- Current proposed assessmentAMOUNT_DUE
- 143
- Amount paidAMOUNT_PAID
- 143
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Final order dateFINAL_ORDER_ISSUE_DT
- Nov 11, 2023
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Nov 5, 2023
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 6876493
- Inspection beganINSPECTION_BEGIN_DT
- Aug 11, 2023
- Inspection closed outINSPECTION_END_DT
- Aug 12, 2023
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2023
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2023
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Aug 11, 2023Type: CitationStandard: 56.14112(b)S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $143.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6563326
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Aug 11, 2023
- Time issuedVIOLATION_ISSUE_TIME
- 1350
- Date of occurrenceVIOLATION_OCCUR_DT
- Aug 11, 2023
- 30 CFR part and sectionPART_SECTION
- 56.14112(b)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Permanent
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- ModNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Aug 11, 2023
- Originally due, timeORIG_TERM_DUE_TIME
- 1800
- Latest dueLATEST_TERM_DUE_DT
- Aug 11, 2023
- Latest due, timeLATEST_TERM_DUE_TIME
- 1800
- TerminatedTERMINATION_DT
- Aug 11, 2023
- Terminated, timeTERMINATION_TIME
- 1430
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 143
- Current proposed assessmentAMOUNT_DUE
- 143
- Amount paidAMOUNT_PAID
- 143
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Final order dateFINAL_ORDER_ISSUE_DT
- Nov 11, 2023
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Nov 5, 2023
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 6876493
- Inspection beganINSPECTION_BEGIN_DT
- Aug 11, 2023
- Inspection closed outINSPECTION_END_DT
- Aug 12, 2023
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2023
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2023
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jul 28, 2022Type: OrderStandard: 46.5S&S: YNegligence: ModNegligenceIssued to: OperatorProposed penalty: $357.00Details
The citation
- Citation or order numberVIOLATION_NO
- 9615231
- TypeCIT_ORD_SAFE
- Order
- IssuedVIOLATION_ISSUE_DT
- Jul 28, 2022
- Time issuedVIOLATION_ISSUE_TIME
- 1107
- Date of occurrenceVIOLATION_OCCUR_DT
- Jul 28, 2022
- 30 CFR part and sectionPART_SECTION
- 46.5
- Section of the Act, primarySECTION_OF_ACT_1
- 104(g)(1)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- Significant and substantialSIG_SUB
- Y
- LikelihoodLIKELIHOOD
- Reasonably
- Expected injury or illnessINJ_ILLNESS
- Fatal
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- ModNegligence
- Special assessmentSPECIAL_ASSESS
- Y
Abatement
- TerminatedTERMINATION_DT
- Oct 27, 2022
- Terminated, timeTERMINATION_TIME
- 2030
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 357
- Current proposed assessmentAMOUNT_DUE
- 357
- Amount paidAMOUNT_PAID
- 357
- Bill first printedBILL_PRINT_DT
- Sep 1, 2022
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 10, 2022
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 22, 2022
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 6876214
- Inspection beganINSPECTION_BEGIN_DT
- Jul 27, 2022
- Inspection closed outINSPECTION_END_DT
- Jul 28, 2022
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2022
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2022
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as 0 (1)
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
Recorded as N (3)
From a 103(g) written noticeWRITTEN_NOTICE, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (17)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, Originally dueORIG_TERM_DUE_DT, Originally due, timeORIG_TERM_DUE_TIME, Latest dueLATEST_TERM_DUE_DT, Latest due, timeLATEST_TERM_DUE_TIME, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jul 28, 2022Type: CitationStandard: 56.14100(a)S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $133.00Details
The citation
- Citation or order numberVIOLATION_NO
- 9615232
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jul 28, 2022
- Time issuedVIOLATION_ISSUE_TIME
- 1113
- Date of occurrenceVIOLATION_OCCUR_DT
- Jul 28, 2022
- 30 CFR part and sectionPART_SECTION
- 56.14100(a)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- LostDays
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jul 28, 2022
- Originally due, timeORIG_TERM_DUE_TIME
- 1200
- Latest dueLATEST_TERM_DUE_DT
- Jul 28, 2022
- Latest due, timeLATEST_TERM_DUE_TIME
- 1200
- TerminatedTERMINATION_DT
- Jul 28, 2022
- Terminated, timeTERMINATION_TIME
- 1137
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 133
- Current proposed assessmentAMOUNT_DUE
- 133
- Amount paidAMOUNT_PAID
- 133
- Bill first printedBILL_PRINT_DT
- Sep 1, 2022
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 10, 2022
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 22, 2022
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 6876214
- Inspection beganINSPECTION_BEGIN_DT
- Jul 27, 2022
- Inspection closed outINSPECTION_END_DT
- Jul 28, 2022
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2022
- Calendar quarterCAL_QTR
- 3
- MSHA fiscal yearFISCAL_YR
- 2022
- MSHA fiscal quarterFISCAL_QTR
- 4
Recorded as 0 (1)
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.12004S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $199.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392506
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1029
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.12004
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Fatal
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 30, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Jun 30, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1646
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 199
- Current proposed assessmentAMOUNT_DUE
- 199
- Amount paidAMOUNT_PAID
- 199
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.9300(b)S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $123.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392509
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1041
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.9300(b)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Permanent
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 30, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Jun 30, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1643
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 123
- Current proposed assessmentAMOUNT_DUE
- 123
- Amount paidAMOUNT_PAID
- 123
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.12032S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $199.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392514
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1106
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.12032
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Fatal
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 30, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Jun 30, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1648
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 199
- Current proposed assessmentAMOUNT_DUE
- 199
- Amount paidAMOUNT_PAID
- 199
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.16005S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $123.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392508
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1037
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.16005
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- LostDays
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 30, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Jun 30, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1625
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 123
- Current proposed assessmentAMOUNT_DUE
- 123
- Amount paidAMOUNT_PAID
- 123
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.12032S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $123.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392507
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1036
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.12032
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- LostDays
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 30, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Jun 30, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1643
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 123
- Current proposed assessmentAMOUNT_DUE
- 123
- Amount paidAMOUNT_PAID
- 123
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.14107(a)S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $123.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392511
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1050
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.14107(a)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Permanent
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 30, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Jun 30, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1643
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 123
- Current proposed assessmentAMOUNT_DUE
- 123
- Amount paidAMOUNT_PAID
- 123
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.14107(a)S&S: YNegligence: HighNegligenceIssued to: OperatorProposed penalty: $994.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392515
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1108
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.14107(a)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- Significant and substantialSIG_SUB
- Y
- LikelihoodLIKELIHOOD
- Reasonably
- Expected injury or illnessINJ_ILLNESS
- Fatal
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 25, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1113
- Latest dueLATEST_TERM_DUE_DT
- Jun 25, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1113
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1643
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 994
- Current proposed assessmentAMOUNT_DUE
- 994
- Amount paidAMOUNT_PAID
- 994
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (4)
From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.12008S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $199.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392512
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1053
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.12008
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Fatal
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 30, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Jun 30, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1641
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 199
- Current proposed assessmentAMOUNT_DUE
- 199
- Amount paidAMOUNT_PAID
- 199
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.11001S&S: YNegligence: HighNegligenceIssued to: OperatorProposed penalty: $298.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392517
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1125
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.11001
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- Significant and substantialSIG_SUB
- Y
- LikelihoodLIKELIHOOD
- Reasonably
- Expected injury or illnessINJ_ILLNESS
- LostDays
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 30, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Jun 30, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1643
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 298
- Current proposed assessmentAMOUNT_DUE
- 298
- Amount paidAMOUNT_PAID
- 298
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (4)
From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.14112(b)S&S: YNegligence: HighNegligenceIssued to: OperatorProposed penalty: $994.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392516
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1123
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.14112(b)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- Significant and substantialSIG_SUB
- Y
- LikelihoodLIKELIHOOD
- Reasonably
- Expected injury or illnessINJ_ILLNESS
- Fatal
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 25, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1128
- Latest dueLATEST_TERM_DUE_DT
- Jun 25, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1128
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1650
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 994
- Current proposed assessmentAMOUNT_DUE
- 994
- Amount paidAMOUNT_PAID
- 994
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (4)
From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.11002S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $123.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392510
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1044
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.11002
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Permanent
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 30, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Jun 30, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1636
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 123
- Current proposed assessmentAMOUNT_DUE
- 123
- Amount paidAMOUNT_PAID
- 123
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
Issued: Jun 25, 2020Type: CitationStandard: 56.14107(a)S&S: NNegligence: HighNegligenceIssued to: OperatorProposed penalty: $123.00Details
The citation
- Citation or order numberVIOLATION_NO
- 6392513
- TypeCIT_ORD_SAFE
- Citation
- IssuedVIOLATION_ISSUE_DT
- Jun 25, 2020
- Time issuedVIOLATION_ISSUE_TIME
- 1055
- Date of occurrenceVIOLATION_OCCUR_DT
- Jun 25, 2020
- 30 CFR part and sectionPART_SECTION
- 56.14107(a)
- Section of the Act, primarySECTION_OF_ACT_1
- 104(a)
- Primary mine or millPRIMARY_OR_MILL
- Primary
Gravity and negligence, as the inspector recorded them
- LikelihoodLIKELIHOOD
- Unlikely
- Expected injury or illnessINJ_ILLNESS
- Permanent
- Persons potentially affectedNO_AFFECTED
- 1
- NegligenceNEGLIGENCE
- HighNegligence
Abatement
- Originally dueORIG_TERM_DUE_DT
- Jun 30, 2020
- Originally due, timeORIG_TERM_DUE_TIME
- 1700
- Latest dueLATEST_TERM_DUE_DT
- Jun 30, 2020
- Latest due, timeLATEST_TERM_DUE_TIME
- 1700
- TerminatedTERMINATION_DT
- Jun 30, 2020
- Terminated, timeTERMINATION_TIME
- 1641
- Termination typeTERMINATION_TYPE
- Terminated
Penalty and contest
- Proposed penaltyPROPOSED_PENALTY
- 123
- Current proposed assessmentAMOUNT_DUE
- 123
- Amount paidAMOUNT_PAID
- 123
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Final order dateFINAL_ORDER_ISSUE_DT
- Oct 13, 2020
- Last actionLAST_ACTION_CD
- Paid
- Last action dateLAST_ACTION_DT
- Sep 14, 2020
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
Who, inspection and period
- Issued toVIOLATOR_TYPE_CD
- Operator
- Operator at the timeVIOLATOR_NAME
- H C Contractors, Inc
- Operator IDVIOLATOR_ID
- 0093385
- Controller IDCONTROLLER_ID
- 0040850
- Inspection eventEVENT_NO
- 1153973
- Inspection beganINSPECTION_BEGIN_DT
- Jun 25, 2020
- Inspection closed outINSPECTION_END_DT
- Jul 4, 2020
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine type in this fileMINE_TYPE
- Surface
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Calendar yearCAL_YR
- 2020
- Calendar quarterCAL_QTR
- 2
- MSHA fiscal yearFISCAL_YR
- 2020
- MSHA fiscal quarterFISCAL_QTR
- 3
Recorded as N (5)
From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND
Not recorded by MSHA (13)
Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME
32 citations and orders since Jun 27, 2009: 32 issued to the operator, 0 to contractors working at the mine; the 25 most recent are listed. Proposed penalty is MSHA's original proposed amount, before any change from a contested case. Citations can be contested, modified or vacated.
Penalties as assessed
Issued: Aug 12, 2024Citation number: 9687852Standard: 56.4201(a)(2)Proposed penalty: $147.00Current assessment: $147.00Paid against proposed penalty: $147.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 9687852
- Assessment control numberASSESS_CASE_NO
- 000604444
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Nov 8, 2024
- Citation issuedISSUE_DT
- Aug 12, 2024
- Date of occurrenceOCCURRENCE_DT
- Aug 12, 2024
- Final order dateFINAL_ORDER_DT
- Nov 14, 2024
- Bill first printedBILL_PRINT_DT
- Oct 3, 2024
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2025
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Nov 14, 2024
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.4201(a)(2)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 147.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 147.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 147.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 27
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 5
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 10
- Mine size pointsMINE_SIZE_POINTS
- 1
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 8
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 2
- Violations per inspection dayVPID
- 4
- Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
- 1
- Repeat violations per inspection dayRPID
- 0.5
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 6356
- Size of mineSIZE_OF_MINE
- 6356
- Controller hours workedCONTROLLER_HRS
- 10078
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 10078
- History period startHISTORY_START_DT
- May 12, 2023
- History period endHISTORY_END_DT
- Aug 11, 2024
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- F009F81
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (11)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Aug 11, 2023Citation number: 6563326Standard: 56.14112(b)Proposed penalty: $143.00Current assessment: $143.00Paid against proposed penalty: $143.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6563326
- Assessment control numberASSESS_CASE_NO
- 000586489
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Nov 3, 2023
- Citation issuedISSUE_DT
- Aug 11, 2023
- Date of occurrenceOCCURRENCE_DT
- Aug 11, 2023
- Final order dateFINAL_ORDER_DT
- Nov 11, 2023
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2024
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Nov 11, 2023
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.14112(b)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 143.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 143.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 143.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 41
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 10
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 20
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 2
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 1928
- Size of mineSIZE_OF_MINE
- 1928
- Controller hours workedCONTROLLER_HRS
- 4900
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 4900
- History period startHISTORY_START_DT
- May 11, 2022
- History period endHISTORY_END_DT
- Aug 10, 2023
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 6876493
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Aug 11, 2023Citation number: 6563328Standard: 56.12032Proposed penalty: $143.00Current assessment: $143.00Paid against proposed penalty: $143.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6563328
- Assessment control numberASSESS_CASE_NO
- 000586489
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Nov 3, 2023
- Citation issuedISSUE_DT
- Aug 11, 2023
- Date of occurrenceOCCURRENCE_DT
- Aug 11, 2023
- Final order dateFINAL_ORDER_DT
- Nov 11, 2023
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2024
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Nov 11, 2023
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.12032
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 143.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 143.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 143.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 41
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 20
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 10
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 2
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 1928
- Size of mineSIZE_OF_MINE
- 1928
- Controller hours workedCONTROLLER_HRS
- 4900
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 4900
- History period startHISTORY_START_DT
- May 11, 2022
- History period endHISTORY_END_DT
- Aug 10, 2023
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 6876493
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Aug 11, 2023Citation number: 6563329Standard: 56.4201(a)(2)Proposed penalty: $143.00Current assessment: $143.00Paid against proposed penalty: $143.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6563329
- Assessment control numberASSESS_CASE_NO
- 000586489
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Nov 3, 2023
- Citation issuedISSUE_DT
- Aug 11, 2023
- Date of occurrenceOCCURRENCE_DT
- Aug 11, 2023
- Final order dateFINAL_ORDER_DT
- Nov 11, 2023
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2024
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Nov 11, 2023
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.4201(a)(2)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 143.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 143.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 143.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 36
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 5
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 20
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 2
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 1928
- Size of mineSIZE_OF_MINE
- 1928
- Controller hours workedCONTROLLER_HRS
- 4900
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 4900
- History period startHISTORY_START_DT
- May 11, 2022
- History period endHISTORY_END_DT
- Aug 10, 2023
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 6876493
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Aug 11, 2023Citation number: 6563325Standard: 56.9300(a)Proposed penalty: $143.00Current assessment: $143.00Paid against proposed penalty: $143.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6563325
- Assessment control numberASSESS_CASE_NO
- 000586489
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Nov 3, 2023
- Citation issuedISSUE_DT
- Aug 11, 2023
- Date of occurrenceOCCURRENCE_DT
- Aug 11, 2023
- Final order dateFINAL_ORDER_DT
- Nov 11, 2023
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2024
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Nov 11, 2023
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.9300(a)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 143.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 143.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 143.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 56
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 10
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 2
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 1928
- Size of mineSIZE_OF_MINE
- 1928
- Controller hours workedCONTROLLER_HRS
- 4900
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 4900
- History period startHISTORY_START_DT
- May 11, 2022
- History period endHISTORY_END_DT
- Aug 10, 2023
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 6876493
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Aug 11, 2023Citation number: 6563327Standard: 56.12008Proposed penalty: $143.00Current assessment: $143.00Paid against proposed penalty: $143.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6563327
- Assessment control numberASSESS_CASE_NO
- 000586489
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Nov 3, 2023
- Citation issuedISSUE_DT
- Aug 11, 2023
- Date of occurrenceOCCURRENCE_DT
- Aug 11, 2023
- Final order dateFINAL_ORDER_DT
- Nov 11, 2023
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2024
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Nov 11, 2023
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.12008
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 143.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 143.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 143.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 51
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 20
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 20
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 2
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 1928
- Size of mineSIZE_OF_MINE
- 1928
- Controller hours workedCONTROLLER_HRS
- 4900
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 4900
- History period startHISTORY_START_DT
- May 11, 2022
- History period endHISTORY_END_DT
- Aug 10, 2023
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 6876493
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Aug 11, 2023Citation number: 6563331Standard: 56.14112(b)Proposed penalty: $143.00Current assessment: $143.00Paid against proposed penalty: $143.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6563331
- Assessment control numberASSESS_CASE_NO
- 000586489
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Nov 3, 2023
- Citation issuedISSUE_DT
- Aug 11, 2023
- Date of occurrenceOCCURRENCE_DT
- Aug 11, 2023
- Final order dateFINAL_ORDER_DT
- Nov 11, 2023
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2024
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Nov 11, 2023
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.14112(b)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 143.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 143.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 143.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 41
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 10
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 20
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 2
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 1928
- Size of mineSIZE_OF_MINE
- 1928
- Controller hours workedCONTROLLER_HRS
- 4900
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 4900
- History period startHISTORY_START_DT
- May 11, 2022
- History period endHISTORY_END_DT
- Aug 10, 2023
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 6876493
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Aug 11, 2023Citation number: 6563332Standard: 56.18002(a)Proposed penalty: $182.00Current assessment: $182.00Paid against proposed penalty: $182.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6563332
- Assessment control numberASSESS_CASE_NO
- 000586489
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Nov 3, 2023
- Citation issuedISSUE_DT
- Aug 11, 2023
- Date of occurrenceOCCURRENCE_DT
- Aug 11, 2023
- Final order dateFINAL_ORDER_DT
- Nov 11, 2023
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2024
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Nov 11, 2023
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.18002(a)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Significant and substantialSIG_SUB_IND
- Y
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 182.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 182.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 182.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 63
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 8
- Injury severity pointsGRAVITY_INJURY_POINTS
- 5
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 30
- Negligence pointsNEGLIGENCE_POINTS
- 20
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 2
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 1928
- Size of mineSIZE_OF_MINE
- 1928
- Controller hours workedCONTROLLER_HRS
- 4900
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 4900
- History period startHISTORY_START_DT
- May 11, 2022
- History period endHISTORY_END_DT
- Aug 10, 2023
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 6876493
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (1)
Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Aug 11, 2023Citation number: 6563330Standard: 56.20003(a)Proposed penalty: $143.00Current assessment: $143.00Paid against proposed penalty: $143.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6563330
- Assessment control numberASSESS_CASE_NO
- 000586489
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Nov 3, 2023
- Citation issuedISSUE_DT
- Aug 11, 2023
- Date of occurrenceOCCURRENCE_DT
- Aug 11, 2023
- Final order dateFINAL_ORDER_DT
- Nov 11, 2023
- Bill first printedBILL_PRINT_DT
- Oct 5, 2023
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2024
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Nov 11, 2023
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.20003(a)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 143.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 143.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 143.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 36
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 5
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 20
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 2
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 2
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 1928
- Size of mineSIZE_OF_MINE
- 1928
- Controller hours workedCONTROLLER_HRS
- 4900
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 4900
- History period startHISTORY_START_DT
- May 11, 2022
- History period endHISTORY_END_DT
- Aug 10, 2023
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 6876493
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jul 28, 2022Citation number: 9615232Standard: 56.14100(a)Proposed penalty: $133.00Current assessment: $133.00Paid against proposed penalty: $133.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 9615232
- Assessment control numberASSESS_CASE_NO
- 000562138
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 22, 2022
- Citation issuedISSUE_DT
- Jul 28, 2022
- Date of occurrenceOCCURRENCE_DT
- Jul 28, 2022
- Final order dateFINAL_ORDER_DT
- Oct 10, 2022
- Bill first printedBILL_PRINT_DT
- Sep 1, 2022
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2022
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 10, 2022
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.14100(a)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 133.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 133.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 133.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 51
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 5
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 1495
- Size of mineSIZE_OF_MINE
- 1495
- Controller hours workedCONTROLLER_HRS
- 4964
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 4964
- History period startHISTORY_START_DT
- Apr 28, 2021
- History period endHISTORY_END_DT
- Jul 27, 2022
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 6876214
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (16)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jul 28, 2022Citation number: 9615231Standard: 46.5Proposed penalty: $357.00Current assessment: $357.00Paid against proposed penalty: $357.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 9615231
- Assessment control numberASSESS_CASE_NO
- 000562138
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 22, 2022
- Citation issuedISSUE_DT
- Jul 28, 2022
- Date of occurrenceOCCURRENCE_DT
- Jul 28, 2022
- Final order dateFINAL_ORDER_DT
- Oct 10, 2022
- Bill first printedBILL_PRINT_DT
- Sep 1, 2022
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2022
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 10, 2022
- Citation typeCITATION_TYPE_CD
- Order
- 30 CFR standardCFR_STANDARD_CD
- 46.5
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(g)(1)
- Significant and substantialSIG_SUB_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 357.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 357.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 357.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 71
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 20
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 30
- Negligence pointsNEGLIGENCE_POINTS
- 20
Inputs to the penalty calculation
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 1495
- Size of mineSIZE_OF_MINE
- 1495
- Controller hours workedCONTROLLER_HRS
- 4964
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 4964
- History period startHISTORY_START_DT
- Apr 28, 2021
- History period endHISTORY_END_DT
- Jul 27, 2022
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 6876214
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (16)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Good faith reduction appliedGOOD_FAITH_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392506Standard: 56.12004Proposed penalty: $199.00Current assessment: $199.00Paid against proposed penalty: $199.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392506
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.12004
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 199.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 199.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 199.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 66
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 20
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392516Standard: 56.14112(b)Proposed penalty: $994.00Current assessment: $994.00Paid against proposed penalty: $994.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392516
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.14112(b)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Significant and substantialSIG_SUB_IND
- Y
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 994.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 994.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 994.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 86
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 20
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 30
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
- 1
- Repeat violations per inspection dayRPID
- 1
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (12)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (1)
Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392514Standard: 56.12032Proposed penalty: $199.00Current assessment: $199.00Paid against proposed penalty: $199.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392514
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.12032
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 199.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 199.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 199.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 66
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 20
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392507Standard: 56.12032Proposed penalty: $123.00Current assessment: $123.00Paid against proposed penalty: $123.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392507
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.12032
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 123.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 123.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 123.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 51
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 5
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392515Standard: 56.14107(a)Proposed penalty: $994.00Current assessment: $994.00Paid against proposed penalty: $994.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392515
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.14107(a)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Significant and substantialSIG_SUB_IND
- Y
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 994.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 994.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 994.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 86
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 20
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 30
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (1)
Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392512Standard: 56.12008Proposed penalty: $199.00Current assessment: $199.00Paid against proposed penalty: $199.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392512
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.12008
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 199.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 199.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 199.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 66
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 20
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
- 1
- Repeat violations per inspection dayRPID
- 1
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (12)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392509Standard: 56.9300(b)Proposed penalty: $123.00Current assessment: $123.00Paid against proposed penalty: $123.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392509
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.9300(b)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 123.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 123.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 123.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 56
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 10
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392517Standard: 56.11001Proposed penalty: $298.00Current assessment: $298.00Paid against proposed penalty: $298.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392517
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.11001
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Significant and substantialSIG_SUB_IND
- Y
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 298.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 298.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 298.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 71
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 5
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 30
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (1)
Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392508Standard: 56.16005Proposed penalty: $123.00Current assessment: $123.00Paid against proposed penalty: $123.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392508
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.16005
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 123.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 123.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 123.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 51
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 5
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
- 1
- Repeat violations per inspection dayRPID
- 1
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (12)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392513Standard: 56.14107(a)Proposed penalty: $123.00Current assessment: $123.00Paid against proposed penalty: $123.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392513
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.14107(a)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 123.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 123.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 123.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 56
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 10
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392510Standard: 56.11002Proposed penalty: $123.00Current assessment: $123.00Paid against proposed penalty: $123.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392510
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.11002
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 123.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 123.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 123.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 56
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 10
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jun 25, 2020Citation number: 6392511Standard: 56.14107(a)Proposed penalty: $123.00Current assessment: $123.00Paid against proposed penalty: $123.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6392511
- Assessment control numberASSESS_CASE_NO
- 000520205
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Sep 14, 2020
- Citation issuedISSUE_DT
- Jun 25, 2020
- Date of occurrenceOCCURRENCE_DT
- Jun 25, 2020
- Final order dateFINAL_ORDER_DT
- Oct 13, 2020
- Bill first printedBILL_PRINT_DT
- Aug 11, 2020
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2020
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 13, 2020
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.14107(a)
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 123.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 123.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 123.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 56
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 10
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
- 3
- Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
- 1
- Violations per inspection dayVPID
- 3
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 4605
- Size of mineSIZE_OF_MINE
- 4605
- Controller hours workedCONTROLLER_HRS
- 12202
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 12202
- History period startHISTORY_START_DT
- Mar 25, 2019
- History period endHISTORY_END_DT
- Jun 24, 2020
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1153973
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (14)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jul 16, 2019Citation number: 6334754Standard: 56.12008Proposed penalty: $121.00Current assessment: $121.00Paid against proposed penalty: $121.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6334754
- Assessment control numberASSESS_CASE_NO
- 000499726
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Oct 8, 2019
- Citation issuedISSUE_DT
- Jul 16, 2019
- Date of occurrenceOCCURRENCE_DT
- Jul 16, 2019
- Final order dateFINAL_ORDER_DT
- Oct 23, 2019
- Bill first printedBILL_PRINT_DT
- Sep 17, 2019
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2019
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 23, 2019
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.12008
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 121.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 121.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 121.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 51
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 20
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 20
Inputs to the penalty calculation
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 360
- Size of mineSIZE_OF_MINE
- 360
- Controller hours workedCONTROLLER_HRS
- 5827
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 5827
- History period startHISTORY_START_DT
- Apr 16, 2018
- History period endHISTORY_END_DT
- Jul 15, 2019
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1124502
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (17)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
Issued: Jul 16, 2019Citation number: 6334752Standard: 56.16005Proposed penalty: $121.00Current assessment: $121.00Paid against proposed penalty: $121.00Case status: ClosedDetails
The assessment
- Citation or order numberVIOLATION_NO
- 6334752
- Assessment control numberASSESS_CASE_NO
- 000499726
- Assessment typeASSESS_TYPE_CD
- Regular
- Case statusASSESS_CASE_STATUS_CD
- Closed
- Case status dateASSESS_CASE_STATUS_DT
- Oct 8, 2019
- Citation issuedISSUE_DT
- Jul 16, 2019
- Date of occurrenceOCCURRENCE_DT
- Jul 16, 2019
- Final order dateFINAL_ORDER_DT
- Oct 23, 2019
- Bill first printedBILL_PRINT_DT
- Sep 17, 2019
- Bill print fiscal yearBILL_PRINT_FISCAL_YR
- 2019
- Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
- Oct 23, 2019
- Citation typeCITATION_TYPE_CD
- Citation
- 30 CFR standardCFR_STANDARD_CD
- 56.16005
- Section of the Act, primaryPRIMARY_ACTION_CD
- 104(a)
- Good faith reduction appliedGOOD_FAITH_IND
- Y
Amounts
- Proposed penaltyPROPOSED_PENALTY_AMT
- 121.00
- Current assessmentCURRENT_ASSESSMENT_AMT
- 121.00
- Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
- 121.00
Penalty points
- Violation history pointsPENALTY_POINTS
- 51
- Persons potentially affected pointsGRAVITY_PERSONS_POINTS
- 1
- Injury severity pointsGRAVITY_INJURY_POINTS
- 5
- Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
- 10
- Negligence pointsNEGLIGENCE_POINTS
- 35
Inputs to the penalty calculation
- Operator hours worked at the mineVIOLATOR_MINE_HRS
- 360
- Size of mineSIZE_OF_MINE
- 360
- Controller hours workedCONTROLLER_HRS
- 5827
- Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
- 5827
- History period startHISTORY_START_DT
- Apr 16, 2018
- History period endHISTORY_END_DT
- Jul 15, 2019
Who
- Issued toVIOLATOR_TYPE_CD
- Operator
- Name at the time of the assessmentVIOLATOR_NAME
- H C Contractors, Inc
- IDVIOLATOR_ID
- 0093385
- Operator start at the mine, as assessedVIOLATOR_START_DT
- Jul 1, 2008
- Operator end at the mine, as assessedVIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
- Inspection eventEVENT_NBR
- 1124502
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- MSHA office codeOFFICE_CD
- M7861
Recorded as 0 (17)
Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT
Recorded as N (2)
Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND
Not recorded by MSHA (1)
Mine Act sectionMINE_ACT_SECTION_CD
25 most recent of 30 assessed citations and orders. Amounts are MSHA's per-citation values; case status is MSHA's own (Closed, Invalid, Printed or Received).
Employment and hours worked
Year: 2026Part of mine: OFFICE WORKERS AT MINE SITEAverage employees: 0Hours worked: 296Details
The report
- YearCALENDAR_YR
- 2026
- Part of the mineSUBUNIT_DESC
- OFFICE WORKERS AT MINE SITE
- Part of the mine codeSUBUNIT_CD
- 99
- Hours workedANNUAL_HRS
- 296
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (3)
Average employeesAVG_ANNUAL_EMPL, Average hours per employeeAVG_EMPLOYEE_HOURS, Coal productionANNUAL_COAL_PROD
Year: 2026Part of mine: STRIP, QUARY, OPEN PITAverage employees: 3Hours worked: 3,316Details
The report
- YearCALENDAR_YR
- 2026
- Part of the mineSUBUNIT_DESC
- STRIP, QUARY, OPEN PIT
- Part of the mine codeSUBUNIT_CD
- 03
- Average employeesAVG_ANNUAL_EMPL
- 3
- Hours workedANNUAL_HRS
- 3316
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 1105
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2025Part of mine: OFFICE WORKERS AT MINE SITEAverage employees: 1Hours worked: 10Details
The report
- YearCALENDAR_YR
- 2025
- Part of the mineSUBUNIT_DESC
- OFFICE WORKERS AT MINE SITE
- Part of the mine codeSUBUNIT_CD
- 99
- Average employeesAVG_ANNUAL_EMPL
- 1
- Hours workedANNUAL_HRS
- 10
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 10
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2025Part of mine: STRIP, QUARY, OPEN PITAverage employees: 3Hours worked: 546Details
The report
- YearCALENDAR_YR
- 2025
- Part of the mineSUBUNIT_DESC
- STRIP, QUARY, OPEN PIT
- Part of the mine codeSUBUNIT_CD
- 03
- Average employeesAVG_ANNUAL_EMPL
- 3
- Hours workedANNUAL_HRS
- 546
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 182
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2024Part of mine: OFFICE WORKERS AT MINE SITEAverage employees: 1Hours worked: 34Details
The report
- YearCALENDAR_YR
- 2024
- Part of the mineSUBUNIT_DESC
- OFFICE WORKERS AT MINE SITE
- Part of the mine codeSUBUNIT_CD
- 99
- Average employeesAVG_ANNUAL_EMPL
- 1
- Hours workedANNUAL_HRS
- 34
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 34
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2024Part of mine: STRIP, QUARY, OPEN PITAverage employees: 7Hours worked: 1,675Details
The report
- YearCALENDAR_YR
- 2024
- Part of the mineSUBUNIT_DESC
- STRIP, QUARY, OPEN PIT
- Part of the mine codeSUBUNIT_CD
- 03
- Average employeesAVG_ANNUAL_EMPL
- 7
- Hours workedANNUAL_HRS
- 1675
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 239
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2023Part of mine: OFFICE WORKERS AT MINE SITEAverage employees: 1Hours worked: 34Details
The report
- YearCALENDAR_YR
- 2023
- Part of the mineSUBUNIT_DESC
- OFFICE WORKERS AT MINE SITE
- Part of the mine codeSUBUNIT_CD
- 99
- Average employeesAVG_ANNUAL_EMPL
- 1
- Hours workedANNUAL_HRS
- 34
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 34
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2023Part of mine: STRIP, QUARY, OPEN PITAverage employees: 5Hours worked: 6,356Details
The report
- YearCALENDAR_YR
- 2023
- Part of the mineSUBUNIT_DESC
- STRIP, QUARY, OPEN PIT
- Part of the mine codeSUBUNIT_CD
- 03
- Average employeesAVG_ANNUAL_EMPL
- 5
- Hours workedANNUAL_HRS
- 6356
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 1271
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2022Part of mine: OFFICE WORKERS AT MINE SITEAverage employees: 1Hours worked: 65Details
The report
- YearCALENDAR_YR
- 2022
- Part of the mineSUBUNIT_DESC
- OFFICE WORKERS AT MINE SITE
- Part of the mine codeSUBUNIT_CD
- 99
- Average employeesAVG_ANNUAL_EMPL
- 1
- Hours workedANNUAL_HRS
- 65
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 65
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2022Part of mine: STRIP, QUARY, OPEN PITAverage employees: 3Hours worked: 1,928Details
The report
- YearCALENDAR_YR
- 2022
- Part of the mineSUBUNIT_DESC
- STRIP, QUARY, OPEN PIT
- Part of the mine codeSUBUNIT_CD
- 03
- Average employeesAVG_ANNUAL_EMPL
- 3
- Hours workedANNUAL_HRS
- 1928
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 643
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2021Part of mine: OFFICE WORKERS AT MINE SITEAverage employees: 1Hours worked: 80Details
The report
- YearCALENDAR_YR
- 2021
- Part of the mineSUBUNIT_DESC
- OFFICE WORKERS AT MINE SITE
- Part of the mine codeSUBUNIT_CD
- 99
- Average employeesAVG_ANNUAL_EMPL
- 1
- Hours workedANNUAL_HRS
- 80
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 80
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2021Part of mine: STRIP, QUARY, OPEN PITAverage employees: 3Hours worked: 1,495Details
The report
- YearCALENDAR_YR
- 2021
- Part of the mineSUBUNIT_DESC
- STRIP, QUARY, OPEN PIT
- Part of the mine codeSUBUNIT_CD
- 03
- Average employeesAVG_ANNUAL_EMPL
- 3
- Hours workedANNUAL_HRS
- 1495
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 498
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2020Part of mine: OFFICE WORKERS AT MINE SITEAverage employees: 1Hours worked: 79Details
The report
- YearCALENDAR_YR
- 2020
- Part of the mineSUBUNIT_DESC
- OFFICE WORKERS AT MINE SITE
- Part of the mine codeSUBUNIT_CD
- 99
- Average employeesAVG_ANNUAL_EMPL
- 1
- Hours workedANNUAL_HRS
- 79
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 79
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2020Part of mine: STRIP, QUARY, OPEN PITAverage employees: 3Hours worked: 1,635Details
The report
- YearCALENDAR_YR
- 2020
- Part of the mineSUBUNIT_DESC
- STRIP, QUARY, OPEN PIT
- Part of the mine codeSUBUNIT_CD
- 03
- Average employeesAVG_ANNUAL_EMPL
- 3
- Hours workedANNUAL_HRS
- 1635
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 545
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2019Part of mine: OFFICE WORKERS AT MINE SITEAverage employees: 1Hours worked: 150Details
The report
- YearCALENDAR_YR
- 2019
- Part of the mineSUBUNIT_DESC
- OFFICE WORKERS AT MINE SITE
- Part of the mine codeSUBUNIT_CD
- 99
- Average employeesAVG_ANNUAL_EMPL
- 1
- Hours workedANNUAL_HRS
- 150
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 150
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
Year: 2019Part of mine: STRIP, QUARY, OPEN PITAverage employees: 7Hours worked: 4,605Details
The report
- YearCALENDAR_YR
- 2019
- Part of the mineSUBUNIT_DESC
- STRIP, QUARY, OPEN PIT
- Part of the mine codeSUBUNIT_CD
- 03
- Average employeesAVG_ANNUAL_EMPL
- 7
- Hours workedANNUAL_HRS
- 4605
- Average hours per employeeAVG_EMPLOYEE_HOURS
- 658
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileCURR_MINE_NM
- H C Contractors Crusher
- StateSTATE_ABBR
- AK
- Coal or Metal/Non-MetalC_M_IND
- M
Recorded as 0 (1)
Coal productionANNUAL_COAL_PROD
What the operator reported to MSHA for the 8 most recent years, one row per part of the mine, as MSHA files them. Rows are not added together.
Mine details
- MSHA field office
- Anchorage AK Field Office
- Nearest town
- Fox
- Days worked per week
- 5
- Hours per shift
- 8
- Production shifts per day
- 1
- Maintenance shifts per day
- 0
- Employees, current record
- 2
- Tailing ponds
- 0
- 103(i) spot inspection status
- Never Had 103I Status
- Safety committee
- N
- Portable operation
- Y
Every field in MSHA's mine record
The mine
- Mine nameCURRENT_MINE_NAME
- H C Contractors Crusher
- Mine IDMINE_ID
- 5001890
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
- Mine typeCURRENT_MINE_TYPE
- Surface
- Current statusCURRENT_MINE_STATUS
- Intermittent
- Status sinceCURRENT_STATUS_DT
- Sep 7, 2018
- Legal entity typeCOMPANY_TYPE
- Corporation
- Portable minePORTABLE_OPERATION
- Y
- Portable mine FIPS state codePORTABLE_FIPS_ST_CD
- 02
Operator and controller
- OperatorCURRENT_OPERATOR_NAME
- H C Contractors, Inc
- Operator IDCURRENT_OPERATOR_ID
- 0093385
- ControllerCURRENT_CONTROLLER_NAME
- Ukpeagvik Inupiat Corporation; William J Hoople Trust dated 2-25-09
- Controller IDCURRENT_CONTROLLER_ID
- 0182020
- Start of the operating periodCURRENT_CONTROLLER_BEGIN_DT
- Jul 1, 2008
Location and MSHA office
- StateSTATE
- AK
- Bureau of Mines state codeBOM_STATE_CD
- 50
- FIPS county codeFIPS_CNTY_CD
- 090
- FIPS county nameFIPS_CNTY_NM
- Fairbanks North Star
- Nearest townNEAREST_TOWN
- Fox
- MSHA districtDISTRICT
- M7
- MSHA office codeOFFICE_CD
- M7861
- MSHA officeOFFICE_NAME
- Anchorage AK Field Office
- Most recent assessment control numberASSESS_CTRL_NO
- 000604444
Commodity
- Primary commodity (SIC)PRIMARY_SIC
- Construction Sand and Gravel
- Primary commodity codePRIMARY_SIC_CD
- 144200
- Primary SIC codePRIMARY_SIC_CD_1
- 1442
- Primary SIC suffixPRIMARY_SIC_CD_SFX
- 00
- Primary industry groupPRIMARY_CANVASS
- SandAndGravel
- Primary industry group codePRIMARY_CANVASS_CD
- 5
Operations, from the Mine Information Form
- Days operating per weekDAYS_PER_WEEK
- 5
- Hours per shiftHOURS_PER_SHIFT
- 8
- Production shifts per dayPROD_SHIFTS_PER_DAY
- 1
- Workers employedNO_EMPLOYEES
- 2
- MSHA restricted from enforcing Part 48 trainingPART48_TRAINING
- Y
- 103(i) statusCURRENT_103I
- Never Had 103I Status
Recorded as 0 (3)
Driving miles from the MSHA officeMILES_FROM_OFFICE, Maintenance-only shifts per dayMAINT_SHIFTS_PER_DAY, Tailing pondsNO_TAILING_PONDS
Recorded as N (4)
Pillar recovery usedPILLAR_RECOVERY_USED, Highwall miner usedHIGHWALL_MINER_USED, Multiple pitsMULTIPLE_PITS, Safety committeeSAFETY_COMMITTEE_IND
Not recorded by MSHA (13)
Congressional districtCONG_DIST_CD, Secondary commodity (SIC)SECONDARY_SIC, Secondary commodity codeSECONDARY_SIC_CD, Secondary SIC codeSECONDARY_SIC_CD_1, Secondary SIC suffixSECONDARY_SIC_CD_SFX, Secondary industry groupSECONDARY_CANVASS, Secondary industry group codeSECONDARY_CANVASS_CD, Average mining height, inchesAVG_MINE_HEIGHT, Mine gas categoryMINE_GAS_CATEGORY_CD, Methane liberation, cu ft per 24 hMETHANE_LIBERATION, Producing pitsNO_PRODUCING_PITS, Non-producing pitsNO_NONPRODUCING_PITS, 103(i) status sinceCURRENT_103I_DT
Operator and controller history
Operator: H C Contractors, IncFrom: Jul 1, 2008To: No end dateController: Ukpeagvik Inupiat Corporation et alFrom : Aug 14, 2023To : No end dateDetails
Operator
- OperatorOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Operator fromOPERATOR_START_DT
- Jul 1, 2008
Controller
- ControllerCONTROLLER_NAME
- Ukpeagvik Inupiat Corporation et al
- Controller IDCONTROLLER_ID
- 0182020
- Company or personCONTROLLER_TYPE
- COMPANY
- Controller fromCONTROLLER_START_DT
- Aug 14, 2023
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine status at this pointMINE_STATUS
- Intermittent
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Not recorded by MSHA (2)
Operator toOPERATOR_END_DT, Controller toCONTROLLER_END_DT
Operator: H C Contractors, IncFrom: Jul 1, 2008To: No end dateController: William J Hoople Trust dated 2-25-09 et alFrom : Aug 14, 2023To : No end dateDetails
Operator
- OperatorOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Operator fromOPERATOR_START_DT
- Jul 1, 2008
Controller
- ControllerCONTROLLER_NAME
- William J Hoople Trust dated 2-25-09 et al
- Controller IDCONTROLLER_ID
- 0182020
- Company or personCONTROLLER_TYPE
- COMPANY
- Controller fromCONTROLLER_START_DT
- Aug 14, 2023
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine status at this pointMINE_STATUS
- Intermittent
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Not recorded by MSHA (2)
Operator toOPERATOR_END_DT, Controller toCONTROLLER_END_DT
Operator: H C Contractors, IncFrom: Jul 1, 2008To: No end dateController: Not shownFrom : Jul 1, 2008To : Aug 13, 2023Details
Operator
- OperatorOPERATOR_NAME
- H C Contractors, Inc
- Operator IDOPERATOR_ID
- 0093385
- Operator fromOPERATOR_START_DT
- Jul 1, 2008
Controller
- Controller IDCONTROLLER_ID
- 0040850
- Company or personCONTROLLER_TYPE
- PERSON
- Controller fromCONTROLLER_START_DT
- Jul 1, 2008
- Controller toCONTROLLER_END_DT
- Aug 13, 2023
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Mine status at this pointMINE_STATUS
- Intermittent
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Not recorded by MSHA (2)
Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME
As MSHA records it, newest operator first.
Address of record
H C Contractors, Inc·Contact title President·1296 Old Richardson Hwy, North Pole AK 99705
MSHA says an address of record "does not represent the actual mine location."
Every field in the address record
Address
- Business nameBUSINESS_NAME
- H C Contractors, Inc
- Contact titleCONTACT_TITLE
- President
- StreetSTREET
- 1296 Old Richardson Hwy
- CityCITY
- North Pole
- StateSTATE_ABBR
- AK
- State nameSTATE
- Alaska
- ZIP codeZIP_CD
- 99705
- CountryCOUNTRY
- USA
- FIPS state codeFIPS_STATE_CD
- 02
Mine
- Mine IDMINE_ID
- 5001890
- Mine name in this fileMINE_NAME
- H C Contractors Crusher
- Nearest townNEAREST_TOWN
- Fox
- Mine typeMINE_TYPE_CD
- Surface
- Mine statusMINE_STATUS
- Intermittent
- Status sinceMINE_STATUS_DT
- Sep 7, 2018
- Primary commodity (SIC)PRIMARY_SIC_CD
- Construction Sand and Gravel
- Coal or Metal/Non-MetalCOAL_METAL_IND
- M
Not recorded by MSHA (3)
PO boxPO_BOX, ProvincePROVINCE, Foreign postal codePOSTAL_CD
Sources. MSHA open government data files: Mines, Inspections, Violations, AssessedViolations, ContestedViolations, 107(a)OrdersIssued, Accidents, MinesProdYearly, ControllerOperatorHistory, AddressOfRecord. Field labels are shortened from MSHA's definition files, with MSHA's column name beside each. MSHA Mine Data Retrieval System·MSHA fatality report search·MSHA open government data
These are U.S. Department of Labor, Mine Safety and Health Administration records, reproduced as published. Citations can be contested, modified or vacated, and records that are contested or not yet final are included. SafetyRecord.org is not a consumer reporting agency. MSHA records as of Nov 6, 2026. Data and methodology