Jenny Lind Quarry

Metal/Non-Metal, SurfaceCrushed, Broken SandstoneSebastian, ArkansasMine ID 0300429

Operator ARKHOLAController CRH PLCMSHA status Active since Oct 3, 2025

What MSHA has on file for this mine

Citations and orders
112
since Mar 17, 2000 · 91 to the operator, 21 to contractors · 14 marked S&S
Imminent danger orders, section 107(a)
None on record
MSHA's list starts July 1, 2010
Yearly employment and hours
8 years
one row per part of the mine

MSHA records as of Nov 6, 2026. Having MSHA inspection records is common for operating mines. Data and methodology

Inspections

Regular Safety and Health Inspection
Apr 21 to Apr 22, 2026Inspectors 1 | Hours on site 11.5

The inspection

BeganINSPECTION_BEGIN_DT
Apr 21, 2026
Closed outINSPECTION_END_DT
Apr 22, 2026
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F03A7DA
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
11.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2026
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Dec 9 to Dec 10, 2025Inspectors 1 | Hours on site 14

The inspection

BeganINSPECTION_BEGIN_DT
Dec 9, 2025
Closed outINSPECTION_END_DT
Dec 10, 2025
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F022A2B
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
14
Total inspection hoursSUM_TOTAL_INSP_HOURS
19.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Dec 11 to Dec 12, 2024Inspectors 1 | Hours on site 6.5

The inspection

BeganINSPECTION_BEGIN_DT
Dec 11, 2024
Closed outINSPECTION_END_DT
Dec 12, 2024
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F013D3B
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
6.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
11.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Oct 2 to Oct 5, 2023Inspectors 1 | Hours on site 24.5

The inspection

BeganINSPECTION_BEGIN_DT
Oct 2, 2023
Closed outINSPECTION_END_DT
Oct 5, 2023
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6935727
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
24.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
31.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Jan 9 to Jan 11, 2023Inspectors 1 | Hours on site 7

The inspection

BeganINSPECTION_BEGIN_DT
Jan 9, 2023
Closed outINSPECTION_END_DT
Jan 11, 2023
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6889893
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
7
Total inspection hoursSUM_TOTAL_INSP_HOURS
19

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Verbal Hazard Complaint Inspections
Aug 1 to Aug 3, 2022Inspectors 1 | Hours on site 11

The inspection

BeganINSPECTION_BEGIN_DT
Aug 1, 2022
Closed outINSPECTION_END_DT
Aug 3, 2022
ActivityACTIVITY
Verbal Hazard Complaint Inspections
Activity codeACTIVITY_CODE
E04
Program areaPROGRAM_AREA
M/NM--Verbal Hazard Complaint Inspections
Event numberEVENT_NO
6889669
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
11
Total inspection hoursSUM_TOTAL_INSP_HOURS
14.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Aug 1 to Aug 3, 2022Inspectors 1 | Hours on site 16

The inspection

BeganINSPECTION_BEGIN_DT
Aug 1, 2022
Closed outINSPECTION_END_DT
Aug 3, 2022
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6889670
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
16
Total inspection hoursSUM_TOTAL_INSP_HOURS
17.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Feb 2 to Feb 5, 2021Inspectors 1 | Hours on site 17.75

The inspection

BeganINSPECTION_BEGIN_DT
Feb 2, 2021
Closed outINSPECTION_END_DT
Feb 5, 2021
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6886423
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
17.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2021
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Dec 4 to Dec 5, 2019Inspectors 1 | Hours on site 17.5

The inspection

BeganINSPECTION_BEGIN_DT
Dec 4, 2019
Closed outINSPECTION_END_DT
Dec 5, 2019
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6810733
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
17.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
22

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Oct 9 to Oct 11, 2018Inspectors 0 | Hours on site 0

The inspection

BeganINSPECTION_BEGIN_DT
Oct 9, 2018
Closed outINSPECTION_END_DT
Oct 11, 2018
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6806004
Inspector's office codeINSPECT_OFFICE_CD
M5871

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2019
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (16)

InspectorsNBR_INSPECTOR, Hours on siteSUM_TOTAL_ON_SITE_HOURS, Total inspection hoursSUM_TOTAL_INSP_HOURS, Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Spot Inspection
Jun 25 to Jun 26, 2018Inspectors 1 | Hours on site 11

The inspection

BeganINSPECTION_BEGIN_DT
Jun 25, 2018
Closed outINSPECTION_END_DT
Jun 26, 2018
ActivityACTIVITY
Spot Inspection
Activity codeACTIVITY_CODE
E16
Program areaPROGRAM_AREA
M/NM--Spot Inspection
Event numberEVENT_NO
6802664
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
11
Total inspection hoursSUM_TOTAL_INSP_HOURS
16

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Apr 30 to May 2, 2018Inspectors 1 | Hours on site 26

The inspection

BeganINSPECTION_BEGIN_DT
Apr 30, 2018
Closed outINSPECTION_END_DT
May 2, 2018
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6802647
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
26
Total inspection hoursSUM_TOTAL_INSP_HOURS
38.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Oct 30 to Nov 2, 2017Inspectors 1 | Hours on site 11.25

The inspection

BeganINSPECTION_BEGIN_DT
Oct 30, 2017
Closed outINSPECTION_END_DT
Nov 2, 2017
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6802612
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
11.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
16.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Jun 20 to Jun 21, 2017Inspectors 1 | Hours on site 8

The inspection

BeganINSPECTION_BEGIN_DT
Jun 20, 2017
Closed outINSPECTION_END_DT
Jun 21, 2017
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6737860
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
8
Total inspection hoursSUM_TOTAL_INSP_HOURS
18.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Part 50 Audit
Sep 28, 2016Inspectors 1 | Hours on site 2

The inspection

BeganINSPECTION_BEGIN_DT
Sep 28, 2016
Closed outINSPECTION_END_DT
Sep 28, 2016
ActivityACTIVITY
Part 50 Audit
Activity codeACTIVITY_CODE
E25
Program areaPROGRAM_AREA
M/NM--Part 50 Audit
Event numberEVENT_NO
6732393
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
2
Total inspection hoursSUM_TOTAL_INSP_HOURS
6.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Spot Inspection
Sep 28, 2016Inspectors 1 | Hours on site 6

The inspection

BeganINSPECTION_BEGIN_DT
Sep 28, 2016
Closed outINSPECTION_END_DT
Sep 28, 2016
ActivityACTIVITY
Spot Inspection
Activity codeACTIVITY_CODE
E16
Program areaPROGRAM_AREA
M/NM--Spot Inspection
Event numberEVENT_NO
6732394
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
6
Total inspection hoursSUM_TOTAL_INSP_HOURS
10

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Jun 20 to Jun 22, 2016Inspectors 1 | Hours on site 15

The inspection

BeganINSPECTION_BEGIN_DT
Jun 20, 2016
Closed outINSPECTION_END_DT
Jun 22, 2016
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6731487
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
15
Total inspection hoursSUM_TOTAL_INSP_HOURS
20.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Apr 14 to Apr 15, 2015Inspectors 1 | Hours on site 11.5

The inspection

BeganINSPECTION_BEGIN_DT
Apr 14, 2015
Closed outINSPECTION_END_DT
Apr 15, 2015
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6657742
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
11.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
20

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Nov 4 to Nov 5, 2014Inspectors 1 | Hours on site 18

The inspection

BeganINSPECTION_BEGIN_DT
Nov 4, 2014
Closed outINSPECTION_END_DT
Nov 5, 2014
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6657711
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
18
Total inspection hoursSUM_TOTAL_INSP_HOURS
29

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2014
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Apr 7 to Apr 9, 2014Inspectors 1 | Hours on site 12

The inspection

BeganINSPECTION_BEGIN_DT
Apr 7, 2014
Closed outINSPECTION_END_DT
Apr 9, 2014
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6610874
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
12
Total inspection hoursSUM_TOTAL_INSP_HOURS
19.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2014
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Oct 28 to Oct 30, 2013Inspectors 0 | Hours on site 0

The inspection

BeganINSPECTION_BEGIN_DT
Oct 28, 2013
Closed outINSPECTION_END_DT
Oct 30, 2013
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6610834
Inspector's office codeINSPECT_OFFICE_CD
M5871

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2013
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (16)

InspectorsNBR_INSPECTOR, Hours on siteSUM_TOTAL_ON_SITE_HOURS, Total inspection hoursSUM_TOTAL_INSP_HOURS, Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Part 50 Audit
Jun 26, 2013Inspectors 1 | Hours on site 5

The inspection

BeganINSPECTION_BEGIN_DT
Jun 26, 2013
Closed outINSPECTION_END_DT
Jun 26, 2013
ActivityACTIVITY
Part 50 Audit
Activity codeACTIVITY_CODE
E25
Program areaPROGRAM_AREA
M/NM--Part 50 Audit
Event numberEVENT_NO
6608252
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
5
Total inspection hoursSUM_TOTAL_INSP_HOURS
6

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2013
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2013
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Jun 24 to Jun 27, 2013Inspectors 1 | Hours on site 23.5

The inspection

BeganINSPECTION_BEGIN_DT
Jun 24, 2013
Closed outINSPECTION_END_DT
Jun 27, 2013
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6608251
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
23.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
34

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2013
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2013
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
Nov 28 to Nov 29, 2012Inspectors 1 | Hours on site 16

The inspection

BeganINSPECTION_BEGIN_DT
Nov 28, 2012
Closed outINSPECTION_END_DT
Nov 29, 2012
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6608209
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
16
Total inspection hoursSUM_TOTAL_INSP_HOURS
23

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2012
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2013
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

Regular Safety and Health Inspection
May 1 to May 2, 2012Inspectors 1 | Hours on site 20.25

The inspection

BeganINSPECTION_BEGIN_DT
May 1, 2012
Closed outINSPECTION_END_DT
May 2, 2012
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6603819
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
20.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
28.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Calendar yearCAL_YR
2012
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2012
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (2)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE

25 most recent of 68 inspections and other MSHA visits since Mar 17, 2000; activity names are MSHA's own text. Full list: MSHA Mine Data Retrieval System.

Citations and orders

Issued: Apr 22, 2026
Type: Citation
Standard: 56.14207
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
5009188
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 22, 2026
Time issuedVIOLATION_ISSUE_TIME
0731
Date of occurrenceVIOLATION_OCCUR_DT
Apr 22, 2026
30 CFR part and sectionPART_SECTION
56.14207
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 22, 2026
Originally due, timeORIG_TERM_DUE_TIME
0800
Latest dueLATEST_TERM_DUE_DT
Apr 22, 2026
Latest due, timeLATEST_TERM_DUE_TIME
0800
TerminatedTERMINATION_DT
Apr 22, 2026
Terminated, timeTERMINATION_TIME
0732
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Amount paidAMOUNT_PAID
151
Bill first printedBILL_PRINT_DT
Jun 18, 2026
Final order dateFINAL_ORDER_ISSUE_DT
Jul 27, 2026
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 4, 2026
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
F03A7DA
Inspection beganINSPECTION_BEGIN_DT
Apr 21, 2026
Inspection closed outINSPECTION_END_DT
Apr 22, 2026
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2026
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (12)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Dec 9, 2025
Type: Citation
Standard: 56.12019
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
5009102
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 9, 2025
Time issuedVIOLATION_ISSUE_TIME
1209
Date of occurrenceVIOLATION_OCCUR_DT
Dec 9, 2025
30 CFR part and sectionPART_SECTION
56.12019
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 10, 2025
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Dec 10, 2025
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Dec 10, 2025
Terminated, timeTERMINATION_TIME
0958
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Amount paidAMOUNT_PAID
151
Bill first printedBILL_PRINT_DT
Jan 14, 2026
Final order dateFINAL_ORDER_ISSUE_DT
Feb 21, 2026
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Feb 15, 2026
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
F022A2B
Inspection beganINSPECTION_BEGIN_DT
Dec 9, 2025
Inspection closed outINSPECTION_END_DT
Dec 10, 2025
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
1

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (12)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Dec 11, 2024
Type: Citation
Standard: 56.14112(a)(1)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $147.00
Details

The citation

Citation or order numberVIOLATION_NO
9795368
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 11, 2024
Time issuedVIOLATION_ISSUE_TIME
1010
Date of occurrenceVIOLATION_OCCUR_DT
Dec 11, 2024
30 CFR part and sectionPART_SECTION
56.14112(a)(1)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Mill

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 11, 2024
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Dec 11, 2024
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Dec 11, 2024
Terminated, timeTERMINATION_TIME
1303
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
147
Current proposed assessmentAMOUNT_DUE
147
Amount paidAMOUNT_PAID
147
Bill first printedBILL_PRINT_DT
Jan 15, 2025
Final order dateFINAL_ORDER_ISSUE_DT
Feb 26, 2025
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jan 30, 2025
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
F013D3B
Inspection beganINSPECTION_BEGIN_DT
Dec 11, 2024
Inspection closed outINSPECTION_END_DT
Dec 12, 2024
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (1)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (12)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Oct 3, 2023
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Contractor
Proposed penalty: $143.00
Details

The citation

Citation or order numberVIOLATION_NO
9743684
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Oct 3, 2023
Time issuedVIOLATION_ISSUE_TIME
0833
Date of occurrenceVIOLATION_OCCUR_DT
Oct 3, 2023
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 3, 2023
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Oct 3, 2023
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Oct 3, 2023
Terminated, timeTERMINATION_TIME
0834
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
143
Current proposed assessmentAMOUNT_DUE
143
Amount paidAMOUNT_PAID
143
Bill first printedBILL_PRINT_DT
Nov 21, 2023
Final order dateFINAL_ORDER_ISSUE_DT
Dec 28, 2023
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Dec 12, 2023

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Contractor
Operator at the timeVIOLATOR_NAME
Wiginton Welding Inc
Operator IDVIOLATOR_ID
B271
Contractor IDCONTRACTOR_ID
B271
Inspection eventEVENT_NO
6935727
Inspection beganINSPECTION_BEGIN_DT
Oct 2, 2023
Inspection closed outINSPECTION_END_DT
Oct 5, 2023
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (3)

Persons potentially affectedNO_AFFECTED, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Controller at the timeCONTROLLER_NAME, Controller IDCONTROLLER_ID

Issued: Oct 3, 2023
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Contractor
Proposed penalty: $143.00
Details

The citation

Citation or order numberVIOLATION_NO
9743686
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Oct 3, 2023
Time issuedVIOLATION_ISSUE_TIME
0836
Date of occurrenceVIOLATION_OCCUR_DT
Oct 3, 2023
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 3, 2023
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Oct 3, 2023
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Oct 3, 2023
Terminated, timeTERMINATION_TIME
0837
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
143
Current proposed assessmentAMOUNT_DUE
143
Amount paidAMOUNT_PAID
143
Bill first printedBILL_PRINT_DT
Nov 21, 2023
Final order dateFINAL_ORDER_ISSUE_DT
Dec 28, 2023
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Dec 12, 2023

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Contractor
Operator at the timeVIOLATOR_NAME
Wiginton Welding Inc
Operator IDVIOLATOR_ID
B271
Contractor IDCONTRACTOR_ID
B271
Inspection eventEVENT_NO
6935727
Inspection beganINSPECTION_BEGIN_DT
Oct 2, 2023
Inspection closed outINSPECTION_END_DT
Oct 5, 2023
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (3)

Persons potentially affectedNO_AFFECTED, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Controller at the timeCONTROLLER_NAME, Controller IDCONTROLLER_ID

Issued: Oct 3, 2023
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Contractor
Proposed penalty: $143.00
Details

The citation

Citation or order numberVIOLATION_NO
9743685
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Oct 3, 2023
Time issuedVIOLATION_ISSUE_TIME
0835
Date of occurrenceVIOLATION_OCCUR_DT
Oct 3, 2023
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 3, 2023
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Oct 3, 2023
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Oct 3, 2023
Terminated, timeTERMINATION_TIME
0836
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
143
Current proposed assessmentAMOUNT_DUE
143
Amount paidAMOUNT_PAID
143
Bill first printedBILL_PRINT_DT
Nov 21, 2023
Final order dateFINAL_ORDER_ISSUE_DT
Dec 28, 2023
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Dec 12, 2023

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Contractor
Operator at the timeVIOLATOR_NAME
Wiginton Welding Inc
Operator IDVIOLATOR_ID
B271
Contractor IDCONTRACTOR_ID
B271
Inspection eventEVENT_NO
6935727
Inspection beganINSPECTION_BEGIN_DT
Oct 2, 2023
Inspection closed outINSPECTION_END_DT
Oct 5, 2023
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (3)

Persons potentially affectedNO_AFFECTED, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Controller at the timeCONTROLLER_NAME, Controller IDCONTROLLER_ID

Issued: Jan 10, 2023
Type: Citation
Standard: 56.14112(a)(1)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $143.00
Details

The citation

Citation or order numberVIOLATION_NO
9674593
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jan 10, 2023
Time issuedVIOLATION_ISSUE_TIME
1029
Date of occurrenceVIOLATION_OCCUR_DT
Jan 10, 2023
30 CFR part and sectionPART_SECTION
56.14112(a)(1)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Mill

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jan 11, 2023
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Jan 11, 2023
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Jan 11, 2023
Terminated, timeTERMINATION_TIME
0807
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
143
Current proposed assessmentAMOUNT_DUE
143
Amount paidAMOUNT_PAID
143
Bill first printedBILL_PRINT_DT
Mar 7, 2023
Final order dateFINAL_ORDER_ISSUE_DT
Apr 13, 2023
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Mar 16, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6889893
Inspection beganINSPECTION_BEGIN_DT
Jan 9, 2023
Inspection closed outINSPECTION_END_DT
Jan 11, 2023
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
2

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (12)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Aug 2, 2022
Type: Citation
Standard: 56.14100(d)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9649190
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Aug 2, 2022
Time issuedVIOLATION_ISSUE_TIME
1110
Date of occurrenceVIOLATION_OCCUR_DT
Aug 2, 2022
30 CFR part and sectionPART_SECTION
56.14100(d)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Aug 2, 2022
Originally due, timeORIG_TERM_DUE_TIME
1130
Latest dueLATEST_TERM_DUE_DT
Aug 2, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1130
TerminatedTERMINATION_DT
Aug 2, 2022
Terminated, timeTERMINATION_TIME
1130
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Amount paidAMOUNT_PAID
133
Bill first printedBILL_PRINT_DT
Sep 6, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Oct 21, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Oct 4, 2022
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6889670
Inspection beganINSPECTION_BEGIN_DT
Aug 1, 2022
Inspection closed outINSPECTION_END_DT
Aug 3, 2022
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (2)

Persons potentially affectedNO_AFFECTED, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (12)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Aug 2, 2022
Type: Citation
Standard: 56.9300(a)
S&S: Y
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $840.00
Details

The citation

Citation or order numberVIOLATION_NO
9649189
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Aug 2, 2022
Time issuedVIOLATION_ISSUE_TIME
0950
Date of occurrenceVIOLATION_OCCUR_DT
Aug 2, 2022
30 CFR part and sectionPART_SECTION
56.9300(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Aug 2, 2022
Originally due, timeORIG_TERM_DUE_TIME
1000
Latest dueLATEST_TERM_DUE_DT
Aug 2, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1000
TerminatedTERMINATION_DT
Aug 2, 2022
Terminated, timeTERMINATION_TIME
1000
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
840
Current proposed assessmentAMOUNT_DUE
840
Amount paidAMOUNT_PAID
840
Bill first printedBILL_PRINT_DT
Sep 6, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Oct 21, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Oct 4, 2022
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6889670
Inspection beganINSPECTION_BEGIN_DT
Aug 1, 2022
Inspection closed outINSPECTION_END_DT
Aug 3, 2022
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (12)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Aug 1, 2022
Type: Citation
Standard: 56.11001
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9649188
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Aug 1, 2022
Time issuedVIOLATION_ISSUE_TIME
1255
Date of occurrenceVIOLATION_OCCUR_DT
Aug 1, 2022
30 CFR part and sectionPART_SECTION
56.11001
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Aug 1, 2022
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Aug 3, 2022
Latest due, timeLATEST_TERM_DUE_TIME
0700
TerminatedTERMINATION_DT
Aug 3, 2022
Terminated, timeTERMINATION_TIME
0829
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Amount paidAMOUNT_PAID
133
Bill first printedBILL_PRINT_DT
Sep 6, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Oct 21, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Oct 4, 2022

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6889670
Inspection beganINSPECTION_BEGIN_DT
Aug 1, 2022
Inspection closed outINSPECTION_END_DT
Aug 3, 2022
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (12)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Aug 1, 2022
Type: Citation
Standard: 56.14103(a)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $169.00
Details

The citation

Citation or order numberVIOLATION_NO
9649187
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Aug 1, 2022
Time issuedVIOLATION_ISSUE_TIME
1120
Date of occurrenceVIOLATION_OCCUR_DT
Aug 1, 2022
30 CFR part and sectionPART_SECTION
56.14103(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Aug 1, 2022
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Aug 3, 2022
Latest due, timeLATEST_TERM_DUE_TIME
0700
TerminatedTERMINATION_DT
Aug 3, 2022
Terminated, timeTERMINATION_TIME
0826
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
169
Current proposed assessmentAMOUNT_DUE
169
Amount paidAMOUNT_PAID
169
Bill first printedBILL_PRINT_DT
Sep 6, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Oct 21, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Oct 4, 2022

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6889670
Inspection beganINSPECTION_BEGIN_DT
Aug 1, 2022
Inspection closed outINSPECTION_END_DT
Aug 3, 2022
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (12)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: May 14, 2018
Type: Citation
Standard: 56.5001(a)/.5005
S&S: Y
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $691.00
Details

The citation

Citation or order numberVIOLATION_NO
9359466
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
May 14, 2018
Time issuedVIOLATION_ISSUE_TIME
1530
Date of occurrenceVIOLATION_OCCUR_DT
May 2, 2018
30 CFR part and sectionPART_SECTION
56.5001(a)/.5005
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
May 17, 2018
Originally due, timeORIG_TERM_DUE_TIME
1700
Latest dueLATEST_TERM_DUE_DT
Jun 22, 2018
Latest due, timeLATEST_TERM_DUE_TIME
1800
TerminatedTERMINATION_DT
Jul 11, 2018
Terminated, timeTERMINATION_TIME
1713
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
691
Current proposed assessmentAMOUNT_DUE
691
Amount paidAMOUNT_PAID
691
Bill first printedBILL_PRINT_DT
Jul 17, 2018
Final order dateFINAL_ORDER_ISSUE_DT
Aug 22, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Aug 7, 2018
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
7

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6802647
Inspection beganINSPECTION_BEGIN_DT
Apr 30, 2018
Inspection closed outINSPECTION_END_DT
May 2, 2018
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (3)

Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Apr 30, 2018
Type: Citation
Standard: 56.14100(a)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $118.00
Details

The citation

Citation or order numberVIOLATION_NO
9359459
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 30, 2018
Time issuedVIOLATION_ISSUE_TIME
1320
Date of occurrenceVIOLATION_OCCUR_DT
Apr 30, 2018
30 CFR part and sectionPART_SECTION
56.14100(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 30, 2018
Originally due, timeORIG_TERM_DUE_TIME
1700
Latest dueLATEST_TERM_DUE_DT
Apr 30, 2018
Latest due, timeLATEST_TERM_DUE_TIME
1700
TerminatedTERMINATION_DT
May 1, 2018
Terminated, timeTERMINATION_TIME
1400
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
118
Current proposed assessmentAMOUNT_DUE
118
Amount paidAMOUNT_PAID
118
Bill first printedBILL_PRINT_DT
Jun 12, 2018
Final order dateFINAL_ORDER_ISSUE_DT
Aug 11, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 17, 2018
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6802647
Inspection beganINSPECTION_BEGIN_DT
Apr 30, 2018
Inspection closed outINSPECTION_END_DT
May 2, 2018
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Oct 31, 2017
Type: Citation
Standard: 56.20003(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $116.00
Details

The citation

Citation or order numberVIOLATION_NO
9352985
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Oct 31, 2017
Time issuedVIOLATION_ISSUE_TIME
0930
Date of occurrenceVIOLATION_OCCUR_DT
Oct 31, 2017
30 CFR part and sectionPART_SECTION
56.20003(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 31, 2017
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Oct 31, 2017
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Oct 31, 2017
Terminated, timeTERMINATION_TIME
0945
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
116
Current proposed assessmentAMOUNT_DUE
116
Amount paidAMOUNT_PAID
116
Bill first printedBILL_PRINT_DT
Dec 12, 2017
Final order dateFINAL_ORDER_ISSUE_DT
Feb 10, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jan 24, 2018
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6802612
Inspection beganINSPECTION_BEGIN_DT
Oct 30, 2017
Inspection closed outINSPECTION_END_DT
Nov 2, 2017
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
1

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Jun 20, 2017
Type: Citation
Standard: 56.20003(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $116.00
Details

The citation

Citation or order numberVIOLATION_NO
9353135
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 20, 2017
Time issuedVIOLATION_ISSUE_TIME
0737
Date of occurrenceVIOLATION_OCCUR_DT
Jun 20, 2017
30 CFR part and sectionPART_SECTION
56.20003(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 20, 2017
Originally due, timeORIG_TERM_DUE_TIME
0800
Latest dueLATEST_TERM_DUE_DT
Jun 20, 2017
Latest due, timeLATEST_TERM_DUE_TIME
0800
TerminatedTERMINATION_DT
Jun 20, 2017
Terminated, timeTERMINATION_TIME
0739
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
116
Current proposed assessmentAMOUNT_DUE
116
Amount paidAMOUNT_PAID
116
Bill first printedBILL_PRINT_DT
Aug 15, 2017
Final order dateFINAL_ORDER_ISSUE_DT
Sep 29, 2017
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Oct 12, 2017
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6737860
Inspection beganINSPECTION_BEGIN_DT
Jun 20, 2017
Inspection closed outINSPECTION_END_DT
Jun 21, 2017
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Jun 21, 2016
Type: Citation
Standard: 56.14100(b)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $114.00
Details

The citation

Citation or order numberVIOLATION_NO
8965264
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 21, 2016
Time issuedVIOLATION_ISSUE_TIME
0801
Date of occurrenceVIOLATION_OCCUR_DT
Jun 21, 2016
30 CFR part and sectionPART_SECTION
56.14100(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence
Special assessmentSPECIAL_ASSESS
Y

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 22, 2016
Originally due, timeORIG_TERM_DUE_TIME
0700
Latest dueLATEST_TERM_DUE_DT
Jun 22, 2016
Latest due, timeLATEST_TERM_DUE_TIME
0700
TerminatedTERMINATION_DT
Jun 22, 2016
Terminated, timeTERMINATION_TIME
1434
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
114
Current proposed assessmentAMOUNT_DUE
114
Amount paidAMOUNT_PAID
114
Bill first printedBILL_PRINT_DT
Aug 17, 2016
Final order dateFINAL_ORDER_ISSUE_DT
Oct 1, 2016
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 14, 2016
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6731487
Inspection beganINSPECTION_BEGIN_DT
Jun 20, 2016
Inspection closed outINSPECTION_END_DT
Jun 22, 2016
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (3)

Significant and substantialSIG_SUB, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Jun 21, 2016
Type: Citation
Standard: 56.4201(a)(2)
S&S: N
Negligence: HighNegligence
Issued to: Contractor
Proposed penalty: $114.00
Details

The citation

Citation or order numberVIOLATION_NO
8965265
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 21, 2016
Time issuedVIOLATION_ISSUE_TIME
1130
Date of occurrenceVIOLATION_OCCUR_DT
Jun 21, 2016
30 CFR part and sectionPART_SECTION
56.4201(a)(2)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 21, 2016
Originally due, timeORIG_TERM_DUE_TIME
1700
Latest dueLATEST_TERM_DUE_DT
Jun 21, 2016
Latest due, timeLATEST_TERM_DUE_TIME
1700
TerminatedTERMINATION_DT
Jun 21, 2016
Terminated, timeTERMINATION_TIME
1300
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
114
Current proposed assessmentAMOUNT_DUE
114
Amount paidAMOUNT_PAID
114
Bill first printedBILL_PRINT_DT
Aug 25, 2016
Final order dateFINAL_ORDER_ISSUE_DT
Sep 30, 2016
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 18, 2016

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Contractor
Operator at the timeVIOLATOR_NAME
J A Riggs Tractor Co
Operator IDVIOLATOR_ID
FLC
Contractor IDCONTRACTOR_ID
FLC
Inspection eventEVENT_NO
6731487
Inspection beganINSPECTION_BEGIN_DT
Jun 20, 2016
Inspection closed outINSPECTION_END_DT
Jun 22, 2016
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Controller at the timeCONTROLLER_NAME, Controller IDCONTROLLER_ID

Issued: Jun 20, 2016
Type: Citation
Standard: 56.20011
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $114.00
Details

The citation

Citation or order numberVIOLATION_NO
8965263
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jun 20, 2016
Time issuedVIOLATION_ISSUE_TIME
1455
Date of occurrenceVIOLATION_OCCUR_DT
Jun 20, 2016
30 CFR part and sectionPART_SECTION
56.20011
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence
Special assessmentSPECIAL_ASSESS
Y

Abatement

Originally dueORIG_TERM_DUE_DT
Jun 20, 2016
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Jun 20, 2016
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Jun 20, 2016
Terminated, timeTERMINATION_TIME
1510
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
114
Current proposed assessmentAMOUNT_DUE
114
Amount paidAMOUNT_PAID
114
Bill first printedBILL_PRINT_DT
Aug 17, 2016
Final order dateFINAL_ORDER_ISSUE_DT
Oct 1, 2016
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 14, 2016
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6731487
Inspection beganINSPECTION_BEGIN_DT
Jun 20, 2016
Inspection closed outINSPECTION_END_DT
Jun 22, 2016
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (3)

Significant and substantialSIG_SUB, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Apr 14, 2015
Type: Citation
Standard: 56.12008
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8856796
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 14, 2015
Time issuedVIOLATION_ISSUE_TIME
0820
Date of occurrenceVIOLATION_OCCUR_DT
Apr 14, 2015
30 CFR part and sectionPART_SECTION
56.12008
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 14, 2015
Originally due, timeORIG_TERM_DUE_TIME
1000
Latest dueLATEST_TERM_DUE_DT
Apr 14, 2015
Latest due, timeLATEST_TERM_DUE_TIME
1000
TerminatedTERMINATION_DT
Apr 14, 2015
Terminated, timeTERMINATION_TIME
0930
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
Jun 17, 2015
Final order dateFINAL_ORDER_ISSUE_DT
Jul 22, 2015
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 6, 2015
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6657742
Inspection beganINSPECTION_BEGIN_DT
Apr 14, 2015
Inspection closed outINSPECTION_END_DT
Apr 15, 2015
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Apr 14, 2015
Type: Citation
Standard: 56.14100(c)
S&S: N
Negligence: ModNegligence
Issued to: Contractor
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8856800
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 14, 2015
Time issuedVIOLATION_ISSUE_TIME
0950
Date of occurrenceVIOLATION_OCCUR_DT
Apr 14, 2015
30 CFR part and sectionPART_SECTION
56.14100(c)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 14, 2015
Originally due, timeORIG_TERM_DUE_TIME
1400
Latest dueLATEST_TERM_DUE_DT
Apr 14, 2015
Latest due, timeLATEST_TERM_DUE_TIME
1400
TerminatedTERMINATION_DT
Apr 14, 2015
Terminated, timeTERMINATION_TIME
1259
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
May 21, 2015
Final order dateFINAL_ORDER_ISSUE_DT
Jun 25, 2015
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 3, 2015

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Contractor
Operator at the timeVIOLATOR_NAME
Daniel Johnson Construction
Operator IDVIOLATOR_ID
W336
Contractor IDCONTRACTOR_ID
W336
Inspection eventEVENT_NO
6657742
Inspection beganINSPECTION_BEGIN_DT
Apr 14, 2015
Inspection closed outINSPECTION_END_DT
Apr 15, 2015
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Controller at the timeCONTROLLER_NAME, Controller IDCONTROLLER_ID

Issued: Apr 14, 2015
Type: Citation
Standard: 56.20003(a)
S&S: N
Negligence: ModNegligence
Issued to: Contractor
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8864001
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 14, 2015
Time issuedVIOLATION_ISSUE_TIME
0955
Date of occurrenceVIOLATION_OCCUR_DT
Apr 14, 2015
30 CFR part and sectionPART_SECTION
56.20003(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 14, 2015
Originally due, timeORIG_TERM_DUE_TIME
1400
Latest dueLATEST_TERM_DUE_DT
Apr 14, 2015
Latest due, timeLATEST_TERM_DUE_TIME
1400
TerminatedTERMINATION_DT
Apr 14, 2015
Terminated, timeTERMINATION_TIME
1300
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
May 21, 2015
Final order dateFINAL_ORDER_ISSUE_DT
Jun 25, 2015
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 3, 2015

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Contractor
Operator at the timeVIOLATOR_NAME
Daniel Johnson Construction
Operator IDVIOLATOR_ID
W336
Contractor IDCONTRACTOR_ID
W336
Inspection eventEVENT_NO
6657742
Inspection beganINSPECTION_BEGIN_DT
Apr 14, 2015
Inspection closed outINSPECTION_END_DT
Apr 15, 2015
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Controller at the timeCONTROLLER_NAME, Controller IDCONTROLLER_ID

Issued: Apr 14, 2015
Type: Citation
Standard: 56.14100(c)
S&S: N
Negligence: ModNegligence
Issued to: Contractor
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8856798
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 14, 2015
Time issuedVIOLATION_ISSUE_TIME
0948
Date of occurrenceVIOLATION_OCCUR_DT
Apr 14, 2015
30 CFR part and sectionPART_SECTION
56.14100(c)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 14, 2015
Originally due, timeORIG_TERM_DUE_TIME
1400
Latest dueLATEST_TERM_DUE_DT
Apr 14, 2015
Latest due, timeLATEST_TERM_DUE_TIME
1400
TerminatedTERMINATION_DT
Apr 14, 2015
Terminated, timeTERMINATION_TIME
1258
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
May 21, 2015
Final order dateFINAL_ORDER_ISSUE_DT
Jun 25, 2015
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 3, 2015

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Contractor
Operator at the timeVIOLATOR_NAME
Daniel Johnson Construction
Operator IDVIOLATOR_ID
W336
Contractor IDCONTRACTOR_ID
W336
Inspection eventEVENT_NO
6657742
Inspection beganINSPECTION_BEGIN_DT
Apr 14, 2015
Inspection closed outINSPECTION_END_DT
Apr 15, 2015
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Controller at the timeCONTROLLER_NAME, Controller IDCONTROLLER_ID

Issued: Apr 14, 2015
Type: Citation
Standard: 56.4200(b)(2)
S&S: N
Negligence: ModNegligence
Issued to: Contractor
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8856799
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 14, 2015
Time issuedVIOLATION_ISSUE_TIME
0949
Date of occurrenceVIOLATION_OCCUR_DT
Apr 14, 2015
30 CFR part and sectionPART_SECTION
56.4200(b)(2)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 14, 2015
Originally due, timeORIG_TERM_DUE_TIME
1100
Latest dueLATEST_TERM_DUE_DT
Apr 14, 2015
Latest due, timeLATEST_TERM_DUE_TIME
1100
TerminatedTERMINATION_DT
Apr 14, 2015
Terminated, timeTERMINATION_TIME
1240
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
May 21, 2015
Final order dateFINAL_ORDER_ISSUE_DT
Jun 25, 2015
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 3, 2015

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Contractor
Operator at the timeVIOLATOR_NAME
Daniel Johnson Construction
Operator IDVIOLATOR_ID
W336
Contractor IDCONTRACTOR_ID
W336
Inspection eventEVENT_NO
6657742
Inspection beganINSPECTION_BEGIN_DT
Apr 14, 2015
Inspection closed outINSPECTION_END_DT
Apr 15, 2015
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Controller at the timeCONTROLLER_NAME, Controller IDCONTROLLER_ID

Issued: Nov 4, 2014
Type: Citation
Standard: 56.9300(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8856632
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Nov 4, 2014
Time issuedVIOLATION_ISSUE_TIME
0800
Date of occurrenceVIOLATION_OCCUR_DT
Nov 4, 2014
30 CFR part and sectionPART_SECTION
56.9300(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Nov 4, 2014
Originally due, timeORIG_TERM_DUE_TIME
0830
Latest dueLATEST_TERM_DUE_DT
Nov 4, 2014
Latest due, timeLATEST_TERM_DUE_TIME
0830
TerminatedTERMINATION_DT
Nov 4, 2014
Terminated, timeTERMINATION_TIME
0830
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
Dec 17, 2014
Final order dateFINAL_ORDER_ISSUE_DT
Feb 8, 2015
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Feb 17, 2015
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6657711
Inspection beganINSPECTION_BEGIN_DT
Nov 4, 2014
Inspection closed outINSPECTION_END_DT
Nov 5, 2014
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2014
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
1

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

Issued: Apr 8, 2014
Type: Citation
Standard: 56.11027
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $100.00
Details

The citation

Citation or order numberVIOLATION_NO
8766222
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 8, 2014
Time issuedVIOLATION_ISSUE_TIME
1052
Date of occurrenceVIOLATION_OCCUR_DT
Apr 8, 2014
30 CFR part and sectionPART_SECTION
56.11027
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 8, 2014
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Apr 8, 2014
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Apr 8, 2014
Terminated, timeTERMINATION_TIME
1531
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
100
Current proposed assessmentAMOUNT_DUE
100
Amount paidAMOUNT_PAID
100
Bill first printedBILL_PRINT_DT
May 14, 2014
Final order dateFINAL_ORDER_ISSUE_DT
Jun 18, 2014
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 3, 2014
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
ARKHOLA
Operator IDVIOLATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Inspection eventEVENT_NO
6610874
Inspection beganINSPECTION_BEGIN_DT
Apr 7, 2014
Inspection closed outINSPECTION_END_DT
Apr 9, 2014
Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2014
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID

112 citations and orders since Mar 17, 2000: 91 issued to the operator, 21 to contractors working at the mine; the 25 most recent are listed. Proposed penalty is MSHA's original proposed amount, before any change from a contested case. Citations can be contested, modified or vacated.

Penalties as assessed

Issued: Apr 22, 2026
Citation number: 5009188
Standard: 56.14207
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $151.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
5009188
Assessment control numberASSESS_CASE_NO
000643291
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 4, 2026
Citation issuedISSUE_DT
Apr 22, 2026
Date of occurrenceOCCURRENCE_DT
Apr 22, 2026
Final order dateFINAL_ORDER_DT
Jul 27, 2026
Bill first printedBILL_PRINT_DT
Jun 18, 2026
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2026
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 27, 2026
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14207
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
151.00

Penalty points

Violation history pointsPENALTY_POINTS
38
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
10

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
0.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
11783
Size of mineSIZE_OF_MINE
11783
Controller hours workedCONTROLLER_HRS
12704522
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
12704522
History period startHISTORY_START_DT
Jan 22, 2025
History period endHISTORY_END_DT
Apr 21, 2026

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
ARKHOLA
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F03A7DA
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 9, 2025
Citation number: 5009102
Standard: 56.12019
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $151.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
5009102
Assessment control numberASSESS_CASE_NO
000634630
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Feb 15, 2026
Citation issuedISSUE_DT
Dec 9, 2025
Date of occurrenceOCCURRENCE_DT
Dec 9, 2025
Final order dateFINAL_ORDER_DT
Feb 21, 2026
Bill first printedBILL_PRINT_DT
Jan 14, 2026
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2026
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Feb 21, 2026
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12019
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
151.00

Penalty points

Violation history pointsPENALTY_POINTS
48
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
10

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
0.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
19716
Size of mineSIZE_OF_MINE
19716
Controller hours workedCONTROLLER_HRS
13036314
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
13036314
History period startHISTORY_START_DT
Sep 9, 2024
History period endHISTORY_END_DT
Dec 8, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
ARKHOLA
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F022A2B
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 11, 2024
Citation number: 9795368
Standard: 56.14112(a)(1)
Proposed penalty: $147.00
Current assessment: $147.00
Paid against proposed penalty: $147.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9795368
Assessment control numberASSESS_CASE_NO
000613577
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jan 30, 2025
Citation issuedISSUE_DT
Dec 11, 2024
Date of occurrenceOCCURRENCE_DT
Dec 11, 2024
Final order dateFINAL_ORDER_DT
Feb 26, 2025
Bill first printedBILL_PRINT_DT
Jan 15, 2025
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Feb 26, 2025
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14112(a)(1)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
147.00
Current assessmentCURRENT_ASSESSMENT_AMT
147.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
147.00

Penalty points

Violation history pointsPENALTY_POINTS
53
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
10

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Operator hours worked at the mineVIOLATOR_MINE_HRS
19079
Size of mineSIZE_OF_MINE
19079
Controller hours workedCONTROLLER_HRS
12277501
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
12277501
History period startHISTORY_START_DT
Sep 11, 2023
History period endHISTORY_END_DT
Dec 10, 2024

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
ARKHOLA
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
F013D3B
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Oct 3, 2023
Citation number: 9743686
Standard: 50.30(a)
Proposed penalty: $143.00
Current assessment: $143.00
Paid against proposed penalty: $143.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9743686
Assessment control numberASSESS_CASE_NO
000589551
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Dec 12, 2023
Citation issuedISSUE_DT
Oct 3, 2023
Date of occurrenceOCCURRENCE_DT
Oct 3, 2023
Final order dateFINAL_ORDER_DT
Dec 28, 2023
Bill first printedBILL_PRINT_DT
Nov 21, 2023
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2024
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 28, 2023
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
143.00
Current assessmentCURRENT_ASSESSMENT_AMT
143.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
143.00

Penalty points

Violation history pointsPENALTY_POINTS
35
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
2333
Size of mineSIZE_OF_MINE
2333
History period startHISTORY_START_DT
Jul 3, 2022
History period endHISTORY_END_DT
Oct 2, 2023

Who

Issued toVIOLATOR_TYPE_CD
Contractor
Name at the time of the assessmentVIOLATOR_NAME
Wiginton Welding Inc
IDVIOLATOR_ID
B271
Operator start at the mine, as assessedVIOLATOR_START_DT
Feb 23, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6935727
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (21)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller hours workedCONTROLLER_HRS, Controller tonnageCONTROLLER_PRODUCTION_AMT, Size of controlling entitySIZE_OF_CONTROLLING_ENTITY

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Mine Act sectionMINE_ACT_SECTION_CD, Controller size pointsCONTROLLER_SIZE_POINTS

Issued: Oct 3, 2023
Citation number: 9743685
Standard: 50.30(a)
Proposed penalty: $143.00
Current assessment: $143.00
Paid against proposed penalty: $143.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9743685
Assessment control numberASSESS_CASE_NO
000589551
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Dec 12, 2023
Citation issuedISSUE_DT
Oct 3, 2023
Date of occurrenceOCCURRENCE_DT
Oct 3, 2023
Final order dateFINAL_ORDER_DT
Dec 28, 2023
Bill first printedBILL_PRINT_DT
Nov 21, 2023
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2024
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 28, 2023
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
143.00
Current assessmentCURRENT_ASSESSMENT_AMT
143.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
143.00

Penalty points

Violation history pointsPENALTY_POINTS
35
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
2333
Size of mineSIZE_OF_MINE
2333
History period startHISTORY_START_DT
Jul 3, 2022
History period endHISTORY_END_DT
Oct 2, 2023

Who

Issued toVIOLATOR_TYPE_CD
Contractor
Name at the time of the assessmentVIOLATOR_NAME
Wiginton Welding Inc
IDVIOLATOR_ID
B271
Operator start at the mine, as assessedVIOLATOR_START_DT
Feb 23, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6935727
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (21)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller hours workedCONTROLLER_HRS, Controller tonnageCONTROLLER_PRODUCTION_AMT, Size of controlling entitySIZE_OF_CONTROLLING_ENTITY

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Mine Act sectionMINE_ACT_SECTION_CD, Controller size pointsCONTROLLER_SIZE_POINTS

Issued: Oct 3, 2023
Citation number: 9743684
Standard: 50.30(a)
Proposed penalty: $143.00
Current assessment: $143.00
Paid against proposed penalty: $143.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9743684
Assessment control numberASSESS_CASE_NO
000589551
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Dec 12, 2023
Citation issuedISSUE_DT
Oct 3, 2023
Date of occurrenceOCCURRENCE_DT
Oct 3, 2023
Final order dateFINAL_ORDER_DT
Dec 28, 2023
Bill first printedBILL_PRINT_DT
Nov 21, 2023
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2024
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 28, 2023
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
143.00
Current assessmentCURRENT_ASSESSMENT_AMT
143.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
143.00

Penalty points

Violation history pointsPENALTY_POINTS
35
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
2333
Size of mineSIZE_OF_MINE
2333
History period startHISTORY_START_DT
Jul 3, 2022
History period endHISTORY_END_DT
Oct 2, 2023

Who

Issued toVIOLATOR_TYPE_CD
Contractor
Name at the time of the assessmentVIOLATOR_NAME
Wiginton Welding Inc
IDVIOLATOR_ID
B271
Operator start at the mine, as assessedVIOLATOR_START_DT
Feb 23, 2001
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6935727
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (21)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller hours workedCONTROLLER_HRS, Controller tonnageCONTROLLER_PRODUCTION_AMT, Size of controlling entitySIZE_OF_CONTROLLING_ENTITY

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Mine Act sectionMINE_ACT_SECTION_CD, Controller size pointsCONTROLLER_SIZE_POINTS

Issued: Jan 10, 2023
Citation number: 9674593
Standard: 56.14112(a)(1)
Proposed penalty: $143.00
Current assessment: $143.00
Paid against proposed penalty: $143.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9674593
Assessment control numberASSESS_CASE_NO
000572355
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Mar 16, 2023
Citation issuedISSUE_DT
Jan 10, 2023
Date of occurrenceOCCURRENCE_DT
Jan 10, 2023
Final order dateFINAL_ORDER_DT
Apr 13, 2023
Bill first printedBILL_PRINT_DT
Mar 7, 2023
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2023
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Apr 13, 2023
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14112(a)(1)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
143.00
Current assessmentCURRENT_ASSESSMENT_AMT
143.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
143.00

Penalty points

Violation history pointsPENALTY_POINTS
53
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
10

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6
Violations per inspection dayVPID
0.67
Operator hours worked at the mineVIOLATOR_MINE_HRS
15265
Size of mineSIZE_OF_MINE
15265
Controller hours workedCONTROLLER_HRS
11720028
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
11720028
History period startHISTORY_START_DT
Oct 10, 2021
History period endHISTORY_END_DT
Jan 9, 2023

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
ARKHOLA
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889893
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Aug 2, 2022
Citation number: 9649189
Standard: 56.9300(a)
Proposed penalty: $840.00
Current assessment: $840.00
Paid against proposed penalty: $840.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9649189
Assessment control numberASSESS_CASE_NO
000562152
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Oct 4, 2022
Citation issuedISSUE_DT
Aug 2, 2022
Date of occurrenceOCCURRENCE_DT
Aug 2, 2022
Final order dateFINAL_ORDER_DT
Oct 21, 2022
Bill first printedBILL_PRINT_DT
Sep 6, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.9300(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
840.00
Current assessmentCURRENT_ASSESSMENT_AMT
840.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
840.00

Penalty points

Violation history pointsPENALTY_POINTS
83
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
10

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Operator hours worked at the mineVIOLATOR_MINE_HRS
14274
Size of mineSIZE_OF_MINE
14274
Controller hours workedCONTROLLER_HRS
11423989
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
11423989
History period startHISTORY_START_DT
May 2, 2021
History period endHISTORY_END_DT
Aug 1, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
ARKHOLA
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889670
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Aug 2, 2022
Citation number: 9649190
Standard: 56.14100(d)
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $133.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9649190
Assessment control numberASSESS_CASE_NO
000562152
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Oct 4, 2022
Citation issuedISSUE_DT
Aug 2, 2022
Date of occurrenceOCCURRENCE_DT
Aug 2, 2022
Final order dateFINAL_ORDER_DT
Oct 21, 2022
Bill first printedBILL_PRINT_DT
Sep 6, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(d)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
133.00

Penalty points

Violation history pointsPENALTY_POINTS
47
Negligence pointsNEGLIGENCE_POINTS
35
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
10

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Operator hours worked at the mineVIOLATOR_MINE_HRS
14274
Size of mineSIZE_OF_MINE
14274
Controller hours workedCONTROLLER_HRS
11423989
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
11423989
History period startHISTORY_START_DT
May 2, 2021
History period endHISTORY_END_DT
Aug 1, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
ARKHOLA
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889670
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (17)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Aug 1, 2022
Citation number: 9649187
Standard: 56.14103(a)
Proposed penalty: $169.00
Current assessment: $169.00
Paid against proposed penalty: $169.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9649187
Assessment control numberASSESS_CASE_NO
000562152
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Oct 4, 2022
Citation issuedISSUE_DT
Aug 1, 2022
Date of occurrenceOCCURRENCE_DT
Aug 1, 2022
Final order dateFINAL_ORDER_DT
Oct 21, 2022
Bill first printedBILL_PRINT_DT
Sep 6, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14103(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
169.00
Current assessmentCURRENT_ASSESSMENT_AMT
169.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
169.00

Penalty points

Violation history pointsPENALTY_POINTS
63
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
35
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
10

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
14274
Size of mineSIZE_OF_MINE
14274
Controller hours workedCONTROLLER_HRS
11423989
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
11423989
History period startHISTORY_START_DT
May 1, 2021
History period endHISTORY_END_DT
Jul 31, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
ARKHOLA
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889670
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Aug 1, 2022
Citation number: 9649188
Standard: 56.11001
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $133.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9649188
Assessment control numberASSESS_CASE_NO
000562152
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Oct 4, 2022
Citation issuedISSUE_DT
Aug 1, 2022
Date of occurrenceOCCURRENCE_DT
Aug 1, 2022
Final order dateFINAL_ORDER_DT
Oct 21, 2022
Bill first printedBILL_PRINT_DT
Sep 6, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.11001
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
133.00

Penalty points

Violation history pointsPENALTY_POINTS
48
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
10

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
14274
Size of mineSIZE_OF_MINE
14274
Controller hours workedCONTROLLER_HRS
11423989
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
11423989
History period startHISTORY_START_DT
May 1, 2021
History period endHISTORY_END_DT
Jul 31, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
ARKHOLA
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889670
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: May 14, 2018
Citation number: 9359466
Standard: 56.5001(a)/.5005
Proposed penalty: $691.00
Current assessment: $691.00
Paid against proposed penalty: $691.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9359466
Assessment control numberASSESS_CASE_NO
000468927
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Aug 7, 2018
Citation issuedISSUE_DT
May 14, 2018
Date of occurrenceOCCURRENCE_DT
May 2, 2018
Final order dateFINAL_ORDER_DT
Aug 22, 2018
Bill first printedBILL_PRINT_DT
Jul 17, 2018
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 22, 2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.5001(a)/.5005
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
691.00
Current assessmentCURRENT_ASSESSMENT_AMT
691.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
691.00

Penalty points

Violation history pointsPENALTY_POINTS
82
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
9

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
7
Violations per inspection dayVPID
0.29
Operator hours worked at the mineVIOLATOR_MINE_HRS
14316
Size of mineSIZE_OF_MINE
14316
Controller hours workedCONTROLLER_HRS
8756596
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
8756596
History period startHISTORY_START_DT
Feb 2, 2017
History period endHISTORY_END_DT
May 1, 2018

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
ARKHOLA
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6802647
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 30, 2018
Citation number: 9359459
Standard: 56.14100(a)
Proposed penalty: $118.00
Current assessment: $118.00
Paid against proposed penalty: $118.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9359459
Assessment control numberASSESS_CASE_NO
000466751
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 17, 2018
Citation issuedISSUE_DT
Apr 30, 2018
Date of occurrenceOCCURRENCE_DT
Apr 30, 2018
Final order dateFINAL_ORDER_DT
Aug 11, 2018
Bill first printedBILL_PRINT_DT
Jun 12, 2018
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 11, 2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
118.00
Current assessmentCURRENT_ASSESSMENT_AMT
118.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
118.00

Penalty points

Violation history pointsPENALTY_POINTS
37
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
9

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
0.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
14316
Size of mineSIZE_OF_MINE
14316
Controller hours workedCONTROLLER_HRS
8756589
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
8756589
History period startHISTORY_START_DT
Jan 30, 2017
History period endHISTORY_END_DT
Apr 29, 2018

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
ARKHOLA
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6802647
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Oct 31, 2017
Citation number: 9352985
Standard: 56.20003(a)
Proposed penalty: $116.00
Current assessment: $116.00
Paid against proposed penalty: $116.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9352985
Assessment control numberASSESS_CASE_NO
000454429
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jan 23, 2018
Citation issuedISSUE_DT
Oct 31, 2017
Date of occurrenceOCCURRENCE_DT
Oct 31, 2017
Final order dateFINAL_ORDER_DT
Feb 10, 2018
Bill first printedBILL_PRINT_DT
Dec 12, 2017
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Feb 10, 2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.20003(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
116.00
Current assessmentCURRENT_ASSESSMENT_AMT
116.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
116.00

Penalty points

Violation history pointsPENALTY_POINTS
47
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
9

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
0.75
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
1
Repeat violations per inspection dayRPID
0.25
Operator hours worked at the mineVIOLATOR_MINE_HRS
18102
Size of mineSIZE_OF_MINE
18102
Controller hours workedCONTROLLER_HRS
8576982
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
8576982
History period startHISTORY_START_DT
Jul 31, 2016
History period endHISTORY_END_DT
Oct 30, 2017

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
APAC-Central, Inc.
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6802612
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (10)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jun 20, 2017
Citation number: 9353135
Standard: 56.20003(a)
Proposed penalty: $116.00
Current assessment: $116.00
Paid against proposed penalty: $116.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9353135
Assessment control numberASSESS_CASE_NO
000445633
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Oct 11, 2017
Citation issuedISSUE_DT
Jun 20, 2017
Date of occurrenceOCCURRENCE_DT
Jun 20, 2017
Final order dateFINAL_ORDER_DT
Sep 29, 2017
Bill first printedBILL_PRINT_DT
Aug 15, 2017
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2017
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.20003(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
116.00
Current assessmentCURRENT_ASSESSMENT_AMT
116.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
116.00

Penalty points

Violation history pointsPENALTY_POINTS
47
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
2
Controller size pointsCONTROLLER_SIZE_POINTS
9

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
0.4
Operator hours worked at the mineVIOLATOR_MINE_HRS
18102
Size of mineSIZE_OF_MINE
18102
Controller hours workedCONTROLLER_HRS
8555454
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
8555454
History period startHISTORY_START_DT
Mar 20, 2016
History period endHISTORY_END_DT
Jun 19, 2017

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
APAC-Central, Inc.
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6737860
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jun 21, 2016
Citation number: 8965264
Standard: 56.14100(b)
Proposed penalty: $114.00
Current assessment: $114.00
Paid against proposed penalty: $114.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8965264
Assessment control numberASSESS_CASE_NO
000417594
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 13, 2016
Citation issuedISSUE_DT
Jun 21, 2016
Date of occurrenceOCCURRENCE_DT
Jun 21, 2016
Final order dateFINAL_ORDER_DT
Oct 1, 2016
Bill first printedBILL_PRINT_DT
Aug 17, 2016
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2016
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
114.00
Current assessmentCURRENT_ASSESSMENT_AMT
114.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
114.00

Penalty points

Violation history pointsPENALTY_POINTS
38
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10
Mine size pointsMINE_SIZE_POINTS
3
Controller size pointsCONTROLLER_SIZE_POINTS
9

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
0.25
Operator hours worked at the mineVIOLATOR_MINE_HRS
25898
Size of mineSIZE_OF_MINE
25898
Controller hours workedCONTROLLER_HRS
7725230
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
7725230
History period startHISTORY_START_DT
Mar 21, 2015
History period endHISTORY_END_DT
Jun 20, 2016

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
APAC-Central, Inc.
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6731487
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jun 21, 2016
Citation number: 8965265
Standard: 56.4201(a)(2)
Proposed penalty: $114.00
Current assessment: $114.00
Paid against proposed penalty: $114.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8965265
Assessment control numberASSESS_CASE_NO
000418332
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 16, 2016
Citation issuedISSUE_DT
Jun 21, 2016
Date of occurrenceOCCURRENCE_DT
Jun 21, 2016
Final order dateFINAL_ORDER_DT
Sep 30, 2016
Bill first printedBILL_PRINT_DT
Aug 25, 2016
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2016
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Sep 30, 2016
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.4201(a)(2)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
114.00
Current assessmentCURRENT_ASSESSMENT_AMT
114.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
114.00

Penalty points

Violation history pointsPENALTY_POINTS
59
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
35
Contractor size pointsCONTRACTOR_SIZE_POINTS
8

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
27522
Size of mineSIZE_OF_MINE
27522
History period startHISTORY_START_DT
Mar 21, 2015
History period endHISTORY_END_DT
Jun 20, 2016

Who

Issued toVIOLATOR_TYPE_CD
Contractor
Name at the time of the assessmentVIOLATOR_NAME
J A Riggs Tractor Co
IDVIOLATOR_ID
FLC
Operator start at the mine, as assessedVIOLATOR_START_DT
Apr 6, 1999
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6731487
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (17)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller hours workedCONTROLLER_HRS, Controller tonnageCONTROLLER_PRODUCTION_AMT, Size of controlling entitySIZE_OF_CONTROLLING_ENTITY

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Mine Act sectionMINE_ACT_SECTION_CD, Controller size pointsCONTROLLER_SIZE_POINTS

Issued: Jun 20, 2016
Citation number: 8965263
Standard: 56.20011
Proposed penalty: $114.00
Current assessment: $114.00
Paid against proposed penalty: $114.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8965263
Assessment control numberASSESS_CASE_NO
000417594
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 13, 2016
Citation issuedISSUE_DT
Jun 20, 2016
Date of occurrenceOCCURRENCE_DT
Jun 20, 2016
Final order dateFINAL_ORDER_DT
Oct 1, 2016
Bill first printedBILL_PRINT_DT
Aug 17, 2016
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2016
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.20011
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
114.00
Current assessmentCURRENT_ASSESSMENT_AMT
114.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
114.00

Penalty points

Violation history pointsPENALTY_POINTS
53
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10
Mine size pointsMINE_SIZE_POINTS
3
Controller size pointsCONTROLLER_SIZE_POINTS
9

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
1
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
0.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
25898
Size of mineSIZE_OF_MINE
25898
Controller hours workedCONTROLLER_HRS
7725230
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
7725230
History period startHISTORY_START_DT
Mar 20, 2015
History period endHISTORY_END_DT
Jun 19, 2016

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
APAC-Central, Inc.
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6731487
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 14, 2015
Citation number: 8856796
Standard: 56.12008
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8856796
Assessment control numberASSESS_CASE_NO
000384236
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 6, 2015
Citation issuedISSUE_DT
Apr 14, 2015
Date of occurrenceOCCURRENCE_DT
Apr 14, 2015
Final order dateFINAL_ORDER_DT
Jul 22, 2015
Bill first printedBILL_PRINT_DT
Jun 17, 2015
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2015
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 22, 2015
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12008
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
49
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
4
Controller size pointsCONTROLLER_SIZE_POINTS
9

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6
Violations per inspection dayVPID
0.67
Operator hours worked at the mineVIOLATOR_MINE_HRS
33585
Size of mineSIZE_OF_MINE
33585
Controller hours workedCONTROLLER_HRS
7174116
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
7174116
History period startHISTORY_START_DT
Jan 14, 2014
History period endHISTORY_END_DT
Apr 13, 2015

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
APAC-Central, Inc.
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6657742
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 14, 2015
Citation number: 8864001
Standard: 56.20003(a)
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8864001
Assessment control numberASSESS_CASE_NO
000382090
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 3, 2015
Citation issuedISSUE_DT
Apr 14, 2015
Date of occurrenceOCCURRENCE_DT
Apr 14, 2015
Final order dateFINAL_ORDER_DT
Jun 25, 2015
Bill first printedBILL_PRINT_DT
May 21, 2015
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2015
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jun 25, 2015
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.20003(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
4355
Size of mineSIZE_OF_MINE
4355
History period startHISTORY_START_DT
Jan 14, 2014
History period endHISTORY_END_DT
Apr 13, 2015

Who

Issued toVIOLATOR_TYPE_CD
Contractor
Name at the time of the assessmentVIOLATOR_NAME
Daniel Johnson Construction
IDVIOLATOR_ID
W336
Operator start at the mine, as assessedVIOLATOR_START_DT
Apr 14, 2015
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6657742
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (18)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller hours workedCONTROLLER_HRS, Controller tonnageCONTROLLER_PRODUCTION_AMT, Size of controlling entitySIZE_OF_CONTROLLING_ENTITY

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Mine Act sectionMINE_ACT_SECTION_CD, Controller size pointsCONTROLLER_SIZE_POINTS

Issued: Apr 14, 2015
Citation number: 8856800
Standard: 56.14100(c)
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8856800
Assessment control numberASSESS_CASE_NO
000382090
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 3, 2015
Citation issuedISSUE_DT
Apr 14, 2015
Date of occurrenceOCCURRENCE_DT
Apr 14, 2015
Final order dateFINAL_ORDER_DT
Jun 25, 2015
Bill first printedBILL_PRINT_DT
May 21, 2015
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2015
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jun 25, 2015
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(c)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
4355
Size of mineSIZE_OF_MINE
4355
History period startHISTORY_START_DT
Jan 14, 2014
History period endHISTORY_END_DT
Apr 13, 2015

Who

Issued toVIOLATOR_TYPE_CD
Contractor
Name at the time of the assessmentVIOLATOR_NAME
Daniel Johnson Construction
IDVIOLATOR_ID
W336
Operator start at the mine, as assessedVIOLATOR_START_DT
Apr 14, 2015
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6657742
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (18)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller hours workedCONTROLLER_HRS, Controller tonnageCONTROLLER_PRODUCTION_AMT, Size of controlling entitySIZE_OF_CONTROLLING_ENTITY

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Mine Act sectionMINE_ACT_SECTION_CD, Controller size pointsCONTROLLER_SIZE_POINTS

Issued: Apr 14, 2015
Citation number: 8856799
Standard: 56.4200(b)(2)
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8856799
Assessment control numberASSESS_CASE_NO
000382090
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 3, 2015
Citation issuedISSUE_DT
Apr 14, 2015
Date of occurrenceOCCURRENCE_DT
Apr 14, 2015
Final order dateFINAL_ORDER_DT
Jun 25, 2015
Bill first printedBILL_PRINT_DT
May 21, 2015
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2015
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jun 25, 2015
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.4200(b)(2)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
4355
Size of mineSIZE_OF_MINE
4355
History period startHISTORY_START_DT
Jan 14, 2014
History period endHISTORY_END_DT
Apr 13, 2015

Who

Issued toVIOLATOR_TYPE_CD
Contractor
Name at the time of the assessmentVIOLATOR_NAME
Daniel Johnson Construction
IDVIOLATOR_ID
W336
Operator start at the mine, as assessedVIOLATOR_START_DT
Apr 14, 2015
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6657742
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (18)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller hours workedCONTROLLER_HRS, Controller tonnageCONTROLLER_PRODUCTION_AMT, Size of controlling entitySIZE_OF_CONTROLLING_ENTITY

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Mine Act sectionMINE_ACT_SECTION_CD, Controller size pointsCONTROLLER_SIZE_POINTS

Issued: Apr 14, 2015
Citation number: 8856798
Standard: 56.14100(c)
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8856798
Assessment control numberASSESS_CASE_NO
000382090
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 3, 2015
Citation issuedISSUE_DT
Apr 14, 2015
Date of occurrenceOCCURRENCE_DT
Apr 14, 2015
Final order dateFINAL_ORDER_DT
Jun 25, 2015
Bill first printedBILL_PRINT_DT
May 21, 2015
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2015
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jun 25, 2015
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(c)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Operator hours worked at the mineVIOLATOR_MINE_HRS
4355
Size of mineSIZE_OF_MINE
4355
History period startHISTORY_START_DT
Jan 14, 2014
History period endHISTORY_END_DT
Apr 13, 2015

Who

Issued toVIOLATOR_TYPE_CD
Contractor
Name at the time of the assessmentVIOLATOR_NAME
Daniel Johnson Construction
IDVIOLATOR_ID
W336
Operator start at the mine, as assessedVIOLATOR_START_DT
Apr 14, 2015
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6657742
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (18)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller hours workedCONTROLLER_HRS, Controller tonnageCONTROLLER_PRODUCTION_AMT, Size of controlling entitySIZE_OF_CONTROLLING_ENTITY

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Mine Act sectionMINE_ACT_SECTION_CD, Controller size pointsCONTROLLER_SIZE_POINTS

Issued: Nov 4, 2014
Citation number: 8856632
Standard: 56.9300(a)
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8856632
Assessment control numberASSESS_CASE_NO
000369656
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Feb 17, 2015
Citation issuedISSUE_DT
Nov 4, 2014
Date of occurrenceOCCURRENCE_DT
Nov 4, 2014
Final order dateFINAL_ORDER_DT
Feb 8, 2015
Bill first printedBILL_PRINT_DT
Dec 17, 2014
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2015
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Feb 8, 2015
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.9300(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
49
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
4
Controller size pointsCONTROLLER_SIZE_POINTS
9

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
30988
Size of mineSIZE_OF_MINE
30988
Controller hours workedCONTROLLER_HRS
7213241
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
7213241
History period startHISTORY_START_DT
Aug 4, 2013
History period endHISTORY_END_DT
Nov 3, 2014

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
APAC-Central, Inc.
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6657711
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 8, 2014
Citation number: 8766222
Standard: 56.11027
Proposed penalty: $100.00
Current assessment: $100.00
Paid against proposed penalty: $100.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8766222
Assessment control numberASSESS_CASE_NO
000350936
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 3, 2014
Citation issuedISSUE_DT
Apr 8, 2014
Date of occurrenceOCCURRENCE_DT
Apr 8, 2014
Final order dateFINAL_ORDER_DT
Jun 18, 2014
Bill first printedBILL_PRINT_DT
May 14, 2014
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2014
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jun 18, 2014
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.11027
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
100.00
Current assessmentCURRENT_ASSESSMENT_AMT
100.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
100.00

Penalty points

Violation history pointsPENALTY_POINTS
49
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
4
Controller size pointsCONTROLLER_SIZE_POINTS
9

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
4
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6
Violations per inspection dayVPID
0.67
Operator hours worked at the mineVIOLATOR_MINE_HRS
30988
Size of mineSIZE_OF_MINE
30988
Controller hours workedCONTROLLER_HRS
7217541
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
7217541
History period startHISTORY_START_DT
Jan 8, 2013
History period endHISTORY_END_DT
Apr 7, 2014

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
APAC-Central, Inc.
IDVIOLATOR_ID
L11502
Operator start at the mine, as assessedVIOLATOR_START_DT
Jan 1, 1950
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6610874
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

25 most recent of 112 assessed citations and orders. Amounts are MSHA's per-citation values; case status is MSHA's own (Closed, Invalid, Printed or Received).

Contested citations and decisions

Contested: Jan 4, 2012
Citation issued: Oct 25, 2011
Docket: CENT 2012-263M
Standard: 56.4102
Proposed penalty: $2,106.00
Penalty after decision: $947.00
Decided: Oct 3, 2012
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
8623495
Citation issuedCITATION_ISSUE_DT
Oct 25, 2011
Hearing request receivedCONTEST_DT
Jan 4, 2012
Docket numberDOCKET_NO
CENT 2012-263M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Oct 3, 2012
Petition duePETITION_DUE_DT
Feb 21, 2012
Petition filedPETITION_FILED_DT
Jan 17, 2012

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
2106.00
Penalty after the decisionDECISION_PENALTY_AMT
947.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.4102
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Fatal
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Permanent
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M5000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M5000
MSHA representative officeMSHA_REP_OFFICE_NAME
Dallas District

Mine

Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry

Other fields

ISSUING_FIELD_OFFICE
M5871

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (2)

Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

Contested: Jan 28, 2011
Citation issued: Dec 8, 2010
Docket: CENT 2011-391M
Standard: 56.9315
Proposed penalty: $138.00
Penalty after decision: $100.00
Decided: Jun 6, 2011
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
8616801
Citation issuedCITATION_ISSUE_DT
Dec 8, 2010
Hearing request receivedCONTEST_DT
Jan 28, 2011
Docket numberDOCKET_NO
CENT 2011-391M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Jun 6, 2011
Petition duePETITION_DUE_DT
Mar 14, 2011
Petition filedPETITION_FILED_DT
Feb 23, 2011

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
138.00
Penalty after the decisionDECISION_PENALTY_AMT
100.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.9315
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
LostDays
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
LostDays
Negligence when contestedORIGINAL_NEGLIGENCE
HighNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M5000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M5000
MSHA representative officeMSHA_REP_OFFICE_NAME
Dallas District

Mine

Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry

Other fields

ISSUING_FIELD_OFFICE
M5871

Recorded as N (2)

S&S when contestedORIGINAL_SIG_SUB_IND, S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (2)

Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

2 contested citations and orders; decision types are MSHA's own text.

Reported injuries, illnesses and accidents

Reports by degree of injury, as MSHA records it. FATALITY rows are left out of this breakdown: MSHA leaves deaths it finds unrelated to mining out of its fatality statistics, so a count of these reports can differ from MSHA's figures. See MSHA's fatality report search.

DAYS RESTRICTED ACTIVITY ONLY
4
NO DYS AWY FRM WRK,NO RSTR ACT
1
NO VALUE FOUND
1
DAYS AWAY FROM WORK ONLY
1
Date: Jul 21, 2025
Degree of injury: DAYS RESTRICTED ACTIVITY ONLY
Classification: HANDTOOLS (NONPOWERED)
Accident type: Over-exertion NEC
Days lost: 0
Details

The report

Document numberDOCUMENT_NO
220252090010
DateACCIDENT_DT
Jul 21, 2025
TimeACCIDENT_TIME
1030
Shift beganSHIFT_BEGIN_TIME
0730
Degree of injuryDEGREE_INJURY
DAYS RESTRICTED ACTIVITY ONLY
Degree of injury codeDEGREE_INJURY_CD
05
ClassificationCLASSIFICATION
HANDTOOLS (NONPOWERED)
Classification codeCLASSIFICATION_CD
10
Accident typeACCIDENT_TYPE
Over-exertion NEC
Accident type codeACCIDENT_TYPE_CD
30
Reportable injuries or illnessesNO_INJURIES
1
Immediately reportable typeIMMED_NOTIFY
NO VALUE FOUND
Immediately reportable codeIMMED_NOTIFY_CD
?
Returned to Duty document numberCLOSED_DOC_NO
320252730004

Injury

Activity at the timeACTIVITY
Hand tools (not powered)
Activity codeACTIVITY_CD
030
Source of injuryINJURY_SOURCE
AXE,HAMMER,SLEDGE
Source of injury codeINJURY_SOURCE_CD
046
Nature of injuryNATURE_INJURY
UNCLASSIFIED,NOT DETERMED
Nature of injury codeNATURE_INJURY_CD
400
Part of bodyINJ_BODY_PART
UPPER EXTREMITIES, MULTIPLE
Part of body codeINJ_BODY_PART_CD
350
Days of restricted workDAYS_RESTRICT
60
Returned to workRETURN_TO_WORK_DT
Sep 29, 2025

Where, and equipment

Location in the mineSUBUNIT
STRIP, QUARY, OPEN PIT
Location codeSUBUNIT_CD
03
Underground locationUG_LOCATION
NO VALUE FOUND
Underground location codeUG_LOCATION_CD
?
Underground mining methodUG_MINING_METHOD
NO VALUE FOUND
Underground mining method codeUG_MINING_METHOD_CD
?
Equipment involvedMINING_EQUIP
Hand tools (not powered)
Equipment codeMINING_EQUIP_CD
28
Equipment manufacturerEQUIP_MFR_NAME
Not Reported
Equipment manufacturer codeEQUIP_MFR_CD
121
FIPS state codeFIPS_STATE_CD
05

Who and period

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Contractor IDCONTRACTOR_ID
FLC
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (2)

Schedule charge, daysSCHEDULE_CHARGE, Days lostDAYS_LOST

Recorded as N (1)

Permanently transferred or terminatedTRANS_TERM

Not recorded by MSHA (2)

MSHA investigation beganINVEST_BEGIN_DT, Equipment model numberEQUIP_MODEL_NO

Date: Apr 14, 2009
Degree of injury: NO DYS AWY FRM WRK,NO RSTR ACT
Classification: HANDLING OF MATERIALS
Accident type: Struck by... NEC
Days lost: 0
Details

The report

Document numberDOCUMENT_NO
220091060003
DateACCIDENT_DT
Apr 14, 2009
TimeACCIDENT_TIME
0900
Shift beganSHIFT_BEGIN_TIME
0600
Degree of injuryDEGREE_INJURY
NO DYS AWY FRM WRK,NO RSTR ACT
Degree of injury codeDEGREE_INJURY_CD
06
ClassificationCLASSIFICATION
HANDLING OF MATERIALS
Classification codeCLASSIFICATION_CD
09
Accident typeACCIDENT_TYPE
Struck by... NEC
Accident type codeACCIDENT_TYPE_CD
08
Reportable injuries or illnessesNO_INJURIES
1
Immediately reportable typeIMMED_NOTIFY
NO VALUE FOUND
Immediately reportable codeIMMED_NOTIFY_CD
?

Injury

Activity at the timeACTIVITY
Machine maintenance
Activity codeACTIVITY_CD
039
Source of injuryINJURY_SOURCE
METAL,NEC(PIPE,WIRE,NAIL)
Source of injury codeINJURY_SOURCE_CD
088
Nature of injuryNATURE_INJURY
CUT,LACER,PUNCT-OPN WOUND
Nature of injury codeNATURE_INJURY_CD
180
Part of bodyINJ_BODY_PART
WRIST
Part of body codeINJ_BODY_PART_CD
320
Returned to workRETURN_TO_WORK_DT
Apr 14, 2009

Where, and equipment

Location in the mineSUBUNIT
MILL OPERATION/PREPARATION PLANT
Location codeSUBUNIT_CD
30
Underground locationUG_LOCATION
NO VALUE FOUND
Underground location codeUG_LOCATION_CD
?
Underground mining methodUG_MINING_METHOD
NO VALUE FOUND
Underground mining method codeUG_MINING_METHOD_CD
?
Equipment involvedMINING_EQUIP
NO VALUE FOUND
Equipment codeMINING_EQUIP_CD
?
Equipment manufacturerEQUIP_MFR_NAME
NO VALUE FOUND
Equipment manufacturer codeEQUIP_MFR_CD
?
FIPS state codeFIPS_STATE_CD
05

Who and period

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2009
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2009
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (3)

Schedule charge, daysSCHEDULE_CHARGE, Days of restricted workDAYS_RESTRICT, Days lostDAYS_LOST

Recorded as N (1)

Permanently transferred or terminatedTRANS_TERM

Not recorded by MSHA (4)

MSHA investigation beganINVEST_BEGIN_DT, Returned to Duty document numberCLOSED_DOC_NO, Equipment model numberEQUIP_MODEL_NO, Contractor IDCONTRACTOR_ID

Date: Apr 9, 2009
Degree of injury: DAYS AWAY FROM WORK ONLY
Classification: HANDLING OF MATERIALS
Accident type: Over-exertion in lifting objects
Days lost: 1
Details

The report

Document numberDOCUMENT_NO
220091060013
DateACCIDENT_DT
Apr 9, 2009
TimeACCIDENT_TIME
1100
Shift beganSHIFT_BEGIN_TIME
0730
Degree of injuryDEGREE_INJURY
DAYS AWAY FROM WORK ONLY
Degree of injury codeDEGREE_INJURY_CD
03
ClassificationCLASSIFICATION
HANDLING OF MATERIALS
Classification codeCLASSIFICATION_CD
09
Accident typeACCIDENT_TYPE
Over-exertion in lifting objects
Accident type codeACCIDENT_TYPE_CD
27
Reportable injuries or illnessesNO_INJURIES
1
Immediately reportable typeIMMED_NOTIFY
NO VALUE FOUND
Immediately reportable codeIMMED_NOTIFY_CD
?

Injury

Activity at the timeACTIVITY
Handling supplies or material
Activity codeACTIVITY_CD
028
Source of injuryINJURY_SOURCE
ELECTRICAL APPARATUS,NEC
Source of injury codeINJURY_SOURCE_CD
043
Nature of injuryNATURE_INJURY
OTHER INJURY,NEC
Nature of injury codeNATURE_INJURY_CD
390
Part of bodyINJ_BODY_PART
UPPER ARM/HUMERUS
Part of body codeINJ_BODY_PART_CD
311
Days lostDAYS_LOST
1
Returned to workRETURN_TO_WORK_DT
Apr 15, 2009

Where, and equipment

Location in the mineSUBUNIT
STRIP, QUARY, OPEN PIT
Location codeSUBUNIT_CD
03
Underground locationUG_LOCATION
NO VALUE FOUND
Underground location codeUG_LOCATION_CD
?
Underground mining methodUG_MINING_METHOD
NO VALUE FOUND
Underground mining method codeUG_MINING_METHOD_CD
?
Equipment involvedMINING_EQUIP
NO VALUE FOUND
Equipment codeMINING_EQUIP_CD
?
Equipment manufacturerEQUIP_MFR_NAME
NO VALUE FOUND
Equipment manufacturer codeEQUIP_MFR_CD
?
FIPS state codeFIPS_STATE_CD
05

Who and period

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Contractor IDCONTRACTOR_ID
1UB
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2009
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2009
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Schedule charge, daysSCHEDULE_CHARGE, Days of restricted workDAYS_RESTRICT

Recorded as N (1)

Permanently transferred or terminatedTRANS_TERM

Not recorded by MSHA (3)

MSHA investigation beganINVEST_BEGIN_DT, Returned to Duty document numberCLOSED_DOC_NO, Equipment model numberEQUIP_MODEL_NO

Date: Apr 10, 2003
Degree of injury: NO VALUE FOUND
Classification: NO VALUE FOUND
Accident type: Contact with electrical current
Days lost: 0
Details

The report

Document numberDOCUMENT_NO
220031040014
DateACCIDENT_DT
Apr 10, 2003
TimeACCIDENT_TIME
0955
Degree of injuryDEGREE_INJURY
NO VALUE FOUND
Degree of injury codeDEGREE_INJURY_CD
?
ClassificationCLASSIFICATION
NO VALUE FOUND
Classification codeCLASSIFICATION_CD
?
Accident typeACCIDENT_TYPE
Contact with electrical current
Accident type codeACCIDENT_TYPE_CD
31
Reportable injuries or illnessesNO_INJURIES
1
Immediately reportable typeIMMED_NOTIFY
NO VALUE FOUND
Immediately reportable codeIMMED_NOTIFY_CD
?

Injury

Activity at the timeACTIVITY
NO VALUE FOUND
Activity codeACTIVITY_CD
?
Source of injuryINJURY_SOURCE
NO VALUE FOUND
Source of injury codeINJURY_SOURCE_CD
?
Nature of injuryNATURE_INJURY
ELECTRIC BURN-CNTACT BURN
Nature of injury codeNATURE_INJURY_CD
360
Part of bodyINJ_BODY_PART
LEG, NEC
Part of body codeINJ_BODY_PART_CD
510

Where, and equipment

Location in the mineSUBUNIT
STRIP, QUARY, OPEN PIT
Location codeSUBUNIT_CD
03
Underground locationUG_LOCATION
NO VALUE FOUND
Underground location codeUG_LOCATION_CD
?
Underground mining methodUG_MINING_METHOD
NO VALUE FOUND
Underground mining method codeUG_MINING_METHOD_CD
?
Equipment involvedMINING_EQUIP
NO VALUE FOUND
Equipment codeMINING_EQUIP_CD
?
Equipment manufacturerEQUIP_MFR_NAME
NO VALUE FOUND
Equipment manufacturer codeEQUIP_MFR_CD
?
FIPS state codeFIPS_STATE_CD
05

Who and period

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
Ashland Inc
Controller IDCONTROLLER_ID
M00049
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2003
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2003
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (3)

Schedule charge, daysSCHEDULE_CHARGE, Days of restricted workDAYS_RESTRICT, Days lostDAYS_LOST

Not recorded by MSHA (7)

Shift beganSHIFT_BEGIN_TIME, MSHA investigation beganINVEST_BEGIN_DT, Returned to Duty document numberCLOSED_DOC_NO, Permanently transferred or terminatedTRANS_TERM, Returned to workRETURN_TO_WORK_DT, Equipment model numberEQUIP_MODEL_NO, Contractor IDCONTRACTOR_ID

Date: Jul 29, 2002
Degree of injury: DAYS RESTRICTED ACTIVITY ONLY
Classification: SLIP OR FALL OF PERSON
Accident type: Fall to the walkway or working surface
Days lost: Not recorded
Details

The report

Document numberDOCUMENT_NO
220022170062
DateACCIDENT_DT
Jul 29, 2002
TimeACCIDENT_TIME
1300
Shift beganSHIFT_BEGIN_TIME
700
Degree of injuryDEGREE_INJURY
DAYS RESTRICTED ACTIVITY ONLY
Degree of injury codeDEGREE_INJURY_CD
05
ClassificationCLASSIFICATION
SLIP OR FALL OF PERSON
Classification codeCLASSIFICATION_CD
18
Accident typeACCIDENT_TYPE
Fall to the walkway or working surface
Accident type codeACCIDENT_TYPE_CD
17
Reportable injuries or illnessesNO_INJURIES
1
Immediately reportable typeIMMED_NOTIFY
NOT MARKED
Immediately reportable codeIMMED_NOTIFY_CD
13

Injury

Activity at the timeACTIVITY
Handling supplies or material
Activity codeACTIVITY_CD
028
Source of injuryINJURY_SOURCE
GROUND
Source of injury codeINJURY_SOURCE_CD
117
Nature of injuryNATURE_INJURY
CONTUSN,BRUISE,INTAC SKIN
Nature of injury codeNATURE_INJURY_CD
160
Part of bodyINJ_BODY_PART
KNEE/PATELLA
Part of body codeINJ_BODY_PART_CD
512
Days of restricted workDAYS_RESTRICT
4
Returned to workRETURN_TO_WORK_DT
Aug 2, 2002

Where, and equipment

Location in the mineSUBUNIT
MILL OPERATION/PREPARATION PLANT
Location codeSUBUNIT_CD
30
Underground locationUG_LOCATION
NO VALUE FOUND
Underground location codeUG_LOCATION_CD
?
Underground mining methodUG_MINING_METHOD
NO VALUE FOUND
Underground mining method codeUG_MINING_METHOD_CD
?
Equipment involvedMINING_EQUIP
NO VALUE FOUND
Equipment codeMINING_EQUIP_CD
?
Equipment manufacturerEQUIP_MFR_NAME
NO VALUE FOUND
Equipment manufacturer codeEQUIP_MFR_CD
?
Equipment model numberEQUIP_MODEL_NO
?
FIPS state codeFIPS_STATE_CD
05

Who and period

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
Ashland Inc
Controller IDCONTROLLER_ID
M00049
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2002
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2002
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (1)

Permanently transferred or terminatedTRANS_TERM

Not recorded by MSHA (5)

MSHA investigation beganINVEST_BEGIN_DT, Returned to Duty document numberCLOSED_DOC_NO, Schedule charge, daysSCHEDULE_CHARGE, Days lostDAYS_LOST, Contractor IDCONTRACTOR_ID

Date: Nov 29, 2001
Degree of injury: DAYS RESTRICTED ACTIVITY ONLY
Classification: SLIP OR FALL OF PERSON
Accident type: Fall from ladders
Days lost: Not recorded
Details

The report

Document numberDOCUMENT_NO
220013410026
DateACCIDENT_DT
Nov 29, 2001
TimeACCIDENT_TIME
0700
Shift beganSHIFT_BEGIN_TIME
600
Degree of injuryDEGREE_INJURY
DAYS RESTRICTED ACTIVITY ONLY
Degree of injury codeDEGREE_INJURY_CD
05
ClassificationCLASSIFICATION
SLIP OR FALL OF PERSON
Classification codeCLASSIFICATION_CD
18
Accident typeACCIDENT_TYPE
Fall from ladders
Accident type codeACCIDENT_TYPE_CD
14
Reportable injuries or illnessesNO_INJURIES
1
Immediately reportable typeIMMED_NOTIFY
NOT MARKED
Immediately reportable codeIMMED_NOTIFY_CD
13

Injury

Activity at the timeACTIVITY
Climb scaffolds, Ladders
Activity codeACTIVITY_CD
013
Source of injuryINJURY_SOURCE
FLOOR,WALKING SURF-NOT UG
Source of injury codeINJURY_SOURCE_CD
010
Nature of injuryNATURE_INJURY
SPRAIN,STRAIN RUPT DISC
Nature of injury codeNATURE_INJURY_CD
330
Part of bodyINJ_BODY_PART
ANKLE
Part of body codeINJ_BODY_PART_CD
520
Days of restricted workDAYS_RESTRICT
5
Returned to workRETURN_TO_WORK_DT
Dec 6, 2001

Where, and equipment

Location in the mineSUBUNIT
MILL OPERATION/PREPARATION PLANT
Location codeSUBUNIT_CD
30
Underground locationUG_LOCATION
NO VALUE FOUND
Underground location codeUG_LOCATION_CD
?
Underground mining methodUG_MINING_METHOD
NO VALUE FOUND
Underground mining method codeUG_MINING_METHOD_CD
?
Equipment involvedMINING_EQUIP
NO VALUE FOUND
Equipment codeMINING_EQUIP_CD
?
Equipment manufacturerEQUIP_MFR_NAME
NO VALUE FOUND
Equipment manufacturer codeEQUIP_MFR_CD
?
Equipment model numberEQUIP_MODEL_NO
?
FIPS state codeFIPS_STATE_CD
05

Who and period

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
Ashland Inc
Controller IDCONTROLLER_ID
M00049
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2001
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2002
MSHA fiscal quarterFISCAL_QTR
1

Recorded as N (1)

Permanently transferred or terminatedTRANS_TERM

Not recorded by MSHA (5)

MSHA investigation beganINVEST_BEGIN_DT, Returned to Duty document numberCLOSED_DOC_NO, Schedule charge, daysSCHEDULE_CHARGE, Days lostDAYS_LOST, Contractor IDCONTRACTOR_ID

Date: Jul 11, 2000
Degree of injury: DAYS RESTRICTED ACTIVITY ONLY
Classification: HANDLING OF MATERIALS
Accident type: Over-exertion in lifting objects
Days lost: Not recorded
Details

The report

Document numberDOCUMENT_NO
220002010049
DateACCIDENT_DT
Jul 11, 2000
TimeACCIDENT_TIME
0945
Shift beganSHIFT_BEGIN_TIME
700
Degree of injuryDEGREE_INJURY
DAYS RESTRICTED ACTIVITY ONLY
Degree of injury codeDEGREE_INJURY_CD
05
ClassificationCLASSIFICATION
HANDLING OF MATERIALS
Classification codeCLASSIFICATION_CD
09
Accident typeACCIDENT_TYPE
Over-exertion in lifting objects
Accident type codeACCIDENT_TYPE_CD
27
Reportable injuries or illnessesNO_INJURIES
1
Immediately reportable typeIMMED_NOTIFY
NOT MARKED
Immediately reportable codeIMMED_NOTIFY_CD
13
Returned to Duty document numberCLOSED_DOC_NO
320002020012

Injury

Activity at the timeACTIVITY
Handling supplies or material
Activity codeACTIVITY_CD
028
Source of injuryINJURY_SOURCE
BRATTICE CURT,PLAS & CANV
Source of injury codeINJURY_SOURCE_CD
009
Nature of injuryNATURE_INJURY
SPRAIN,STRAIN RUPT DISC
Nature of injury codeNATURE_INJURY_CD
330
Part of bodyINJ_BODY_PART
BACK (MUSCLES/SPINE/S-CORD/TAILBONE)
Part of body codeINJ_BODY_PART_CD
420
Days of restricted workDAYS_RESTRICT
6
Returned to workRETURN_TO_WORK_DT
Jul 19, 2000

Where, and equipment

Location in the mineSUBUNIT
STRIP, QUARY, OPEN PIT
Location codeSUBUNIT_CD
03
Underground locationUG_LOCATION
NO VALUE FOUND
Underground location codeUG_LOCATION_CD
?
Underground mining methodUG_MINING_METHOD
NO VALUE FOUND
Underground mining method codeUG_MINING_METHOD_CD
?
Equipment involvedMINING_EQUIP
NO VALUE FOUND
Equipment codeMINING_EQUIP_CD
?
Equipment manufacturerEQUIP_MFR_NAME
NO VALUE FOUND
Equipment manufacturer codeEQUIP_MFR_CD
?
Equipment model numberEQUIP_MODEL_NO
?
FIPS state codeFIPS_STATE_CD
05

Who and period

Operator at the timeOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Controller at the timeCONTROLLER_NAME
Ashland Inc
Controller IDCONTROLLER_ID
M00049
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2000
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2000
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (1)

Permanently transferred or terminatedTRANS_TERM

Not recorded by MSHA (4)

MSHA investigation beganINVEST_BEGIN_DT, Schedule charge, daysSCHEDULE_CHARGE, Days lostDAYS_LOST, Contractor IDCONTRACTOR_ID

7 reports filed on MSHA Form 7000-1; categories are MSHA's own text.

Employment and hours worked

Year: 2026
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 3
Hours worked: 4,225
Details

The report

YearCALENDAR_YR
2026
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
4225
Average hours per employeeAVG_EMPLOYEE_HOURS
1408

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2026
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 6
Hours worked: 8,738
Details

The report

YearCALENDAR_YR
2026
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
6
Hours workedANNUAL_HRS
8738
Average hours per employeeAVG_EMPLOYEE_HOURS
1456

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2025
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 3
Hours worked: 5,635
Details

The report

YearCALENDAR_YR
2025
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
5635
Average hours per employeeAVG_EMPLOYEE_HOURS
1878

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2025
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 6
Hours worked: 11,783
Details

The report

YearCALENDAR_YR
2025
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
6
Hours workedANNUAL_HRS
11783
Average hours per employeeAVG_EMPLOYEE_HOURS
1964

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2024
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 3
Hours worked: 5,220
Details

The report

YearCALENDAR_YR
2024
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
5220
Average hours per employeeAVG_EMPLOYEE_HOURS
1740

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2024
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 9
Hours worked: 19,716
Details

The report

YearCALENDAR_YR
2024
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
9
Hours workedANNUAL_HRS
19716
Average hours per employeeAVG_EMPLOYEE_HOURS
2191

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2023
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 3
Hours worked: 5,178
Details

The report

YearCALENDAR_YR
2023
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
5178
Average hours per employeeAVG_EMPLOYEE_HOURS
1726

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2023
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 9
Hours worked: 19,079
Details

The report

YearCALENDAR_YR
2023
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
9
Hours workedANNUAL_HRS
19079
Average hours per employeeAVG_EMPLOYEE_HOURS
2120

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2022
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 3
Hours worked: 5,275
Details

The report

YearCALENDAR_YR
2022
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
5275
Average hours per employeeAVG_EMPLOYEE_HOURS
1758

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2022
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 8
Hours worked: 15,265
Details

The report

YearCALENDAR_YR
2022
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
8
Hours workedANNUAL_HRS
15265
Average hours per employeeAVG_EMPLOYEE_HOURS
1908

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2021
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 3
Hours worked: 4,766
Details

The report

YearCALENDAR_YR
2021
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
4766
Average hours per employeeAVG_EMPLOYEE_HOURS
1589

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2021
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 7
Hours worked: 14,274
Details

The report

YearCALENDAR_YR
2021
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
7
Hours workedANNUAL_HRS
14274
Average hours per employeeAVG_EMPLOYEE_HOURS
2039

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2020
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 3
Hours worked: 4,594
Details

The report

YearCALENDAR_YR
2020
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
4594
Average hours per employeeAVG_EMPLOYEE_HOURS
1531

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2020
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 7
Hours worked: 12,905
Details

The report

YearCALENDAR_YR
2020
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
7
Hours workedANNUAL_HRS
12905
Average hours per employeeAVG_EMPLOYEE_HOURS
1844

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2019
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 3
Hours worked: 4,186
Details

The report

YearCALENDAR_YR
2019
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
4186
Average hours per employeeAVG_EMPLOYEE_HOURS
1395

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2019
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 8
Hours worked: 12,610
Details

The report

YearCALENDAR_YR
2019
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
8
Hours workedANNUAL_HRS
12610
Average hours per employeeAVG_EMPLOYEE_HOURS
1576

Mine

Mine IDMINE_ID
0300429
Mine name in this fileCURR_MINE_NM
Jenny Lind Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

What the operator reported to MSHA for the 8 most recent years, one row per part of the mine, as MSHA files them. Rows are not added together.

Mine details

MSHA field office
Little Rock AR Field Office
Nearest town
Ft Smith
Days worked per week
5
Hours per shift
8
Production shifts per day
1
Maintenance shifts per day
0
Employees, current record
3
Tailing ponds
0
103(i) spot inspection status
Never Had 103I Status
Safety committee
N
Portable operation
N
Every field in MSHA's mine record

The mine

Mine nameCURRENT_MINE_NAME
Jenny Lind Quarry
Mine IDMINE_ID
0300429
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Mine typeCURRENT_MINE_TYPE
Surface
Current statusCURRENT_MINE_STATUS
Active
Status sinceCURRENT_STATUS_DT
Oct 3, 2025
Legal entity typeCOMPANY_TYPE
Corporation

Operator and controller

OperatorCURRENT_OPERATOR_NAME
ARKHOLA
Operator IDCURRENT_OPERATOR_ID
L11502
ControllerCURRENT_CONTROLLER_NAME
CRH PLC
Controller IDCURRENT_CONTROLLER_ID
M06183
Start of the operating periodCURRENT_CONTROLLER_BEGIN_DT
Jan 1, 1950

Location and MSHA office

StateSTATE
AR
Bureau of Mines state codeBOM_STATE_CD
03
FIPS county codeFIPS_CNTY_CD
131
FIPS county nameFIPS_CNTY_NM
Sebastian
Congressional districtCONG_DIST_CD
03
Nearest townNEAREST_TOWN
Ft Smith
MSHA districtDISTRICT
M5
MSHA office codeOFFICE_CD
M5871
MSHA officeOFFICE_NAME
Little Rock AR Field Office
Driving miles from the MSHA officeMILES_FROM_OFFICE
145
Most recent assessment control numberASSESS_CTRL_NO
000643291

Commodity

Primary commodity (SIC)PRIMARY_SIC
Crushed, Broken Sandstone
Primary commodity codePRIMARY_SIC_CD
142902
Primary SIC codePRIMARY_SIC_CD_1
1429
Primary SIC suffixPRIMARY_SIC_CD_SFX
02
Primary industry groupPRIMARY_CANVASS
Stone
Primary industry group codePRIMARY_CANVASS_CD
6

Operations, from the Mine Information Form

Days operating per weekDAYS_PER_WEEK
5
Hours per shiftHOURS_PER_SHIFT
8
Production shifts per dayPROD_SHIFTS_PER_DAY
1
Workers employedNO_EMPLOYEES
3
MSHA restricted from enforcing Part 48 trainingPART48_TRAINING
Y
103(i) statusCURRENT_103I
Never Had 103I Status

Recorded as 0 (2)

Maintenance-only shifts per dayMAINT_SHIFTS_PER_DAY, Tailing pondsNO_TAILING_PONDS

Recorded as N (5)

Portable minePORTABLE_OPERATION, Pillar recovery usedPILLAR_RECOVERY_USED, Highwall miner usedHIGHWALL_MINER_USED, Multiple pitsMULTIPLE_PITS, Safety committeeSAFETY_COMMITTEE_IND

Not recorded by MSHA (13)

Portable mine FIPS state codePORTABLE_FIPS_ST_CD, Secondary commodity (SIC)SECONDARY_SIC, Secondary commodity codeSECONDARY_SIC_CD, Secondary SIC codeSECONDARY_SIC_CD_1, Secondary SIC suffixSECONDARY_SIC_CD_SFX, Secondary industry groupSECONDARY_CANVASS, Secondary industry group codeSECONDARY_CANVASS_CD, Average mining height, inchesAVG_MINE_HEIGHT, Mine gas categoryMINE_GAS_CATEGORY_CD, Methane liberation, cu ft per 24 hMETHANE_LIBERATION, Producing pitsNO_PRODUCING_PITS, Non-producing pitsNO_NONPRODUCING_PITS, 103(i) status sinceCURRENT_103I_DT

Operator and controller history

Operator: ARKHOLA
From: Jan 1, 1950
To: No end date
Controller: CRH PLC
From : Aug 28, 2006
To : No end date
Details

Operator

OperatorOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Operator fromOPERATOR_START_DT
Jan 1, 1950

Controller

ControllerCONTROLLER_NAME
CRH PLC
Controller IDCONTROLLER_ID
M06183
Company or personCONTROLLER_TYPE
COMPANY
Controller fromCONTROLLER_START_DT
Aug 28, 2006

Mine

Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine status at this pointMINE_STATUS
Active
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (2)

Operator toOPERATOR_END_DT, Controller toCONTROLLER_END_DT

Operator: ARKHOLA
From: Jan 1, 1950
To: No end date
Controller: Ashland Inc
From : Jan 1, 1950
To : Aug 27, 2006
Details

Operator

OperatorOPERATOR_NAME
ARKHOLA
Operator IDOPERATOR_ID
L11502
Operator fromOPERATOR_START_DT
Jan 1, 1950

Controller

ControllerCONTROLLER_NAME
Ashland Inc
Controller IDCONTROLLER_ID
M00049
Company or personCONTROLLER_TYPE
COMPANY
Controller fromCONTROLLER_START_DT
Jan 1, 1950
Controller toCONTROLLER_END_DT
Aug 27, 2006

Mine

Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Mine status at this pointMINE_STATUS
Active
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (1)

Operator toOPERATOR_END_DT

As MSHA records it, newest operator first.

Address of record

ARKHOLA·Contact title Safety Director·1010 Frontier Road, Barling AR 72923

MSHA says an address of record "does not represent the actual mine location."

Every field in the address record

Address

Business nameBUSINESS_NAME
ARKHOLA
Contact titleCONTACT_TITLE
Safety Director
StreetSTREET
1010 Frontier Road
CityCITY
Barling
StateSTATE_ABBR
AR
State nameSTATE
Arkansas
ZIP codeZIP_CD
72923
CountryCOUNTRY
USA
FIPS state codeFIPS_STATE_CD
05

Mine

Mine IDMINE_ID
0300429
Mine name in this fileMINE_NAME
Jenny Lind Quarry
Nearest townNEAREST_TOWN
Ft Smith
Mine typeMINE_TYPE_CD
Surface
Mine statusMINE_STATUS
Active
Status sinceMINE_STATUS_DT
Oct 3, 2025
Primary commodity (SIC)PRIMARY_SIC_CD
Crushed, Broken Sandstone
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (3)

PO boxPO_BOX, ProvincePROVINCE, Foreign postal codePOSTAL_CD

Sources. MSHA open government data files: Mines, Inspections, Violations, AssessedViolations, ContestedViolations, 107(a)OrdersIssued, Accidents, MinesProdYearly, ControllerOperatorHistory, AddressOfRecord. Field labels are shortened from MSHA's definition files, with MSHA's column name beside each. MSHA Mine Data Retrieval System·MSHA fatality report search·MSHA open government data

These are U.S. Department of Labor, Mine Safety and Health Administration records, reproduced as published. Citations can be contested, modified or vacated, and records that are contested or not yet final are included. SafetyRecord.org is not a consumer reporting agency. MSHA records as of Nov 6, 2026. Data and methodology