BECHTEL POWER CORP
$695
penalties
23
viol.
19
insp.

BECHTEL POWER CORP

GRAND GULF NUCLEAR POWER PLANT, Port Gibson, MS 39150

Inspections
19
Oct 1974 to Jan 1984 · 15 safety, 4 health
Violations
23
across 19 inspections
Penalties on record
$695
latest amounts in DOL records
By classification
Serious 5Willful 0Repeat 0Other 18

Having inspection records is common for businesses in regulated industries. Data and methodology

Inspection records

Jan 31, 1984Accident (A) · Partial scope, Safety#228528$00 viol.

Inspection #228528

Dates

Opened
Jan 31, 1984
Closing Conference Date
Jan 31, 1984
Closed
Feb 6, 1984

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
447
Related Activity
1 accident

Violations and Penalties

Total Violations
0
Initial Penalties
$0
Penalties on Record
$0
Site Address
Grand Gulf Nuclear Power Plant, Port Gibson, MS 39150
Industry
Not classified in OSHA's inspection record.

Accident Inspection: This inspection record is categorized as an accident inspection in the U.S. Department of Labor OSHA enforcement data. Employers must report work-related fatalities within 8 hours, and work-related inpatient hospitalizations, amputations, or losses of an eye within 24 hours. An accident-related inspection does not by itself determine fault.

Feb 2, 1983Complaint (B) · Partial scope, Health#13516679$00 viol.

Inspection #13516679

Dates

Opened
Feb 2, 1983
Closing Conference Date
Feb 3, 1983
Closed
Feb 4, 1983

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
1,200
Related Activity
1 complaint

Violations and Penalties

Total Violations
0
Initial Penalties
$0
Penalties on Record
$0
Site Address
Grand Gulf Nuclear Power Plant, Port Gibson, MS 39150
Industry
Not classified in OSHA's inspection record.

Complaint Inspection: This inspection record is categorized as a complaint inspection in the DOL OSHA enforcement data. OSHA can open complaint-driven inspections after receiving safety or health complaints from workers or their representatives.

Jan 26, 1982Complaint (B) · Partial scope, Health#13596580$00 viol.

Inspection #13596580

Dates

Opened
Jan 26, 1982
Closing Conference Date
Jan 26, 1982
Closed
Jan 29, 1982

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
2,264
Related Activity
1 complaint

Violations and Penalties

Total Violations
0
Initial Penalties
$0
Penalties on Record
$0
Site Address
Grand Gulf Nuclear Power Plant, Port Gibson, MS 39150
Industry
Not classified in OSHA's inspection record.

Complaint Inspection: This inspection record is categorized as a complaint inspection in the DOL OSHA enforcement data. OSHA can open complaint-driven inspections after receiving safety or health complaints from workers or their representatives.

Nov 7, 1980Complaint (B) · Partial scope, Health#13538749$00 viol.

Inspection #13538749

Dates

Opened
Nov 7, 1980
Closing Conference Date
Nov 7, 1980
Closed
Nov 13, 1980

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
3,200
Related Activity
1 complaint

Violations and Penalties

Total Violations
0
Initial Penalties
$0
Penalties on Record
$0
Site Address
Grand Gulf Nuclear Power Plant, Port Gibson, MS 39150
Industry
Not classified in OSHA's inspection record.

Complaint Inspection: This inspection record is categorized as a complaint inspection in the DOL OSHA enforcement data. OSHA can open complaint-driven inspections after receiving safety or health complaints from workers or their representatives.

Oct 24, 1979Complaint (B) · Partial scope, Health#13515713$03 viol.

Inspection #13515713

Dates

Opened
Oct 24, 1979
Closing Conference Date
Oct 25, 1979
Contested
Feb 15, 1980
Closed
Mar 27, 1980

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
4,400
Related Activity
2 complaints

Violations and Penalties

Total Violations
3
Violation Types
3 serious
Initial Penalties
$720
Penalties on Record
$0
Site Address
Grand Gulf Nuclear Power Plant, Port Gibson, MS 39150
Industry
Not classified in OSHA's inspection record.

Complaint Inspection: This inspection record is categorized as a complaint inspection in the DOL OSHA enforcement data. OSHA can open complaint-driven inspections after receiving safety or health complaints from workers or their representatives.

Violations

Violation list (3 of 3 shown)
CitationStandardTypeInstancesExposedInitialCurrentAbatementContestFinal Order
01001A1910.134
Respiratory Protection
OSHA citation code: 19100134 A02
Serious1-$720$0Feb 11, 1980Feb 15, 1980-
01001B1910.1000
Air Contaminants
OSHA citation code: 19101000 D02 I
Serious1-$0$0Apr 11, 1980Feb 15, 1980-
01001C1910.1000
Air Contaminants
OSHA citation code: 19101000 E
Serious1-$0$0Apr 11, 1980Feb 15, 1980-
Oct 17, 1979Complaint (B) · Partial scope, Safety#13579677$01 viol.

Inspection #13579677

Dates

Opened
Oct 17, 1979
Closing Conference Date
Oct 17, 1979
Contested
Nov 15, 1979
Closed
May 16, 1980

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
5,000
Related Activity
2 complaints

Violations and Penalties

Total Violations
1
Violation Types
1 other-than-serious
Initial Penalties
$160
Penalties on Record
$0
Site Address
Grand Gulf Nuclear Power Plant, Port Gibson, MS 39150
Industry
Not classified in OSHA's inspection record.

Complaint Inspection: This inspection record is categorized as a complaint inspection in the DOL OSHA enforcement data. OSHA can open complaint-driven inspections after receiving safety or health complaints from workers or their representatives.

Violations

Violation list (1 of 1 shown)
CitationStandardTypeInstancesExposedInitialCurrentAbatementContestFinal Order
020011926.102
Eye and Face Protection (Construction)
OSHA citation code: 19260102 A01
Other1-$160$0Nov 1, 1979Nov 15, 1979-
Mar 1, 1978Complaint (B) · Complete scope, Safety#13569066$01 viol.

Inspection #13569066

Dates

Opened
Mar 1, 1978
Closing Conference Date
Mar 1, 1978
Closed
Mar 29, 1978

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
2,900
Related Activity
1 complaint

Violations and Penalties

Total Violations
1
Violation Types
1 other-than-serious
Initial Penalties
$0
Penalties on Record
$0
Site Address
Grand Gulf Nuclear Power Plant, Port Gibson, MS 39150
Industry
Not classified in OSHA's inspection record.

Complaint Inspection: This inspection record is categorized as a complaint inspection in the DOL OSHA enforcement data. OSHA can open complaint-driven inspections after receiving safety or health complaints from workers or their representatives.

Violations

Violation list (1 of 1 shown)
CitationStandardTypeInstancesExposedInitialCurrentAbatementContestFinal Order
010011926.451
Scaffolding - General Requirements
OSHA citation code: 19260451 A04
Other1-$0$0Mar 9, 1978--
Jan 23, 1978Complaint (B) · Partial scope, Safety#13568985$00 viol.

Inspection #13568985

Dates

Opened
Jan 23, 1978
Closing Conference Date
Jan 23, 1978
Closed
Mar 10, 1984

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
2,900
Related Activity
1 complaint

Violations and Penalties

Total Violations
0
Initial Penalties
$0
Penalties on Record
$0
Site Address
Grand Gulf Nuclear Power Plant, Port Gibson, MS 39150
Industry
Not classified in OSHA's inspection record.

Complaint Inspection: This inspection record is categorized as a complaint inspection in the DOL OSHA enforcement data. OSHA can open complaint-driven inspections after receiving safety or health complaints from workers or their representatives.

Sep 15, 1977Complaint (B) · Partial scope, Safety#13568803$02 viol.

Inspection #13568803

Dates

Opened
Sep 15, 1977
Closing Conference Date
Sep 20, 1977
Contested
Sep 15, 1977
Closed
Dec 9, 1977

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
2,900
Related Activity
1 complaint

Violations and Penalties

Total Violations
2
Violation Types
2 other-than-serious
Initial Penalties
$0
Penalties on Record
$0
Site Address
Grand Gulf Nuclear Power Plant, Port Gibson, MS 39150
Industry
Not classified in OSHA's inspection record.

Complaint Inspection: This inspection record is categorized as a complaint inspection in the DOL OSHA enforcement data. OSHA can open complaint-driven inspections after receiving safety or health complaints from workers or their representatives.

Violations

Violation list (2 of 2 shown)
CitationStandardTypeInstancesExposedInitialCurrentAbatementContestFinal Order
010011926.600
Equipment
OSHA citation code: 19260600 A05
Other1-$0$0Oct 14, 1977Sep 15, 1977-
010021926.602
Material Handling Equipment
OSHA citation code: 19260602 A04
Other1-$0$0Oct 14, 1977Sep 15, 1977-
Sep 12, 1977Complaint (B) · Partial scope, Safety#13591615$00 viol.

Inspection #13591615

Dates

Opened
Sep 12, 1977
Closing Conference Date
Sep 12, 1977
Closed
Mar 10, 1984

Inspection

Advance Notice
Not recorded
Owner Type
Not recorded
Union Status
Yes
Number of Employees
2,900
Related Activity
1 complaint

Violations and Penalties

Total Violations
0
Initial Penalties
$0
Penalties on Record
$0
Site Address
Grand Gulf Nuclear Power Plant, Port Gibson, MS 39150
Industry
Not classified in OSHA's inspection record.

Complaint Inspection: This inspection record is categorized as a complaint inspection in the DOL OSHA enforcement data. OSHA can open complaint-driven inspections after receiving safety or health complaints from workers or their representatives.

Inspections 1 to 10 of 19, newest first

Penalty amounts may differ from final amounts after settlement or judicial review. How to read these records

About these records

A company page groups inspections with the same normalized employer name, city and state; it is not a legal-entity identifier (how pages are grouped).

This page displays public OSHA enforcement data. Status text follows the DOL inspection record first and may include citation-level context when the inspection feed and citation records are out of sync. Penalty amounts shown reflect the latest penalty amounts on record in the DOL database and may differ from initial assessments or final amounts. This is not an official OSHA resource.

OSHA's public enforcement data does not publish a "guilty" or "not guilty" field for inspections. The closest outcome fields available are the citation counts, penalty amounts, contest dates, final-order dates, and the inspection close date shown on this page. How to interpret these status fields. How initial and current penalties are recorded.

OSHA may publish multiple citation rows in the same inspection with the same standard and penalty fields. Separate rows can still differ in OSHA metadata such as citation identifier, recorded instance count, exposed workers, or gravity value. Contest and Final Order columns show citation-level dates from OSHA's enforcement record. A dash means OSHA's record does not currently show that activity for the citation.

Understanding These Penalties

The maximum penalty for a serious violation in 2025 is $16,550 per violation. For willful violations, the range is $11,823 to $165,514. The current penalty column shows the latest amount on record in OSHA's database for each citation. When the current penalty differs from the initial penalty, OSHA's records show that the amount changed during the enforcement process, but this page does not determine the specific reason for each change. Penalty amounts are set by OSHA and adjusted annually for inflation.

Standards cited

1926.102Eye and Face Protection (Construction)2 citations · $0
1926.251Rigging Equipment for Material Handling2 citations · $85
1910.1000Air Contaminants2 citations · $0

Other inspected employers in Port Gibson, MS

All employers in Port Gibson →