NATIONAL VALVE & MFG CO
$395
penalties
16
viol.
4
insp.

NATIONAL VALVE & MFG CO

SOMERSET POWER STATION, Barker, NY 14012

Inspections
4
Sep 1982 to Mar 1984 · 4 safety, 0 health
Violations
16
across 4 inspections
Penalties on record
$395
latest amounts in DOL records
By classification
Serious 4Willful 0Repeat 0Other 12

Having inspection records is common for businesses in regulated industries. Data and methodology

Inspection records

Mar 8, 1984Planned (H) · Complete scope, Safety#130815$1001 viol.

Inspection #130815

Dates

Opened
Mar 8, 1984
Closing Conference Date
Not recorded
Closed
Dec 31, 1996

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
94

Violations and Penalties

Total Violations
1
Violation Types
1 serious
Initial Penalties
$200
Penalties on Record
$100
Site Address
Somerset Power Station, Barker, NY 14012
Industry
Not classified in OSHA's inspection record.

Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.

Violations

Violation list (1 of 1 shown)
CitationStandardTypeInstancesExposedInitialCurrentAbatementContestFinal Order
010011926.451
Scaffolding - General Requirements
OSHA citation code: 19260451 D10
Serious1-$200$100Mar 18, 1984--
Aug 22, 1983Planned (H) · Complete scope, Safety#10799179$06 viol.

Inspection #10799179

Dates

Opened
Aug 22, 1983
Closing Conference Date
Not recorded
Closed
Nov 8, 1983

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
103

Violations and Penalties

Total Violations
6
Violation Types
1 serious, 5 other-than-serious
Initial Penalties
$240
Penalties on Record
$0
Site Address
Somerset Power Station, Barker, NY 14012
Industry
Not classified in OSHA's inspection record.

Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.

Violations

Violation list (6 of 6 shown)
CitationStandardTypeInstancesExposedInitialCurrentAbatementContestFinal Order
010011926.451
Scaffolding - General Requirements
OSHA citation code: 19260451 D04
Serious1-$240$0Sep 26, 1983--
020011926.300
General requirements
OSHA citation code: 19260300 C
Other1-$0$0Sep 18, 1983--
020021926.402
Applicability (Electrical - Construction)
OSHA citation code: 19260402 A08
Other1-$0$0Sep 18, 1983--
020031926.451
Scaffolding - General Requirements
OSHA citation code: 19260451 A07
Other2-$0$0Sep 26, 1983--
020041926.500
Scope, application, and definitions applicable to this subpart
OSHA citation code: 19260500 B01
Other1-$0$0Sep 18, 1983--
020051926.451
Scaffolding - General Requirements
OSHA citation code: 19260451 D04
Other1-$0$0Oct 13, 1983--
Mar 16, 1983Planned (H) · Complete scope, Safety#10848943$1754 viol.

Inspection #10848943

Dates

Opened
Mar 16, 1983
Closing Conference Date
Mar 23, 1983
Closed
May 19, 1983

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
115

Violations and Penalties

Total Violations
4
Violation Types
1 serious, 3 other-than-serious
Initial Penalties
$490
Penalties on Record
$175
Site Address
Somerset Power Station, Barker, NY 14012
Industry
Not classified in OSHA's inspection record.

Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.

Violations

Violation list (4 of 4 shown)
CitationStandardTypeInstancesExposedInitialCurrentAbatementContestFinal Order
010011926.451
Scaffolding - General Requirements
OSHA citation code: 19260451 A04
Serious1-$490$175Mar 16, 1983--
020011926.451
Scaffolding - General Requirements
OSHA citation code: 19260451 E04
Other1-$0$0Mar 16, 1983--
020021926.451
Scaffolding - General Requirements
OSHA citation code: 19260451 E10
Other1-$0$0Mar 16, 1983--
020031926.500
Scope, application, and definitions applicable to this subpart
OSHA citation code: 19260500 D01
Other1-$0$0Mar 16, 1983--
Sep 21, 1982Planned (H) · Complete scope, Safety#10848489$1205 viol.

Inspection #10848489

Dates

Opened
Sep 21, 1982
Closing Conference Date
Oct 8, 1982
Closed
Nov 8, 1982

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
90

Violations and Penalties

Total Violations
5
Violation Types
1 serious, 4 other-than-serious
Initial Penalties
$240
Penalties on Record
$120
Site Address
Somerset Power Station, Barker, NY 14012
Industry
Not classified in OSHA's inspection record.

Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.

Violations

Violation list (5 of 5 shown)
CitationStandardTypeInstancesExposedInitialCurrentAbatementContestFinal Order
010011926.556
OSHA citation code: 19260556 B02 V
Serious1-$240$120Sep 21, 1982--
020011926.351
Arc Welding and Cutting
OSHA citation code: 19260351 E
Other1-$0$0Oct 18, 1982--
020021926.401
OSHA citation code: 19260401 J03
Other1-$0$0Oct 18, 1982--
020031926.402
Applicability (Electrical - Construction)
OSHA citation code: 19260402 A08
Other1-$0$0Oct 18, 1982--
020041926.402
Applicability (Electrical - Construction)
OSHA citation code: 19260402 A11
Other1-$0$0Oct 18, 1982--
Inspections 1 to 4 of 4, newest first

Penalty amounts may differ from final amounts after settlement or judicial review. How to read these records

About these records

A company page groups inspections with the same normalized employer name, city and state; it is not a legal-entity identifier (how pages are grouped).

This page displays public OSHA enforcement data. Status text follows the DOL inspection record first and may include citation-level context when the inspection feed and citation records are out of sync. Penalty amounts shown reflect the latest penalty amounts on record in the DOL database and may differ from initial assessments or final amounts. This is not an official OSHA resource.

OSHA's public enforcement data does not publish a "guilty" or "not guilty" field for inspections. The closest outcome fields available are the citation counts, penalty amounts, contest dates, final-order dates, and the inspection close date shown on this page. How to interpret these status fields. How initial and current penalties are recorded.

OSHA may publish multiple citation rows in the same inspection with the same standard and penalty fields. Separate rows can still differ in OSHA metadata such as citation identifier, recorded instance count, exposed workers, or gravity value. Contest and Final Order columns show citation-level dates from OSHA's enforcement record. A dash means OSHA's record does not currently show that activity for the citation.

Understanding These Penalties

The maximum penalty for a serious violation in 2025 is $16,550 per violation. For willful violations, the range is $11,823 to $165,514. The current penalty column shows the latest amount on record in OSHA's database for each citation. When the current penalty differs from the initial penalty, OSHA's records show that the amount changed during the enforcement process, but this page does not determine the specific reason for each change. Penalty amounts are set by OSHA and adjusted annually for inflation.

Standards cited

1926.451Scaffolding - General Requirements7 citations · $275
1926.402Applicability (Electrical - Construction)3 citations · $0
1926.500Scope, application, and definitions applicable to this subpart2 citations · $0

Other inspected employers in Barker, NY

All employers in Barker →