Skip to content
SafetyRecord logoSafetyRecord
GROSZ-HALES CONSTRUCTION CO., INC.
$725
penalties
7
viol.
1
insp.

GROSZ-HALES CONSTRUCTION CO., INC.

1402 ALBERTSONS DR., PLANT CITY, FL 33566

Inspections
1
Nov 1993 to Nov 1993 · 1 safety, 0 health
Violations
7
across 1 inspection
Penalties on record
$725
latest amounts in DOL records
By classification
Serious 7Willful 0Repeat 0Other 0

Having inspection records is common for businesses in regulated industries. Data and methodology

Inspection records

Nov 3, 1993Planned (H) · Complete scope, Safety#109709535$7257 viol.

Inspection #109709535

Dates

Opened
Nov 3, 1993
Closing Conference Date
Nov 9, 1993
Closed
Apr 25, 1995

Inspection

Advance Notice
No
Owner Type
Private
Union Status
No
Number of Employees
5

Violations and Penalties

Total Violations
7
Violation Types
7 serious
Initial Penalties
$725
Penalties on Record
$725
Site Address
1402 Albertsons Dr., Plant City, FL 33566
Industry
Not classified in OSHA's inspection record.

Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.

Violations

Violation list (7 of 7 shown)
CitationStandardTypeInstancesExposedInitialCurrentAbatementContestFinal Order
010011926.451
Scaffolding - General Requirements
OSHA citation code: 19260451 A03
Serious11$175$175Feb 11, 1994--
01002A1926.453
Aerial Lifts
OSHA citation code: 19260453 B03 I
Serious11$175$175Feb 11, 1994--
01002B1926.453
Aerial Lifts
OSHA citation code: 19260453 B03 I
Serious11$0$0Feb 11, 1994--
010031926.453
Aerial Lifts
OSHA citation code: 19260453 B03 III
Serious11$175$175Feb 11, 1994--
01004A1926.453
Aerial Lifts
OSHA citation code: 19260453 B03 VI
Serious11$100$100Feb 11, 1994--
01004B1926.453
Aerial Lifts
OSHA citation code: 19260453 B03 VII
Serious11$0$0Feb 11, 1994--
010051926.405
Electrical - Wiring Methods (Construction)
OSHA citation code: 19260405 G02 IV
Serious12$100$100Feb 10, 1994--
Inspections 1 to 1 of 1, newest first

Penalty amounts may differ from final amounts after settlement or judicial review. How to read these records

About these records

A company page groups inspections with the same normalized employer name, city and state; it is not a legal-entity identifier (how pages are grouped).

This page displays public OSHA enforcement data. Status text follows the DOL inspection record first and may include citation-level context when the inspection feed and citation records are out of sync. Penalty amounts shown reflect the latest penalty amounts on record in the DOL database and may differ from initial assessments or final amounts. This is not an official OSHA resource.

OSHA's public enforcement data does not publish a "guilty" or "not guilty" field for inspections. The closest outcome fields available are the citation counts, penalty amounts, contest dates, final-order dates, and the inspection close date shown on this page. How to interpret these status fields. How initial and current penalties are recorded.

OSHA may publish multiple citation rows in the same inspection with the same standard and penalty fields. Separate rows can still differ in OSHA metadata such as citation identifier, recorded instance count, exposed workers, or gravity value. Contest and Final Order columns show citation-level dates from OSHA's enforcement record. A dash means OSHA's record does not currently show that activity for the citation.

Understanding These Penalties

The maximum penalty for a serious violation in 2025 is $16,550 per violation. For willful violations, the range is $11,823 to $165,514. The current penalty column shows the latest amount on record in OSHA's database for each citation. When the current penalty differs from the initial penalty, OSHA's records show that the amount changed during the enforcement process, but this page does not determine the specific reason for each change. Penalty amounts are set by OSHA and adjusted annually for inflation.

Standards cited

1926.453Aerial Lifts5 citations · $450
1926.405Electrical - Wiring Methods (Construction)1 citation · $100
1926.451Scaffolding - General Requirements1 citation · $175

Other inspected employers in PLANT CITY, FL