Aug 17, 2011#314527169Aug 17, 2011Planned (H) · Complete scope, Health#314527169$1652 viol.2 violations$165 in penalties
Inspection #314527169
Dates
- Opened
- Aug 17, 2011
- Closing Conference Date
- Nov 7, 2011
- Closed
- Mar 27, 2012
Inspection
- Advance Notice
- No
- Owner Type
- Private
- Union Status
- No
- Number of Employees
- 8
Violations and Penalties
- Total Violations
- 2
- Violation Types
- 1 serious, 1 other-than-serious
- Initial Penalties
- $165
- Penalties on Record
- $165
- Site Address
- 2668 Ne 3rd St, Prineville, OR 97754
- Industry
- 332420 Metal Tank (Heavy Gauge) Manufacturing
Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.
Violations
Violation list (2 of 2 shown)
| Citation | Standard | Type | Instances | Exposed | Initial | Current | Abatement | Contest | Final Order |
|---|---|---|---|---|---|---|---|---|---|
| 01001 | 1910.1026 Chromium (VI) OSHA citation code: 19101026 D02 III | Serious | 1 | 1 | $165 | $165 | Dec 24, 2011 | - | - |
| 02002 | 1910.106 Flammable Liquids OSHA citation code: 19100106 G03 IVD | Other | 1 | 8 | $0 | $0 | Jan 7, 2012 | - | - |
Sep 5, 2008#312261522Sep 5, 2008Planned (H) · Complete scope, Safety#312261522$3258 viol.8 violations$325 in penalties
Inspection #312261522
Dates
- Opened
- Sep 5, 2008
- Closing Conference Date
- Sep 12, 2008
- Contested
- Oct 31, 2008
- Final Order
- Feb 2, 2009
- Closed
- Mar 12, 2009
Inspection
- Advance Notice
- No
- Owner Type
- Private
- Union Status
- Yes
- Number of Employees
- 13
Violations and Penalties
- Total Violations
- 8
- Violation Types
- 4 serious, 4 other-than-serious
- Initial Penalties
- $655
- Penalties on Record
- $325
- Site Address
- 2668 E 3rd St, Prineville, OR 97754
- Industry
- 332420 Metal Tank (Heavy Gauge) Manufacturing
Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.
Violations
Violation list (8 of 8 shown)
| Citation | Standard | Type | Instances | Exposed | Initial | Current | Abatement | Contest | Final Order |
|---|---|---|---|---|---|---|---|---|---|
| 01001 | 1910.212 General Requirements for All Machines (Machine Guarding) OSHA citation code: 19100212 B | Serious | 2 | 5 | $330 | $0 | Nov 1, 2008 | Oct 31, 2008 | Feb 2, 2009 |
| 01002 | 1910.184 Slings OSHA citation code: 19100184 H05 III | Serious | 1 | 5 | $125 | $125 | Sep 5, 2008 | Oct 31, 2008 | Feb 2, 2009 |
| 01003 | 1910.184 Slings OSHA citation code: 19100184 I01 | Serious | 1 | 5 | $100 | $100 | Sep 5, 2008 | Oct 31, 2008 | Feb 2, 2009 |
| 01004 | 702022809 OSHA citation code: 702022809 I | Serious | 1 | 2 | $100 | $100 | Sep 5, 2008 | Oct 31, 2008 | Feb 2, 2009 |
| 02005 | 1910.305 Electrical - Wiring Methods, Components, and Equipment OSHA citation code: 19100305 G02 III | Other | 1 | 5 | $0 | $0 | Sep 5, 2008 | Oct 31, 2008 | Feb 2, 2009 |
| 02006 | 1910.303 Electrical - General Requirements OSHA citation code: 19100303 G01 II | Other | 1 | 3 | $0 | $0 | Sep 5, 2008 | Oct 31, 2008 | Feb 2, 2009 |
| 02007 | 1910.305 Electrical - Wiring Methods, Components, and Equipment OSHA citation code: 19100305 G02 III | Other | 1 | 1 | $0 | $0 | Nov 1, 2008 | Oct 31, 2008 | Feb 2, 2009 |
| 02008 | 1910.305 Electrical - Wiring Methods, Components, and Equipment OSHA citation code: 19100305 G01 IVA | Other | 1 | 2 | $0 | $0 | Sep 5, 2008 | Oct 31, 2008 | Feb 2, 2009 |
Jun 3, 2003#306597279Jun 3, 2003Planned (H) · Complete scope, Safety#306597279$1254 viol.4 violations$125 in penalties
Inspection #306597279
Dates
- Opened
- Jun 3, 2003
- Closing Conference Date
- Jun 3, 2003
- Closed
- Apr 6, 2004
Inspection
- Advance Notice
- No
- Owner Type
- Private
- Union Status
- Yes
- Number of Employees
- 14
Violations and Penalties
- Total Violations
- 4
- Violation Types
- 1 serious, 3 other-than-serious
- Initial Penalties
- $125
- Penalties on Record
- $125
- Site Address
- 2668 E 3rd St, Prineville, OR 97754
- Industry
- 336211 Motor Vehicle Body Manufacturing
Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.
Violations
Violation list (4 of 4 shown)
| Citation | Standard | Type | Instances | Exposed | Initial | Current | Abatement | Contest | Final Order |
|---|---|---|---|---|---|---|---|---|---|
| 01001 | 702029003 OSHA citation code: 702029003 C | Serious | 1 | 1 | $125 | $125 | Jun 3, 2003 | - | - |
| 02002 | 702029003 OSHA citation code: 702029003 A | Other | 1 | 1 | $0 | $0 | Jun 3, 2003 | - | - |
| 02003 | 1910.184 Slings OSHA citation code: 19100184 E01 | Other | 1 | 1 | $0 | $0 | Jul 24, 2003 | - | - |
| 02004 | 1910.305 Electrical - Wiring Methods, Components, and Equipment OSHA citation code: 19100305 G02 III | Other | 1 | 1 | $0 | $0 | Jul 24, 2003 | - | - |
Feb 9, 1999#302591235Feb 9, 1999Planned (H) · Complete scope, Safety#302591235$3103 viol.3 violations$310 in penalties
Inspection #302591235
Dates
- Opened
- Feb 9, 1999
- Closing Conference Date
- Feb 9, 1999
- Closed
- Jun 15, 1999
Inspection
- Advance Notice
- No
- Owner Type
- Private
- Union Status
- No
- Number of Employees
- 20
Violations and Penalties
- Total Violations
- 3
- Violation Types
- 1 serious, 2 other-than-serious
- Initial Penalties
- $310
- Penalties on Record
- $310
- Site Address
- 2668 E 3rd St, Prineville, OR 97754
- Industry
- Not classified in OSHA's inspection record.
Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.
Violations
Violation list (3 of 3 shown)
| Citation | Standard | Type | Instances | Exposed | Initial | Current | Abatement | Contest | Final Order |
|---|---|---|---|---|---|---|---|---|---|
| 01001 | 1910.212 General Requirements for All Machines (Machine Guarding) OSHA citation code: 19100212 A03 II | Serious | 1 | 1 | $310 | $310 | Feb 9, 1999 | - | - |
| 02002 | 702037804 OSHA citation code: 702037804 A | Other | 1 | 1 | $0 | $0 | Mar 15, 1999 | - | - |
| 02003 | 1910.305 Electrical - Wiring Methods, Components, and Equipment OSHA citation code: 19100305 A02 IIIF | Other | 1 | 1 | $0 | $0 | Mar 15, 1999 | - | - |
Jan 18, 1994#115779951Jan 18, 1994Planned (H) · Complete scope, Safety#115779951$06 viol.6 violations$0 in penalties
Inspection #115779951
Dates
- Opened
- Jan 18, 1994
- Closing Conference Date
- Jan 18, 1994
- Closed
- Feb 24, 1994
Inspection
- Advance Notice
- No
- Owner Type
- Private
- Union Status
- No
- Number of Employees
- 12
Violations and Penalties
- Total Violations
- 6
- Violation Types
- 6 other-than-serious
- Initial Penalties
- $0
- Penalties on Record
- $0
- Site Address
- 2668 E 3rd St, Prineville, OR 97754
- Industry
- Not classified in OSHA's inspection record.
Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.
Violations
Violation list (6 of 6 shown)
| Citation | Standard | Type | Instances | Exposed | Initial | Current | Abatement | Contest | Final Order |
|---|---|---|---|---|---|---|---|---|---|
| 01001 | 740004702 | Other | 1 | 12 | $0 | $0 | Feb 13, 1994 | - | - |
| 01002 | 1910.157 Portable Fire Extinguishers OSHA citation code: 19100157 E02 | Other | 1 | 1 | $0 | $0 | Feb 13, 1994 | - | - |
| 01003 | 702037804 OSHA citation code: 702037804 A | Other | 1 | 1 | $0 | $0 | Feb 24, 1994 | - | - |
| 01004 | 702029402 | Other | 1 | 1 | $0 | $0 | Jan 18, 1994 | - | - |
| 01005 | 1910.215 Abrasive Wheel Machinery OSHA citation code: 19100215 B09 | Other | 1 | 1 | $0 | $0 | Jan 18, 1994 | - | - |
| 01006 | 1910.157 Portable Fire Extinguishers OSHA citation code: 19100157 C01 | Other | 1 | 1 | $0 | $0 | Feb 13, 1994 | - | - |
Sep 19, 1989#105304935Sep 19, 1989Planned (H) · Complete scope, Safety#105304935$36014 viol.14 violations$360 in penalties
Inspection #105304935
Dates
- Opened
- Sep 19, 1989
- Closing Conference Date
- Sep 22, 1989
- Contested
- Nov 1, 1989
- Closed
- Feb 27, 1990
Inspection
- Advance Notice
- No
- Owner Type
- Private
- Union Status
- No
- Number of Employees
- 16
Violations and Penalties
- Total Violations
- 14
- Violation Types
- 2 serious, 12 other-than-serious
- Initial Penalties
- $360
- Penalties on Record
- $360
- Site Address
- 2668 E 3rd St, Prineville, OR 97754
- Industry
- Not classified in OSHA's inspection record.
Planned Inspection: This inspection record is categorized as a planned inspection in the DOL OSHA enforcement data. Planned inspections are part of OSHA's scheduled enforcement activity rather than being opened directly from a complaint or reported incident at that worksite.
Violations
Violation list (8 of 14 shown)
| Citation | Standard | Type | Instances | Exposed | Initial | Current | Abatement | Contest | Final Order |
|---|---|---|---|---|---|---|---|---|---|
| 01001 | 1910.212 General Requirements for All Machines (Machine Guarding) OSHA citation code: 19100212 A01 | Serious | 1 | 1 | $120 | $120 | Sep 22, 1989 | Nov 1, 1989 | - |
| 01004 | 1910.219 Mechanical Power-Transmission Apparatus OSHA citation code: 19100219 E01 I | Serious | 1 | 1 | $120 | $120 | Sep 22, 1989 | Nov 1, 1989 | - |
| 02005 | 1910.219 Mechanical Power-Transmission Apparatus OSHA citation code: 19100219 A01 | Other | 1 | 1 | $0 | $0 | Sep 22, 1989 | Nov 1, 1989 | - |
| 02006 | 1910.215 Abrasive Wheel Machinery OSHA citation code: 19100215 A04 | Other | 1 | 1 | $0 | $0 | Sep 22, 1989 | Nov 1, 1989 | - |
| 02007 | 1910.215 Abrasive Wheel Machinery OSHA citation code: 19100215 B09 | Other | 1 | 1 | $0 | $0 | Sep 22, 1989 | Nov 1, 1989 | - |
| 02008 | 1910.219 Mechanical Power-Transmission Apparatus OSHA citation code: 19100219 C04 I | Other | 1 | 1 | $0 | $0 | Sep 22, 1989 | Nov 1, 1989 | - |
| 02009 | 767031001 OSHA citation code: 767031001 C | Other | 1 | 1 | $0 | $0 | Sep 22, 1989 | Nov 1, 1989 | - |
| 02010 | 1910.213 Woodworking Machinery Requirements OSHA citation code: 19100213 P04 | Other | 1 | 1 | $60 | $60 | Sep 22, 1989 | Nov 1, 1989 | - |
Showing the 8 violations listed first by citation identifier. This inspection has 14 total violations documented in the U.S. Department of Labor OSHA enforcement database. The complete violation list is available at enforcedata.dol.gov.
Penalty amounts may differ from final amounts after settlement or judicial review. How to read these records
About these records
A company page groups inspections with the same normalized employer name, city and state; it is not a legal-entity identifier (how pages are grouped).
This page displays public OSHA enforcement data. Status text follows the DOL inspection record first and may include citation-level context when the inspection feed and citation records are out of sync. Penalty amounts shown reflect the latest penalty amounts on record in the DOL database and may differ from initial assessments or final amounts. This is not an official OSHA resource.
OSHA's public enforcement data does not publish a "guilty" or "not guilty" field for inspections. The closest outcome fields available are the citation counts, penalty amounts, contest dates, final-order dates, and the inspection close date shown on this page. How to interpret these status fields. How initial and current penalties are recorded.
OSHA may publish multiple citation rows in the same inspection with the same standard and penalty fields. Separate rows can still differ in OSHA metadata such as citation identifier, recorded instance count, exposed workers, or gravity value. Contest and Final Order columns show citation-level dates from OSHA's enforcement record. A dash means OSHA's record does not currently show that activity for the citation.
Understanding These Penalties
The maximum penalty for a serious violation in 2025 is $16,550 per violation. For willful violations, the range is $11,823 to $165,514. The current penalty column shows the latest amount on record in OSHA's database for each citation. When the current penalty differs from the initial penalty, OSHA's records show that the amount changed during the enforcement process, but this page does not determine the specific reason for each change. Penalty amounts are set by OSHA and adjusted annually for inflation.
6 inspections, 1989 to 2011. Each row is one inspection; point at or tap a row for its dates and totals.
Source: DOL OSHA enforcement data (inspections and violations), linked via activity_nr (exact government key).
Penalty changes: Amounts shown reflect what OSHA's enforcement record publishes. The reason for any change is not stated unless OSHA's record explicitly says so.
Short cases: When a case closed soon after it opened, the closed marker is drawn slightly to the right so both markers stay visible. Each row's card shows the exact dates.