C & M Stone Company Cecil Quarry

Metal/Non-Metal, SurfaceDimension LimestoneFranklin, ArkansasMine ID 0302011

Operator C & M Stone CompanyController not shownMSHA status Intermittent since Oct 15, 2026

What MSHA has on file for this mine

Citations and orders
63
since May 17, 2011 · 61 to the operator, 2 to contractors · 25 marked S&S
Contested citations
None on record
Imminent danger orders, section 107(a)
None on record
MSHA's list starts July 1, 2010
Accident, injury or illness reports
None on record
MSHA's file starts January 2000
Yearly employment and hours
8 years
one row per part of the mine

MSHA records as of Nov 20, 2026. Having MSHA inspection records is common for operating mines. Data and methodology

Inspections

Mine Idle Activity
Aug 28 to Aug 29, 2023Inspectors 1 | Hours on site 8

The inspection

BeganINSPECTION_BEGIN_DT
Aug 28, 2023
Closed outINSPECTION_END_DT
Aug 29, 2023
ActivityACTIVITY
Mine Idle Activity
Activity codeACTIVITY_CODE
E28
Program areaPROGRAM_AREA
M/NM--Mine Idle Activity
Event numberEVENT_NO
6935042
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
8
Total inspection hoursSUM_TOTAL_INSP_HOURS
12.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jan 30 to Jan 31, 2023Inspectors 1 | Hours on site 4

The inspection

BeganINSPECTION_BEGIN_DT
Jan 30, 2023
Closed outINSPECTION_END_DT
Jan 31, 2023
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6889899
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4
Total inspection hoursSUM_TOTAL_INSP_HOURS
9

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Compliance Follow-up Inspection
Sep 9 to Sep 19, 2022Inspectors 1 | Hours on site 1.5

The inspection

BeganINSPECTION_BEGIN_DT
Sep 9, 2022
Closed outINSPECTION_END_DT
Sep 19, 2022
ActivityACTIVITY
Compliance Follow-up Inspection
Activity codeACTIVITY_CODE
E15
Program areaPROGRAM_AREA
M/NM--Compliance Follow-up Inspection
Event numberEVENT_NO
6889870
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
1.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
7.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Aug 31 to Sep 2, 2022Inspectors 1 | Hours on site 4.5

The inspection

BeganINSPECTION_BEGIN_DT
Aug 31, 2022
Closed outINSPECTION_END_DT
Sep 2, 2022
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6889867
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
12.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Mar 22 to Mar 24, 2022Inspectors 1 | Hours on site 12

The inspection

BeganINSPECTION_BEGIN_DT
Mar 22, 2022
Closed outINSPECTION_END_DT
Mar 24, 2022
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6888836
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
12
Total inspection hoursSUM_TOTAL_INSP_HOURS
16

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
May 10 to May 11, 2021Inspectors 1 | Hours on site 11

The inspection

BeganINSPECTION_BEGIN_DT
May 10, 2021
Closed outINSPECTION_END_DT
May 11, 2021
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6886448
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
11
Total inspection hoursSUM_TOTAL_INSP_HOURS
14.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2021
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Dec 8 to Dec 10, 2020Inspectors 1 | Hours on site 9

The inspection

BeganINSPECTION_BEGIN_DT
Dec 8, 2020
Closed outINSPECTION_END_DT
Dec 10, 2020
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6886411
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
9
Total inspection hoursSUM_TOTAL_INSP_HOURS
15

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Spot Inspection
Sep 3 to Sep 4, 2020Inspectors 1 | Hours on site 7

The inspection

BeganINSPECTION_BEGIN_DT
Sep 3, 2020
Closed outINSPECTION_END_DT
Sep 4, 2020
ActivityACTIVITY
Spot Inspection
Activity codeACTIVITY_CODE
E16
Program areaPROGRAM_AREA
M/NM--Spot Inspection
Event numberEVENT_NO
6884324
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
7
Total inspection hoursSUM_TOTAL_INSP_HOURS
14

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jul 30 to Jul 31, 2020Inspectors 1 | Hours on site 8

The inspection

BeganINSPECTION_BEGIN_DT
Jul 30, 2020
Closed outINSPECTION_END_DT
Jul 31, 2020
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6884315
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
8
Total inspection hoursSUM_TOTAL_INSP_HOURS
11

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Spot Inspection
Dec 18, 2019Inspectors 1 | Hours on site 3.5

The inspection

BeganINSPECTION_BEGIN_DT
Dec 18, 2019
Closed outINSPECTION_END_DT
Dec 18, 2019
ActivityACTIVITY
Spot Inspection
Activity codeACTIVITY_CODE
E16
Program areaPROGRAM_AREA
M/NM--Spot Inspection
Event numberEVENT_NO
6810430
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
6.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Nov 12 to Nov 18, 2019Inspectors 1 | Hours on site 7

The inspection

BeganINSPECTION_BEGIN_DT
Nov 12, 2019
Closed outINSPECTION_END_DT
Nov 18, 2019
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6805496
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
7
Total inspection hoursSUM_TOTAL_INSP_HOURS
12.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 19 to Jun 20, 2019Inspectors 1 | Hours on site 12.75

The inspection

BeganINSPECTION_BEGIN_DT
Jun 19, 2019
Closed outINSPECTION_END_DT
Jun 20, 2019
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6810701
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
12.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
16.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2019
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jan 22 to Jan 23, 2019Inspectors 1 | Hours on site 8.75

The inspection

BeganINSPECTION_BEGIN_DT
Jan 22, 2019
Closed outINSPECTION_END_DT
Jan 23, 2019
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6804368
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
8.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
13.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2019
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 13 to Jun 14, 2018Inspectors 1 | Hours on site 9.5

The inspection

BeganINSPECTION_BEGIN_DT
Jun 13, 2018
Closed outINSPECTION_END_DT
Jun 14, 2018
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6739092
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
9.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
14.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Dec 5 to Dec 7, 2017Inspectors 1 | Hours on site 10.5

The inspection

BeganINSPECTION_BEGIN_DT
Dec 5, 2017
Closed outINSPECTION_END_DT
Dec 7, 2017
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6739050
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
10.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
16.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Sep 5 to Sep 7, 2017Inspectors 1 | Hours on site 19

The inspection

BeganINSPECTION_BEGIN_DT
Sep 5, 2017
Closed outINSPECTION_END_DT
Sep 7, 2017
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6737370
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
19
Total inspection hoursSUM_TOTAL_INSP_HOURS
28

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Mar 22, 2017Inspectors 1 | Hours on site 4.75

The inspection

BeganINSPECTION_BEGIN_DT
Mar 22, 2017
Closed outINSPECTION_END_DT
Mar 22, 2017
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6738631
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
14.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Aug 23, 2016Inspectors 1 | Hours on site 9.5

The inspection

BeganINSPECTION_BEGIN_DT
Aug 23, 2016
Closed outINSPECTION_END_DT
Aug 23, 2016
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6735925
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
9.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
12

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Sep 1 to Sep 2, 2015Inspectors 1 | Hours on site 11.25

The inspection

BeganINSPECTION_BEGIN_DT
Sep 1, 2015
Closed outINSPECTION_END_DT
Sep 2, 2015
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6732306
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
11.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
31.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
May 29 to May 30, 2012Inspectors 1 | Hours on site 3.75

The inspection

BeganINSPECTION_BEGIN_DT
May 29, 2012
Closed outINSPECTION_END_DT
May 30, 2012
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6603826
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
10.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2012
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2012
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Nov 2, 2011Inspectors 1 | Hours on site 7.75

The inspection

BeganINSPECTION_BEGIN_DT
Nov 2, 2011
Closed outINSPECTION_END_DT
Nov 2, 2011
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6547990
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
7.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
13.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2011
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2012
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
May 16 to May 24, 2011Inspectors 1 | Hours on site 0.5

The inspection

BeganINSPECTION_BEGIN_DT
May 16, 2011
Closed outINSPECTION_END_DT
May 24, 2011
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6543993
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M5871
Hours on siteSUM_TOTAL_ON_SITE_HOURS
0.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
2

Who and when, as recorded

Operator at the timeOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Mine IDMINE_ID
0302011
Calendar yearCAL_YR
2011
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2011
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

22 inspections and other MSHA visits since May 16, 2011; activity names are MSHA's own text. Full list: MSHA Mine Data Retrieval System.

Citations and orders

Issued: Aug 28, 2023
Type: Citation
Standard: 56.1000
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $143.00
Details

The citation

Citation or order numberVIOLATION_NO
9740958
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Aug 28, 2023
Time issuedVIOLATION_ISSUE_TIME
1401
Date of occurrenceVIOLATION_OCCUR_DT
Aug 28, 2023
30 CFR part and sectionPART_SECTION
56.1000
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Mill

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Aug 28, 2023
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Aug 28, 2023
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Aug 28, 2023
Terminated, timeTERMINATION_TIME
1404
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
143
Current proposed assessmentAMOUNT_DUE
143
Bill first printedBILL_PRINT_DT
Oct 5, 2023
Final order dateFINAL_ORDER_ISSUE_DT
Dec 5, 2023
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Mar 21, 2024
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6935042
Inspection beganINSPECTION_BEGIN_DT
Aug 28, 2023
Inspection closed outINSPECTION_END_DT
Aug 29, 2023
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jan 30, 2023
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $143.00
Details

The citation

Citation or order numberVIOLATION_NO
9740822
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jan 30, 2023
Time issuedVIOLATION_ISSUE_TIME
1319
Date of occurrenceVIOLATION_OCCUR_DT
Jan 30, 2023
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jan 30, 2023
Originally due, timeORIG_TERM_DUE_TIME
1321
Latest dueLATEST_TERM_DUE_DT
Jan 30, 2023
Latest due, timeLATEST_TERM_DUE_TIME
1321
TerminatedTERMINATION_DT
Jan 30, 2023
Terminated, timeTERMINATION_TIME
1320
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
143
Current proposed assessmentAMOUNT_DUE
143
Bill first printedBILL_PRINT_DT
Mar 2, 2023
Final order dateFINAL_ORDER_ISSUE_DT
Apr 9, 2023
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Jul 27, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6889899
Inspection beganINSPECTION_BEGIN_DT
Jan 30, 2023
Inspection closed outINSPECTION_END_DT
Jan 31, 2023
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
2

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jan 30, 2023
Type: Citation
Standard: 56.14105
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $143.00
Details

The citation

Citation or order numberVIOLATION_NO
9740821
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jan 30, 2023
Time issuedVIOLATION_ISSUE_TIME
1133
Date of occurrenceVIOLATION_OCCUR_DT
Jan 30, 2023
30 CFR part and sectionPART_SECTION
56.14105
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jan 30, 2023
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Jan 30, 2023
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Jan 30, 2023
Terminated, timeTERMINATION_TIME
1135
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
143
Current proposed assessmentAMOUNT_DUE
143
Bill first printedBILL_PRINT_DT
Mar 2, 2023
Final order dateFINAL_ORDER_ISSUE_DT
Apr 9, 2023
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Jul 27, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6889899
Inspection beganINSPECTION_BEGIN_DT
Jan 30, 2023
Inspection closed outINSPECTION_END_DT
Jan 31, 2023
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
2

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Aug 31, 2022
Type: Citation
Standard: 56.4201(a)(2)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9674506
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Aug 31, 2022
Time issuedVIOLATION_ISSUE_TIME
1310
Date of occurrenceVIOLATION_OCCUR_DT
Aug 31, 2022
30 CFR part and sectionPART_SECTION
56.4201(a)(2)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Sep 2, 2022
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Sep 2, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Sep 9, 2022
Terminated, timeTERMINATION_TIME
0822
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Bill first printedBILL_PRINT_DT
Nov 3, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Dec 16, 2022
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Apr 13, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6889867
Inspection beganINSPECTION_BEGIN_DT
Aug 31, 2022
Inspection closed outINSPECTION_END_DT
Sep 2, 2022
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Aug 31, 2022
Type: Citation
Standard: 56.4402
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9674504
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Aug 31, 2022
Time issuedVIOLATION_ISSUE_TIME
1218
Date of occurrenceVIOLATION_OCCUR_DT
Aug 31, 2022
30 CFR part and sectionPART_SECTION
56.4402
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Aug 31, 2022
Originally due, timeORIG_TERM_DUE_TIME
1233
Latest dueLATEST_TERM_DUE_DT
Aug 31, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1233
TerminatedTERMINATION_DT
Aug 31, 2022
Terminated, timeTERMINATION_TIME
1222
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Bill first printedBILL_PRINT_DT
Nov 3, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Dec 16, 2022
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Apr 13, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6889867
Inspection beganINSPECTION_BEGIN_DT
Aug 31, 2022
Inspection closed outINSPECTION_END_DT
Sep 2, 2022
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Aug 31, 2022
Type: Citation
Standard: 56.14206(b)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9674503
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Aug 31, 2022
Time issuedVIOLATION_ISSUE_TIME
1200
Date of occurrenceVIOLATION_OCCUR_DT
Aug 31, 2022
30 CFR part and sectionPART_SECTION
56.14206(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Aug 31, 2022
Originally due, timeORIG_TERM_DUE_TIME
1205
Latest dueLATEST_TERM_DUE_DT
Aug 31, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1205
TerminatedTERMINATION_DT
Aug 31, 2022
Terminated, timeTERMINATION_TIME
1205
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Bill first printedBILL_PRINT_DT
Nov 3, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Dec 16, 2022
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Apr 13, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6889867
Inspection beganINSPECTION_BEGIN_DT
Aug 31, 2022
Inspection closed outINSPECTION_END_DT
Sep 2, 2022
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Aug 31, 2022
Type: Citation
Standard: 56.14130(g)
S&S: Y
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $1,069.00
Details

The citation

Citation or order numberVIOLATION_NO
9674505
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Aug 31, 2022
Time issuedVIOLATION_ISSUE_TIME
1302
Date of occurrenceVIOLATION_OCCUR_DT
Aug 31, 2022
30 CFR part and sectionPART_SECTION
56.14130(g)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Aug 31, 2022
Originally due, timeORIG_TERM_DUE_TIME
1317
Latest dueLATEST_TERM_DUE_DT
Aug 31, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1317
TerminatedTERMINATION_DT
Sep 19, 2022
Terminated, timeTERMINATION_TIME
0904
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
1069
Current proposed assessmentAMOUNT_DUE
1069
Bill first printedBILL_PRINT_DT
Nov 3, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Dec 16, 2022
Last actionLAST_ACTION_CD
Treasury
Last action dateLAST_ACTION_DT
Apr 13, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6889867
Inspection beganINSPECTION_BEGIN_DT
Aug 31, 2022
Inspection closed outINSPECTION_END_DT
Sep 2, 2022
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Amount paidAMOUNT_PAID

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Mar 23, 2022
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9646756
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Mar 23, 2022
Time issuedVIOLATION_ISSUE_TIME
1100
Date of occurrenceVIOLATION_OCCUR_DT
Mar 23, 2022
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Mill

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Mar 25, 2022
Originally due, timeORIG_TERM_DUE_TIME
1000
Latest dueLATEST_TERM_DUE_DT
Mar 25, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1000
TerminatedTERMINATION_DT
Apr 18, 2022
Terminated, timeTERMINATION_TIME
1048
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Amount paidAMOUNT_PAID
133
Bill first printedBILL_PRINT_DT
May 5, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Jun 11, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Apr 12, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
11
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6888836
Inspection beganINSPECTION_BEGIN_DT
Mar 22, 2022
Inspection closed outINSPECTION_END_DT
Mar 24, 2022
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
2

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Mar 23, 2022
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9646757
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Mar 23, 2022
Time issuedVIOLATION_ISSUE_TIME
1101
Date of occurrenceVIOLATION_OCCUR_DT
Mar 23, 2022
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Mill

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Mar 23, 2022
Originally due, timeORIG_TERM_DUE_TIME
1230
Latest dueLATEST_TERM_DUE_DT
Mar 23, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1230
TerminatedTERMINATION_DT
Mar 23, 2022
Terminated, timeTERMINATION_TIME
1102
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Amount paidAMOUNT_PAID
133
Bill first printedBILL_PRINT_DT
May 5, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Jun 11, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
May 11, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
11
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6888836
Inspection beganINSPECTION_BEGIN_DT
Mar 22, 2022
Inspection closed outINSPECTION_END_DT
Mar 24, 2022
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
2

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Mar 23, 2022
Type: Citation
Standard: 56.14100(b)
S&S: Y
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $716.00
Details

The citation

Citation or order numberVIOLATION_NO
9646755
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Mar 23, 2022
Time issuedVIOLATION_ISSUE_TIME
0825
Date of occurrenceVIOLATION_OCCUR_DT
Mar 23, 2022
30 CFR part and sectionPART_SECTION
56.14100(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Mill

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Mar 23, 2022
Originally due, timeORIG_TERM_DUE_TIME
0925
Latest dueLATEST_TERM_DUE_DT
Mar 23, 2022
Latest due, timeLATEST_TERM_DUE_TIME
0925
TerminatedTERMINATION_DT
Mar 23, 2022
Terminated, timeTERMINATION_TIME
0840
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
716
Current proposed assessmentAMOUNT_DUE
716
Amount paidAMOUNT_PAID
716
Bill first printedBILL_PRINT_DT
May 5, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Jun 11, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Mar 9, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
11
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6888836
Inspection beganINSPECTION_BEGIN_DT
Mar 22, 2022
Inspection closed outINSPECTION_END_DT
Mar 24, 2022
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
2

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: May 10, 2021
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $125.00
Details

The citation

Citation or order numberVIOLATION_NO
9642260
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
May 10, 2021
Time issuedVIOLATION_ISSUE_TIME
1535
Date of occurrenceVIOLATION_OCCUR_DT
May 10, 2021
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
May 10, 2021
Originally due, timeORIG_TERM_DUE_TIME
1540
Latest dueLATEST_TERM_DUE_DT
May 10, 2021
Latest due, timeLATEST_TERM_DUE_TIME
1540
TerminatedTERMINATION_DT
May 10, 2021
Terminated, timeTERMINATION_TIME
1540
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
125
Current proposed assessmentAMOUNT_DUE
125
Amount paidAMOUNT_PAID
125
Bill first printedBILL_PRINT_DT
Jul 1, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Aug 31, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 2, 2021
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886448
Inspection beganINSPECTION_BEGIN_DT
May 10, 2021
Inspection closed outINSPECTION_END_DT
May 11, 2021
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2021
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: May 10, 2021
Type: Citation
Standard: 56.9300(a)
S&S: Y
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $302.00
Details

The citation

Citation or order numberVIOLATION_NO
9642257
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
May 10, 2021
Time issuedVIOLATION_ISSUE_TIME
1230
Date of occurrenceVIOLATION_OCCUR_DT
May 10, 2021
30 CFR part and sectionPART_SECTION
56.9300(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
May 10, 2021
Originally due, timeORIG_TERM_DUE_TIME
1400
Latest dueLATEST_TERM_DUE_DT
May 10, 2021
Latest due, timeLATEST_TERM_DUE_TIME
1400
TerminatedTERMINATION_DT
May 10, 2021
Terminated, timeTERMINATION_TIME
1345
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
302
Current proposed assessmentAMOUNT_DUE
302
Amount paidAMOUNT_PAID
302
Bill first printedBILL_PRINT_DT
Jul 1, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Aug 31, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 2, 2021
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886448
Inspection beganINSPECTION_BEGIN_DT
May 10, 2021
Inspection closed outINSPECTION_END_DT
May 11, 2021
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2021
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: May 10, 2021
Type: Citation
Standard: 47.41(c)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $125.00
Details

The citation

Citation or order numberVIOLATION_NO
9642255
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
May 10, 2021
Time issuedVIOLATION_ISSUE_TIME
1100
Date of occurrenceVIOLATION_OCCUR_DT
May 10, 2021
30 CFR part and sectionPART_SECTION
47.41(c)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
May 10, 2021
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
May 10, 2021
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
May 10, 2021
Terminated, timeTERMINATION_TIME
1130
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
125
Current proposed assessmentAMOUNT_DUE
125
Amount paidAMOUNT_PAID
125
Bill first printedBILL_PRINT_DT
Jul 1, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Aug 31, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 2, 2021
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886448
Inspection beganINSPECTION_BEGIN_DT
May 10, 2021
Inspection closed outINSPECTION_END_DT
May 11, 2021
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2021
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: May 10, 2021
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $125.00
Details

The citation

Citation or order numberVIOLATION_NO
9642259
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
May 10, 2021
Time issuedVIOLATION_ISSUE_TIME
1530
Date of occurrenceVIOLATION_OCCUR_DT
May 10, 2021
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
May 10, 2021
Originally due, timeORIG_TERM_DUE_TIME
1530
Latest dueLATEST_TERM_DUE_DT
May 10, 2021
Latest due, timeLATEST_TERM_DUE_TIME
1530
TerminatedTERMINATION_DT
May 10, 2021
Terminated, timeTERMINATION_TIME
1535
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
125
Current proposed assessmentAMOUNT_DUE
125
Amount paidAMOUNT_PAID
125
Bill first printedBILL_PRINT_DT
Jul 1, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Aug 31, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 2, 2021
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886448
Inspection beganINSPECTION_BEGIN_DT
May 10, 2021
Inspection closed outINSPECTION_END_DT
May 11, 2021
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2021
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: May 10, 2021
Type: Citation
Standard: 47.54
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $125.00
Details

The citation

Citation or order numberVIOLATION_NO
9642256
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
May 10, 2021
Time issuedVIOLATION_ISSUE_TIME
1200
Date of occurrenceVIOLATION_OCCUR_DT
May 10, 2021
30 CFR part and sectionPART_SECTION
47.54
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
May 24, 2021
Originally due, timeORIG_TERM_DUE_TIME
1700
Latest dueLATEST_TERM_DUE_DT
May 24, 2021
Latest due, timeLATEST_TERM_DUE_TIME
1700
TerminatedTERMINATION_DT
May 11, 2021
Terminated, timeTERMINATION_TIME
0930
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
125
Current proposed assessmentAMOUNT_DUE
125
Amount paidAMOUNT_PAID
125
Bill first printedBILL_PRINT_DT
Jul 1, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Aug 31, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 2, 2021
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886448
Inspection beganINSPECTION_BEGIN_DT
May 10, 2021
Inspection closed outINSPECTION_END_DT
May 11, 2021
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2021
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: May 10, 2021
Type: Order
Standard: 46.6(b)
S&S: Y
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $1,118.00
Details

The citation

Citation or order numberVIOLATION_NO
9642258
TypeCIT_ORD_SAFE
Order
IssuedVIOLATION_ISSUE_DT
May 10, 2021
Time issuedVIOLATION_ISSUE_TIME
1515
Date of occurrenceVIOLATION_OCCUR_DT
May 10, 2021
30 CFR part and sectionPART_SECTION
46.6(b)
Section of the Act, primarySECTION_OF_ACT_1
104(g)(1)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence
Special assessmentSPECIAL_ASSESS
Y

Abatement

TerminatedTERMINATION_DT
May 11, 2021
Terminated, timeTERMINATION_TIME
0945
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
1118
Current proposed assessmentAMOUNT_DUE
1118
Amount paidAMOUNT_PAID
1118
Bill first printedBILL_PRINT_DT
Dec 2, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Jan 12, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Oct 17, 2022
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886448
Inspection beganINSPECTION_BEGIN_DT
May 10, 2021
Inspection closed outINSPECTION_END_DT
May 11, 2021
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2021
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (3)

From a 103(g) written noticeWRITTEN_NOTICE, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (17)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, Originally dueORIG_TERM_DUE_DT, Originally due, timeORIG_TERM_DUE_TIME, Latest dueLATEST_TERM_DUE_DT, Latest due, timeLATEST_TERM_DUE_TIME, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 9, 2020
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $125.00
Details

The citation

Citation or order numberVIOLATION_NO
9459582
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 9, 2020
Time issuedVIOLATION_ISSUE_TIME
0930
Date of occurrenceVIOLATION_OCCUR_DT
Dec 9, 2020
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 9, 2020
Originally due, timeORIG_TERM_DUE_TIME
1000
Latest dueLATEST_TERM_DUE_DT
Dec 9, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1000
TerminatedTERMINATION_DT
Dec 9, 2020
Terminated, timeTERMINATION_TIME
1000
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
125
Current proposed assessmentAMOUNT_DUE
125
Amount paidAMOUNT_PAID
125
Bill first printedBILL_PRINT_DT
Feb 4, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Mar 14, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Aug 23, 2022
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886411
Inspection beganINSPECTION_BEGIN_DT
Dec 8, 2020
Inspection closed outINSPECTION_END_DT
Dec 10, 2020
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 9, 2020
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $125.00
Details

The citation

Citation or order numberVIOLATION_NO
9459584
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 9, 2020
Time issuedVIOLATION_ISSUE_TIME
0940
Date of occurrenceVIOLATION_OCCUR_DT
Dec 9, 2020
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 9, 2020
Originally due, timeORIG_TERM_DUE_TIME
1000
Latest dueLATEST_TERM_DUE_DT
Dec 9, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1000
TerminatedTERMINATION_DT
Dec 9, 2020
Terminated, timeTERMINATION_TIME
1000
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
125
Current proposed assessmentAMOUNT_DUE
125
Amount paidAMOUNT_PAID
125
Bill first printedBILL_PRINT_DT
Feb 4, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Mar 14, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Aug 23, 2022
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886411
Inspection beganINSPECTION_BEGIN_DT
Dec 8, 2020
Inspection closed outINSPECTION_END_DT
Dec 10, 2020
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 9, 2020
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $125.00
Details

The citation

Citation or order numberVIOLATION_NO
9459583
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 9, 2020
Time issuedVIOLATION_ISSUE_TIME
0935
Date of occurrenceVIOLATION_OCCUR_DT
Dec 9, 2020
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 9, 2020
Originally due, timeORIG_TERM_DUE_TIME
1000
Latest dueLATEST_TERM_DUE_DT
Dec 9, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1000
TerminatedTERMINATION_DT
Dec 9, 2020
Terminated, timeTERMINATION_TIME
1000
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
125
Current proposed assessmentAMOUNT_DUE
125
Amount paidAMOUNT_PAID
125
Bill first printedBILL_PRINT_DT
Feb 4, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Mar 14, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Aug 23, 2022
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886411
Inspection beganINSPECTION_BEGIN_DT
Dec 8, 2020
Inspection closed outINSPECTION_END_DT
Dec 10, 2020
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 8, 2020
Type: Citation
Standard: 56.18002(b)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $125.00
Details

The citation

Citation or order numberVIOLATION_NO
9459581
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 8, 2020
Time issuedVIOLATION_ISSUE_TIME
1345
Date of occurrenceVIOLATION_OCCUR_DT
Dec 8, 2020
30 CFR part and sectionPART_SECTION
56.18002(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 8, 2020
Originally due, timeORIG_TERM_DUE_TIME
1400
Latest dueLATEST_TERM_DUE_DT
Dec 8, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1400
TerminatedTERMINATION_DT
Dec 8, 2020
Terminated, timeTERMINATION_TIME
1400
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
125
Current proposed assessmentAMOUNT_DUE
125
Amount paidAMOUNT_PAID
125
Bill first printedBILL_PRINT_DT
Feb 4, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Mar 14, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Aug 23, 2022
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886411
Inspection beganINSPECTION_BEGIN_DT
Dec 8, 2020
Inspection closed outINSPECTION_END_DT
Dec 10, 2020
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
1

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Dec 8, 2020
Type: Citation
Standard: 56.14206(b)
S&S: Y
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $136.00
Details

The citation

Citation or order numberVIOLATION_NO
9459580
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Dec 8, 2020
Time issuedVIOLATION_ISSUE_TIME
1315
Date of occurrenceVIOLATION_OCCUR_DT
Dec 8, 2020
30 CFR part and sectionPART_SECTION
56.14206(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Dec 8, 2020
Originally due, timeORIG_TERM_DUE_TIME
1330
Latest dueLATEST_TERM_DUE_DT
Dec 8, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1330
TerminatedTERMINATION_DT
Dec 8, 2020
Terminated, timeTERMINATION_TIME
1325
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
136
Current proposed assessmentAMOUNT_DUE
136
Amount paidAMOUNT_PAID
136
Bill first printedBILL_PRINT_DT
Feb 4, 2021
Final order dateFINAL_ORDER_ISSUE_DT
Mar 14, 2021
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 26, 2022
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6886411
Inspection beganINSPECTION_BEGIN_DT
Dec 8, 2020
Inspection closed outINSPECTION_END_DT
Dec 10, 2020
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
1

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 30, 2020
Type: Order
Standard: 46.8(a)(2)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $137.00
Details

The citation

Citation or order numberVIOLATION_NO
9518802
TypeCIT_ORD_SAFE
Order
IssuedVIOLATION_ISSUE_DT
Jul 30, 2020
Time issuedVIOLATION_ISSUE_TIME
1010
Date of occurrenceVIOLATION_OCCUR_DT
Jul 30, 2020
30 CFR part and sectionPART_SECTION
46.8(a)(2)
Section of the Act, primarySECTION_OF_ACT_1
104(g)(1)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

TerminatedTERMINATION_DT
Jul 30, 2020
Terminated, timeTERMINATION_TIME
1311
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
137
Current proposed assessmentAMOUNT_DUE
137
Amount paidAMOUNT_PAID
137
Bill first printedBILL_PRINT_DT
Sep 3, 2020
Final order dateFINAL_ORDER_ISSUE_DT
Oct 14, 2020
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Dec 22, 2020
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6884315
Inspection beganINSPECTION_BEGIN_DT
Jul 30, 2020
Inspection closed outINSPECTION_END_DT
Jul 31, 2020
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (17)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, Originally dueORIG_TERM_DUE_DT, Originally due, timeORIG_TERM_DUE_TIME, Latest dueLATEST_TERM_DUE_DT, Latest due, timeLATEST_TERM_DUE_TIME, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 30, 2020
Type: Citation
Standard: 56.4201(b)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $123.00
Details

The citation

Citation or order numberVIOLATION_NO
9518804
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 30, 2020
Time issuedVIOLATION_ISSUE_TIME
1215
Date of occurrenceVIOLATION_OCCUR_DT
Jul 30, 2020
30 CFR part and sectionPART_SECTION
56.4201(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 31, 2020
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Jul 31, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Jul 30, 2020
Terminated, timeTERMINATION_TIME
1609
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
123
Current proposed assessmentAMOUNT_DUE
123
Amount paidAMOUNT_PAID
123
Bill first printedBILL_PRINT_DT
Sep 3, 2020
Final order dateFINAL_ORDER_ISSUE_DT
Oct 14, 2020
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Dec 22, 2020
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6884315
Inspection beganINSPECTION_BEGIN_DT
Jul 30, 2020
Inspection closed outINSPECTION_END_DT
Jul 31, 2020
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 30, 2020
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $123.00
Details

The citation

Citation or order numberVIOLATION_NO
9518803
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 30, 2020
Time issuedVIOLATION_ISSUE_TIME
1028
Date of occurrenceVIOLATION_OCCUR_DT
Jul 30, 2020
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 30, 2020
Originally due, timeORIG_TERM_DUE_TIME
1030
Latest dueLATEST_TERM_DUE_DT
Jul 30, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1030
TerminatedTERMINATION_DT
Jul 30, 2020
Terminated, timeTERMINATION_TIME
1029
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
123
Current proposed assessmentAMOUNT_DUE
123
Amount paidAMOUNT_PAID
123
Bill first printedBILL_PRINT_DT
Sep 3, 2020
Final order dateFINAL_ORDER_ISSUE_DT
Oct 14, 2020
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Dec 22, 2020
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6884315
Inspection beganINSPECTION_BEGIN_DT
Jul 30, 2020
Inspection closed outINSPECTION_END_DT
Jul 31, 2020
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 30, 2020
Type: Citation
Standard: 56.18002(b)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $123.00
Details

The citation

Citation or order numberVIOLATION_NO
9518801
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 30, 2020
Time issuedVIOLATION_ISSUE_TIME
0810
Date of occurrenceVIOLATION_OCCUR_DT
Jul 30, 2020
30 CFR part and sectionPART_SECTION
56.18002(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 30, 2020
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Jul 30, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Jul 30, 2020
Terminated, timeTERMINATION_TIME
1125
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
123
Current proposed assessmentAMOUNT_DUE
123
Amount paidAMOUNT_PAID
123
Bill first printedBILL_PRINT_DT
Sep 3, 2020
Final order dateFINAL_ORDER_ISSUE_DT
Oct 14, 2020
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Dec 22, 2020
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
C & M Stone Company
Operator IDVIOLATOR_ID
0059563
Controller IDCONTROLLER_ID
0049609
Inspection eventEVENT_NO
6884315
Inspection beganINSPECTION_BEGIN_DT
Jul 30, 2020
Inspection closed outINSPECTION_END_DT
Jul 31, 2020
Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
4

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

63 citations and orders since May 17, 2011: 61 issued to the operator, 2 to contractors working at the mine; the 25 most recent are listed. Proposed penalty is MSHA's original proposed amount, before any change from a contested case. Citations can be contested, modified or vacated.

Penalties as assessed

Issued: Aug 28, 2023
Citation number: 9740958
Standard: 56.1000
Proposed penalty: $143.00
Current assessment: $143.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9740958
Assessment control numberASSESS_CASE_NO
000586274
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Nov 5, 2023
Citation issuedISSUE_DT
Aug 28, 2023
Date of occurrenceOCCURRENCE_DT
Aug 28, 2023
Final order dateFINAL_ORDER_DT
Dec 5, 2023
Bill first printedBILL_PRINT_DT
Oct 5, 2023
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2024
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 5, 2023
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.1000
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
143.00
Current assessmentCURRENT_ASSESSMENT_AMT
143.00
Mine Act interestMINEACT_INTEREST_AMT
1.76

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
4.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
1040
Size of mineSIZE_OF_MINE
1040
Controller hours workedCONTROLLER_HRS
1040
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
1040
History period startHISTORY_START_DT
May 28, 2022
History period endHISTORY_END_DT
Aug 27, 2023

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6935042
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (16)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jan 30, 2023
Citation number: 9740822
Standard: 50.30(a)
Proposed penalty: $143.00
Current assessment: $143.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9740822
Assessment control numberASSESS_CASE_NO
000572214
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Mar 11, 2023
Citation issuedISSUE_DT
Jan 30, 2023
Date of occurrenceOCCURRENCE_DT
Jan 30, 2023
Final order dateFINAL_ORDER_DT
Apr 9, 2023
Bill first printedBILL_PRINT_DT
Mar 2, 2023
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2023
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Apr 9, 2023
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
143.00
Current assessmentCURRENT_ASSESSMENT_AMT
143.00
Mine Act interestMINEACT_INTEREST_AMT
0.88

Penalty points

Violation history pointsPENALTY_POINTS
51
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
2
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
2
Repeat violations per inspection dayRPID
0.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
1040
Size of mineSIZE_OF_MINE
1040
Controller hours workedCONTROLLER_HRS
1040
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
1040
History period startHISTORY_START_DT
Oct 30, 2021
History period endHISTORY_END_DT
Jan 29, 2023

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889899
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (12)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jan 30, 2023
Citation number: 9740821
Standard: 56.14105
Proposed penalty: $143.00
Current assessment: $143.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9740821
Assessment control numberASSESS_CASE_NO
000572214
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Mar 11, 2023
Citation issuedISSUE_DT
Jan 30, 2023
Date of occurrenceOCCURRENCE_DT
Jan 30, 2023
Final order dateFINAL_ORDER_DT
Apr 9, 2023
Bill first printedBILL_PRINT_DT
Mar 2, 2023
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2023
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Apr 9, 2023
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14105
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
143.00
Current assessmentCURRENT_ASSESSMENT_AMT
143.00
Mine Act interestMINEACT_INTEREST_AMT
0.88

Penalty points

Violation history pointsPENALTY_POINTS
56
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
2
Operator hours worked at the mineVIOLATOR_MINE_HRS
1040
Size of mineSIZE_OF_MINE
1040
Controller hours workedCONTROLLER_HRS
1040
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
1040
History period startHISTORY_START_DT
Oct 30, 2021
History period endHISTORY_END_DT
Jan 29, 2023

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889899
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (14)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Aug 31, 2022
Citation number: 9674503
Standard: 56.14206(b)
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9674503
Assessment control numberASSESS_CASE_NO
000565871
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Nov 16, 2022
Citation issuedISSUE_DT
Aug 31, 2022
Date of occurrenceOCCURRENCE_DT
Aug 31, 2022
Final order dateFINAL_ORDER_DT
Dec 16, 2022
Bill first printedBILL_PRINT_DT
Nov 3, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2023
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 16, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14206(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Mine Act interestMINEACT_INTEREST_AMT
1.00
Excessive late payment interestEXLATE_INTEREST_AMT
1.00

Penalty points

Violation history pointsPENALTY_POINTS
51
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
3
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
May 31, 2021
History period endHISTORY_END_DT
Aug 30, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889867
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Aug 31, 2022
Citation number: 9674504
Standard: 56.4402
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9674504
Assessment control numberASSESS_CASE_NO
000565871
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Nov 16, 2022
Citation issuedISSUE_DT
Aug 31, 2022
Date of occurrenceOCCURRENCE_DT
Aug 31, 2022
Final order dateFINAL_ORDER_DT
Dec 16, 2022
Bill first printedBILL_PRINT_DT
Nov 3, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2023
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 16, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.4402
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Mine Act interestMINEACT_INTEREST_AMT
1.00
Excessive late payment interestEXLATE_INTEREST_AMT
1.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
3
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
May 31, 2021
History period endHISTORY_END_DT
Aug 30, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889867
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Aug 31, 2022
Citation number: 9674506
Standard: 56.4201(a)(2)
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9674506
Assessment control numberASSESS_CASE_NO
000565871
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Nov 16, 2022
Citation issuedISSUE_DT
Aug 31, 2022
Date of occurrenceOCCURRENCE_DT
Aug 31, 2022
Final order dateFINAL_ORDER_DT
Dec 16, 2022
Bill first printedBILL_PRINT_DT
Nov 3, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2023
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 16, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.4201(a)(2)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Mine Act interestMINEACT_INTEREST_AMT
1.00
Excessive late payment interestEXLATE_INTEREST_AMT
1.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
3
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
May 31, 2021
History period endHISTORY_END_DT
Aug 30, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889867
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Aug 31, 2022
Citation number: 9674505
Standard: 56.14130(g)
Proposed penalty: $1,069.00
Current assessment: $1,069.00
Paid against proposed penalty: $0.00
Case status: Received
Details

The assessment

Citation or order numberVIOLATION_NO
9674505
Assessment control numberASSESS_CASE_NO
000565871
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Received
Case status dateASSESS_CASE_STATUS_DT
Nov 16, 2022
Citation issuedISSUE_DT
Aug 31, 2022
Date of occurrenceOCCURRENCE_DT
Aug 31, 2022
Final order dateFINAL_ORDER_DT
Dec 16, 2022
Bill first printedBILL_PRINT_DT
Nov 3, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2023
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 16, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14130(g)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
1069.00
Current assessmentCURRENT_ASSESSMENT_AMT
1069.00
Mine Act interestMINEACT_INTEREST_AMT
16.00
Excessive late payment interestEXLATE_INTEREST_AMT
10.00

Penalty points

Violation history pointsPENALTY_POINTS
86
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
3
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
May 31, 2021
History period endHISTORY_END_DT
Aug 30, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6889867
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Mar 23, 2022
Citation number: 9646757
Standard: 50.30(a)
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $133.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9646757
Assessment control numberASSESS_CASE_NO
000554102
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
May 4, 2023
Citation issuedISSUE_DT
Mar 23, 2022
Date of occurrenceOCCURRENCE_DT
Mar 23, 2022
Final order dateFINAL_ORDER_DT
Jun 11, 2022
Bill first printedBILL_PRINT_DT
May 5, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jun 11, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Mine Act interestMINEACT_INTEREST_AMT
2.34
Excessive late payment interestEXLATE_INTEREST_AMT
1.40
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
133.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
2.34
Paid against late payment interestPAID_EXLATE_INTEREST_AMT
1.40

Penalty points

Violation history pointsPENALTY_POINTS
60
Negligence pointsNEGLIGENCE_POINTS
35
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
11
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
3.67
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
5
Repeat violations per inspection dayRPID
1.667
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
Dec 23, 2020
History period endHISTORY_END_DT
Mar 22, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6888836
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (10)

Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Mar 23, 2022
Citation number: 9646756
Standard: 50.30(a)
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $133.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9646756
Assessment control numberASSESS_CASE_NO
000554102
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
May 4, 2023
Citation issuedISSUE_DT
Mar 23, 2022
Date of occurrenceOCCURRENCE_DT
Mar 23, 2022
Final order dateFINAL_ORDER_DT
Jun 11, 2022
Bill first printedBILL_PRINT_DT
May 5, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jun 11, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Mine Act interestMINEACT_INTEREST_AMT
2.34
Excessive late payment interestEXLATE_INTEREST_AMT
1.40
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
133.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
2.34
Paid against late payment interestPAID_EXLATE_INTEREST_AMT
1.40

Penalty points

Violation history pointsPENALTY_POINTS
60
Negligence pointsNEGLIGENCE_POINTS
35
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
11
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
3.67
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
5
Repeat violations per inspection dayRPID
1.667
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
Dec 23, 2020
History period endHISTORY_END_DT
Mar 22, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6888836
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (10)

Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Mar 23, 2022
Citation number: 9646755
Standard: 56.14100(b)
Proposed penalty: $716.00
Current assessment: $716.00
Paid against proposed penalty: $716.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9646755
Assessment control numberASSESS_CASE_NO
000554102
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
May 4, 2023
Citation issuedISSUE_DT
Mar 23, 2022
Date of occurrenceOCCURRENCE_DT
Mar 23, 2022
Final order dateFINAL_ORDER_DT
Jun 11, 2022
Bill first printedBILL_PRINT_DT
May 5, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jun 11, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
716.00
Current assessmentCURRENT_ASSESSMENT_AMT
716.00
Mine Act interestMINEACT_INTEREST_AMT
12.55
Excessive late payment interestEXLATE_INTEREST_AMT
7.53
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
716.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
12.55
Paid against late payment interestPAID_EXLATE_INTEREST_AMT
7.53

Penalty points

Violation history pointsPENALTY_POINTS
81
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
20
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
11
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
3.67
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
Dec 23, 2020
History period endHISTORY_END_DT
Mar 22, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6888836
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (9)

Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: May 10, 2021
Citation number: 9642255
Standard: 47.41(c)
Proposed penalty: $125.00
Current assessment: $125.00
Paid against proposed penalty: $125.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9642255
Assessment control numberASSESS_CASE_NO
000537853
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 2, 2021
Citation issuedISSUE_DT
May 10, 2021
Date of occurrenceOCCURRENCE_DT
May 10, 2021
Final order dateFINAL_ORDER_DT
Aug 31, 2021
Bill first printedBILL_PRINT_DT
Jul 1, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 31, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
47.41(c)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
125.00
Current assessmentCURRENT_ASSESSMENT_AMT
125.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
125.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
1.8
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
Feb 10, 2020
History period endHISTORY_END_DT
May 9, 2021

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886448
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: May 10, 2021
Citation number: 9642256
Standard: 47.54
Proposed penalty: $125.00
Current assessment: $125.00
Paid against proposed penalty: $125.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9642256
Assessment control numberASSESS_CASE_NO
000537853
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 2, 2021
Citation issuedISSUE_DT
May 10, 2021
Date of occurrenceOCCURRENCE_DT
May 10, 2021
Final order dateFINAL_ORDER_DT
Aug 31, 2021
Bill first printedBILL_PRINT_DT
Jul 1, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 31, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
47.54
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
125.00
Current assessmentCURRENT_ASSESSMENT_AMT
125.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
125.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
1.8
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
Feb 10, 2020
History period endHISTORY_END_DT
May 9, 2021

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886448
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: May 10, 2021
Citation number: 9642257
Standard: 56.9300(a)
Proposed penalty: $302.00
Current assessment: $302.00
Paid against proposed penalty: $302.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9642257
Assessment control numberASSESS_CASE_NO
000537853
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 2, 2021
Citation issuedISSUE_DT
May 10, 2021
Date of occurrenceOCCURRENCE_DT
May 10, 2021
Final order dateFINAL_ORDER_DT
Aug 31, 2021
Bill first printedBILL_PRINT_DT
Jul 1, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 31, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.9300(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
302.00
Current assessmentCURRENT_ASSESSMENT_AMT
302.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
302.00

Penalty points

Violation history pointsPENALTY_POINTS
71
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
1.8
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
Feb 10, 2020
History period endHISTORY_END_DT
May 9, 2021

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886448
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: May 10, 2021
Citation number: 9642259
Standard: 50.30(a)
Proposed penalty: $125.00
Current assessment: $125.00
Paid against proposed penalty: $125.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9642259
Assessment control numberASSESS_CASE_NO
000537853
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 2, 2021
Citation issuedISSUE_DT
May 10, 2021
Date of occurrenceOCCURRENCE_DT
May 10, 2021
Final order dateFINAL_ORDER_DT
Aug 31, 2021
Bill first printedBILL_PRINT_DT
Jul 1, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 31, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
125.00
Current assessmentCURRENT_ASSESSMENT_AMT
125.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
125.00

Penalty points

Violation history pointsPENALTY_POINTS
35
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
1.8
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
4
Repeat violations per inspection dayRPID
0.8
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
Feb 10, 2020
History period endHISTORY_END_DT
May 9, 2021

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886448
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: May 10, 2021
Citation number: 9642260
Standard: 50.30(a)
Proposed penalty: $125.00
Current assessment: $125.00
Paid against proposed penalty: $125.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9642260
Assessment control numberASSESS_CASE_NO
000537853
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 2, 2021
Citation issuedISSUE_DT
May 10, 2021
Date of occurrenceOCCURRENCE_DT
May 10, 2021
Final order dateFINAL_ORDER_DT
Aug 31, 2021
Bill first printedBILL_PRINT_DT
Jul 1, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Aug 31, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
125.00
Current assessmentCURRENT_ASSESSMENT_AMT
125.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
125.00

Penalty points

Violation history pointsPENALTY_POINTS
35
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
1.8
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
4
Repeat violations per inspection dayRPID
0.8
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
Feb 10, 2020
History period endHISTORY_END_DT
May 9, 2021

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886448
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: May 10, 2021
Citation number: 9642258
Standard: 46.6(b)
Proposed penalty: $1,118.00
Current assessment: $1,118.00
Paid against proposed penalty: $1,118.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9642258
Assessment control numberASSESS_CASE_NO
000546351
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Oct 6, 2022
Citation issuedISSUE_DT
May 10, 2021
Date of occurrenceOCCURRENCE_DT
May 10, 2021
Final order dateFINAL_ORDER_DT
Jan 12, 2022
Bill first printedBILL_PRINT_DT
Dec 2, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jan 12, 2022
Citation typeCITATION_TYPE_CD
Order
30 CFR standardCFR_STANDARD_CD
46.6(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(g)(1)
Significant and substantialSIG_SUB_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
1118.00
Current assessmentCURRENT_ASSESSMENT_AMT
1118.00
Mine Act interestMINEACT_INTEREST_AMT
20.34
Excessive late payment interestEXLATE_INTEREST_AMT
11.95
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
1118.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
20.34
Paid against late payment interestPAID_EXLATE_INTEREST_AMT
11.95

Penalty points

Violation history pointsPENALTY_POINTS
86
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
1.8
Operator hours worked at the mineVIOLATOR_MINE_HRS
960
Size of mineSIZE_OF_MINE
960
Controller hours workedCONTROLLER_HRS
960
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
960
History period startHISTORY_START_DT
Feb 10, 2020
History period endHISTORY_END_DT
May 9, 2021

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886448
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (10)

Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Good faith reduction appliedGOOD_FAITH_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 9, 2020
Citation number: 9459582
Standard: 50.30(a)
Proposed penalty: $125.00
Current assessment: $125.00
Paid against proposed penalty: $125.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9459582
Assessment control numberASSESS_CASE_NO
000529295
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Aug 18, 2022
Citation issuedISSUE_DT
Dec 9, 2020
Date of occurrenceOCCURRENCE_DT
Dec 9, 2020
Final order dateFINAL_ORDER_DT
Mar 14, 2021
Bill first printedBILL_PRINT_DT
Feb 4, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 14, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
125.00
Current assessmentCURRENT_ASSESSMENT_AMT
125.00
Mine Act interestMINEACT_INTEREST_AMT
2.17
Excessive late payment interestEXLATE_INTEREST_AMT
1.27
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
125.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
2.17
Paid against late payment interestPAID_EXLATE_INTEREST_AMT
1.27

Penalty points

Violation history pointsPENALTY_POINTS
20
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6
Violations per inspection dayVPID
1.33
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
2
Repeat violations per inspection dayRPID
0.333
Operator hours worked at the mineVIOLATOR_MINE_HRS
4320
Size of mineSIZE_OF_MINE
4320
Controller hours workedCONTROLLER_HRS
4320
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4320
History period startHISTORY_START_DT
Sep 9, 2019
History period endHISTORY_END_DT
Dec 8, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886411
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (11)

Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 9, 2020
Citation number: 9459583
Standard: 50.30(a)
Proposed penalty: $125.00
Current assessment: $125.00
Paid against proposed penalty: $125.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9459583
Assessment control numberASSESS_CASE_NO
000529295
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Aug 18, 2022
Citation issuedISSUE_DT
Dec 9, 2020
Date of occurrenceOCCURRENCE_DT
Dec 9, 2020
Final order dateFINAL_ORDER_DT
Mar 14, 2021
Bill first printedBILL_PRINT_DT
Feb 4, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 14, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
125.00
Current assessmentCURRENT_ASSESSMENT_AMT
125.00
Mine Act interestMINEACT_INTEREST_AMT
2.17
Excessive late payment interestEXLATE_INTEREST_AMT
1.27
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
125.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
2.17
Paid against late payment interestPAID_EXLATE_INTEREST_AMT
1.27

Penalty points

Violation history pointsPENALTY_POINTS
20
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6
Violations per inspection dayVPID
1.33
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
2
Repeat violations per inspection dayRPID
0.333
Operator hours worked at the mineVIOLATOR_MINE_HRS
4320
Size of mineSIZE_OF_MINE
4320
Controller hours workedCONTROLLER_HRS
4320
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4320
History period startHISTORY_START_DT
Sep 9, 2019
History period endHISTORY_END_DT
Dec 8, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886411
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (11)

Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 9, 2020
Citation number: 9459584
Standard: 50.30(a)
Proposed penalty: $125.00
Current assessment: $125.00
Paid against proposed penalty: $125.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9459584
Assessment control numberASSESS_CASE_NO
000529295
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Aug 18, 2022
Citation issuedISSUE_DT
Dec 9, 2020
Date of occurrenceOCCURRENCE_DT
Dec 9, 2020
Final order dateFINAL_ORDER_DT
Mar 14, 2021
Bill first printedBILL_PRINT_DT
Feb 4, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 14, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
125.00
Current assessmentCURRENT_ASSESSMENT_AMT
125.00
Mine Act interestMINEACT_INTEREST_AMT
2.17
Excessive late payment interestEXLATE_INTEREST_AMT
1.27
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
125.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
2.17
Paid against late payment interestPAID_EXLATE_INTEREST_AMT
1.27

Penalty points

Violation history pointsPENALTY_POINTS
20
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6
Violations per inspection dayVPID
1.33
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
2
Repeat violations per inspection dayRPID
0.333
Operator hours worked at the mineVIOLATOR_MINE_HRS
4320
Size of mineSIZE_OF_MINE
4320
Controller hours workedCONTROLLER_HRS
4320
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4320
History period startHISTORY_START_DT
Sep 9, 2019
History period endHISTORY_END_DT
Dec 8, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886411
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (11)

Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 8, 2020
Citation number: 9459580
Standard: 56.14206(b)
Proposed penalty: $136.00
Current assessment: $136.00
Paid against proposed penalty: $136.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9459580
Assessment control numberASSESS_CASE_NO
000529295
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Aug 18, 2022
Citation issuedISSUE_DT
Dec 8, 2020
Date of occurrenceOCCURRENCE_DT
Dec 8, 2020
Final order dateFINAL_ORDER_DT
Mar 14, 2021
Bill first printedBILL_PRINT_DT
Feb 4, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 14, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14206(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
136.00
Current assessmentCURRENT_ASSESSMENT_AMT
136.00
Mine Act interestMINEACT_INTEREST_AMT
2.35
Excessive late payment interestEXLATE_INTEREST_AMT
1.39
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
136.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
2.35
Paid against late payment interestPAID_EXLATE_INTEREST_AMT
1.39

Penalty points

Violation history pointsPENALTY_POINTS
61
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6
Violations per inspection dayVPID
1.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
4320
Size of mineSIZE_OF_MINE
4320
Controller hours workedCONTROLLER_HRS
4320
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4320
History period startHISTORY_START_DT
Sep 8, 2019
History period endHISTORY_END_DT
Dec 7, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886411
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (10)

Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Dec 8, 2020
Citation number: 9459581
Standard: 56.18002(b)
Proposed penalty: $125.00
Current assessment: $125.00
Paid against proposed penalty: $125.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9459581
Assessment control numberASSESS_CASE_NO
000529295
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Aug 18, 2022
Citation issuedISSUE_DT
Dec 8, 2020
Date of occurrenceOCCURRENCE_DT
Dec 8, 2020
Final order dateFINAL_ORDER_DT
Mar 14, 2021
Bill first printedBILL_PRINT_DT
Feb 4, 2021
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2021
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Mar 14, 2021
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.18002(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
125.00
Current assessmentCURRENT_ASSESSMENT_AMT
125.00
Mine Act interestMINEACT_INTEREST_AMT
2.17
Excessive late payment interestEXLATE_INTEREST_AMT
1.27
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
125.00
Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT
2.17
Paid against late payment interestPAID_EXLATE_INTEREST_AMT
1.27

Penalty points

Violation history pointsPENALTY_POINTS
20
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
8
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
6
Violations per inspection dayVPID
1.33
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
1
Repeat violations per inspection dayRPID
0.167
Operator hours worked at the mineVIOLATOR_MINE_HRS
4320
Size of mineSIZE_OF_MINE
4320
Controller hours workedCONTROLLER_HRS
4320
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4320
History period startHISTORY_START_DT
Sep 8, 2019
History period endHISTORY_END_DT
Dec 7, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6886411
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (11)

Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 30, 2020
Citation number: 9518802
Standard: 46.8(a)(2)
Proposed penalty: $137.00
Current assessment: $137.00
Paid against proposed penalty: $137.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9518802
Assessment control numberASSESS_CASE_NO
000521111
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Dec 21, 2020
Citation issuedISSUE_DT
Jul 30, 2020
Date of occurrenceOCCURRENCE_DT
Jul 30, 2020
Final order dateFINAL_ORDER_DT
Oct 14, 2020
Bill first printedBILL_PRINT_DT
Sep 3, 2020
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2020
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 14, 2020
Citation typeCITATION_TYPE_CD
Order
30 CFR standardCFR_STANDARD_CD
46.8(a)(2)
Section of the Act, primaryPRIMARY_ACTION_CD
104(g)(1)

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
137.00
Current assessmentCURRENT_ASSESSMENT_AMT
137.00
Mine Act interestMINEACT_INTEREST_AMT
0.60
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
137.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
1.8
Operator hours worked at the mineVIOLATOR_MINE_HRS
4320
Size of mineSIZE_OF_MINE
4320
Controller hours workedCONTROLLER_HRS
4320
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4320
History period startHISTORY_START_DT
Apr 30, 2019
History period endHISTORY_END_DT
Jul 29, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6884315
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (3)

Significant and substantialSIG_SUB_IND, Good faith reduction appliedGOOD_FAITH_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 30, 2020
Citation number: 9518804
Standard: 56.4201(b)
Proposed penalty: $123.00
Current assessment: $123.00
Paid against proposed penalty: $123.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9518804
Assessment control numberASSESS_CASE_NO
000521111
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Dec 21, 2020
Citation issuedISSUE_DT
Jul 30, 2020
Date of occurrenceOCCURRENCE_DT
Jul 30, 2020
Final order dateFINAL_ORDER_DT
Oct 14, 2020
Bill first printedBILL_PRINT_DT
Sep 3, 2020
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2020
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 14, 2020
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.4201(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
123.00
Current assessmentCURRENT_ASSESSMENT_AMT
123.00
Mine Act interestMINEACT_INTEREST_AMT
0.54
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
123.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
1.8
Operator hours worked at the mineVIOLATOR_MINE_HRS
4320
Size of mineSIZE_OF_MINE
4320
Controller hours workedCONTROLLER_HRS
4320
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4320
History period startHISTORY_START_DT
Apr 30, 2019
History period endHISTORY_END_DT
Jul 29, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6884315
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 30, 2020
Citation number: 9518801
Standard: 56.18002(b)
Proposed penalty: $123.00
Current assessment: $123.00
Paid against proposed penalty: $123.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9518801
Assessment control numberASSESS_CASE_NO
000521111
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Dec 21, 2020
Citation issuedISSUE_DT
Jul 30, 2020
Date of occurrenceOCCURRENCE_DT
Jul 30, 2020
Final order dateFINAL_ORDER_DT
Oct 14, 2020
Bill first printedBILL_PRINT_DT
Sep 3, 2020
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2020
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 14, 2020
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.18002(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
123.00
Current assessmentCURRENT_ASSESSMENT_AMT
123.00
Mine Act interestMINEACT_INTEREST_AMT
0.54
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
123.00

Penalty points

Violation history pointsPENALTY_POINTS
51
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
1.8
Operator hours worked at the mineVIOLATOR_MINE_HRS
4320
Size of mineSIZE_OF_MINE
4320
Controller hours workedCONTROLLER_HRS
4320
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4320
History period startHISTORY_START_DT
Apr 30, 2019
History period endHISTORY_END_DT
Jul 29, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6884315
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 30, 2020
Citation number: 9518803
Standard: 50.30(a)
Proposed penalty: $123.00
Current assessment: $123.00
Paid against proposed penalty: $123.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9518803
Assessment control numberASSESS_CASE_NO
000521111
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Dec 21, 2020
Citation issuedISSUE_DT
Jul 30, 2020
Date of occurrenceOCCURRENCE_DT
Jul 30, 2020
Final order dateFINAL_ORDER_DT
Oct 14, 2020
Bill first printedBILL_PRINT_DT
Sep 3, 2020
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2020
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 14, 2020
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
123.00
Current assessmentCURRENT_ASSESSMENT_AMT
123.00
Mine Act interestMINEACT_INTEREST_AMT
0.54
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
123.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Negligence pointsNEGLIGENCE_POINTS
35

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
9
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
5
Violations per inspection dayVPID
1.8
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
3
Repeat violations per inspection dayRPID
0.6
Operator hours worked at the mineVIOLATOR_MINE_HRS
4320
Size of mineSIZE_OF_MINE
4320
Controller hours workedCONTROLLER_HRS
4320
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
4320
History period startHISTORY_START_DT
Apr 30, 2019
History period endHISTORY_END_DT
Jul 29, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
C & M Stone Company
IDVIOLATOR_ID
0059563
Operator start at the mine, as assessedVIOLATOR_START_DT
May 16, 2011
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6884315
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M5871

Recorded as 0 (13)

Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Mine size pointsMINE_SIZE_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

25 most recent of 63 assessed citations and orders. Amounts are MSHA's per-citation values; case status is MSHA's own (Closed, Invalid, Printed or Received).

Employment and hours worked

Year: 2023
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 3
Hours worked: 520
Details

The report

YearCALENDAR_YR
2023
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
520
Average hours per employeeAVG_EMPLOYEE_HOURS
173

Mine

Mine IDMINE_ID
0302011
Mine name in this fileCURR_MINE_NM
C & M Stone Company Cecil Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2022
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 3
Hours worked: 1,040
Details

The report

YearCALENDAR_YR
2022
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
1040
Average hours per employeeAVG_EMPLOYEE_HOURS
347

Mine

Mine IDMINE_ID
0302011
Mine name in this fileCURR_MINE_NM
C & M Stone Company Cecil Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2021
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 2
Hours worked: 960
Details

The report

YearCALENDAR_YR
2021
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
2
Hours workedANNUAL_HRS
960
Average hours per employeeAVG_EMPLOYEE_HOURS
480

Mine

Mine IDMINE_ID
0302011
Mine name in this fileCURR_MINE_NM
C & M Stone Company Cecil Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2020
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 2
Hours worked: 960
Details

The report

YearCALENDAR_YR
2020
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
2
Hours workedANNUAL_HRS
960
Average hours per employeeAVG_EMPLOYEE_HOURS
480

Mine

Mine IDMINE_ID
0302011
Mine name in this fileCURR_MINE_NM
C & M Stone Company Cecil Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2019
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 3
Hours worked: 4,320
Details

The report

YearCALENDAR_YR
2019
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
4320
Average hours per employeeAVG_EMPLOYEE_HOURS
1440

Mine

Mine IDMINE_ID
0302011
Mine name in this fileCURR_MINE_NM
C & M Stone Company Cecil Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2018
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 5
Hours worked: 14,327
Details

The report

YearCALENDAR_YR
2018
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
5
Hours workedANNUAL_HRS
14327
Average hours per employeeAVG_EMPLOYEE_HOURS
2865

Mine

Mine IDMINE_ID
0302011
Mine name in this fileCURR_MINE_NM
C & M Stone Company Cecil Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2017
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 9
Hours worked: 19,610
Details

The report

YearCALENDAR_YR
2017
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
9
Hours workedANNUAL_HRS
19610
Average hours per employeeAVG_EMPLOYEE_HOURS
2179

Mine

Mine IDMINE_ID
0302011
Mine name in this fileCURR_MINE_NM
C & M Stone Company Cecil Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2016
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 7
Hours worked: 14,695
Details

The report

YearCALENDAR_YR
2016
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
7
Hours workedANNUAL_HRS
14695
Average hours per employeeAVG_EMPLOYEE_HOURS
2099

Mine

Mine IDMINE_ID
0302011
Mine name in this fileCURR_MINE_NM
C & M Stone Company Cecil Quarry
StateSTATE_ABBR
AR
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

What the operator reported to MSHA for the 8 most recent years, one row per part of the mine, as MSHA files them. Rows are not added together.

Mine details

MSHA field office
Little Rock AR Field Office
Nearest town
Cecil
Days worked per week
5
Hours per shift
10
Production shifts per day
1
Maintenance shifts per day
0
Employees, current record
2
Tailing ponds
0
103(i) spot inspection status
Never Had 103I Status
Safety committee
N
Portable operation
N
Every field in MSHA's mine record

The mine

Mine nameCURRENT_MINE_NAME
C & M Stone Company Cecil Quarry
Mine IDMINE_ID
0302011
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Mine typeCURRENT_MINE_TYPE
Surface
Current statusCURRENT_MINE_STATUS
Intermittent
Status sinceCURRENT_STATUS_DT
Oct 15, 2026
Legal entity typeCOMPANY_TYPE
Sole Proprietor

Operator and controller

OperatorCURRENT_OPERATOR_NAME
C & M Stone Company
Operator IDCURRENT_OPERATOR_ID
0059563
Controller IDCURRENT_CONTROLLER_ID
0049609
Start of the operating periodCURRENT_CONTROLLER_BEGIN_DT
May 16, 2011

Location and MSHA office

StateSTATE
AR
Bureau of Mines state codeBOM_STATE_CD
03
FIPS county codeFIPS_CNTY_CD
047
FIPS county nameFIPS_CNTY_NM
Franklin
Nearest townNEAREST_TOWN
Cecil
MSHA districtDISTRICT
M5
MSHA office codeOFFICE_CD
M5871
MSHA officeOFFICE_NAME
Little Rock AR Field Office
Driving miles from the MSHA officeMILES_FROM_OFFICE
143
Most recent assessment control numberASSESS_CTRL_NO
000586274

Commodity

Primary commodity (SIC)PRIMARY_SIC
Dimension Limestone
Primary commodity codePRIMARY_SIC_CD
141102
Primary SIC codePRIMARY_SIC_CD_1
1411
Primary SIC suffixPRIMARY_SIC_CD_SFX
02
Primary industry groupPRIMARY_CANVASS
Stone
Primary industry group codePRIMARY_CANVASS_CD
6

Operations, from the Mine Information Form

Days operating per weekDAYS_PER_WEEK
5
Hours per shiftHOURS_PER_SHIFT
10
Production shifts per dayPROD_SHIFTS_PER_DAY
1
Workers employedNO_EMPLOYEES
2
MSHA restricted from enforcing Part 48 trainingPART48_TRAINING
Y
103(i) statusCURRENT_103I
Never Had 103I Status

Recorded as 0 (2)

Maintenance-only shifts per dayMAINT_SHIFTS_PER_DAY, Tailing pondsNO_TAILING_PONDS

Recorded as N (5)

Portable minePORTABLE_OPERATION, Pillar recovery usedPILLAR_RECOVERY_USED, Highwall miner usedHIGHWALL_MINER_USED, Multiple pitsMULTIPLE_PITS, Safety committeeSAFETY_COMMITTEE_IND

Not recorded by MSHA (15)

Portable mine FIPS state codePORTABLE_FIPS_ST_CD, ControllerCURRENT_CONTROLLER_NAME, Congressional districtCONG_DIST_CD, Secondary commodity (SIC)SECONDARY_SIC, Secondary commodity codeSECONDARY_SIC_CD, Secondary SIC codeSECONDARY_SIC_CD_1, Secondary SIC suffixSECONDARY_SIC_CD_SFX, Secondary industry groupSECONDARY_CANVASS, Secondary industry group codeSECONDARY_CANVASS_CD, Average mining height, inchesAVG_MINE_HEIGHT, Mine gas categoryMINE_GAS_CATEGORY_CD, Methane liberation, cu ft per 24 hMETHANE_LIBERATION, Producing pitsNO_PRODUCING_PITS, Non-producing pitsNO_NONPRODUCING_PITS, 103(i) status sinceCURRENT_103I_DT

Operator and controller history

Operator: C & M Stone Company
From: May 16, 2011
To: No end date
Controller: Not shown
From : Nov 9, 2004
To : No end date
Details

Operator

OperatorOPERATOR_NAME
C & M Stone Company
Operator IDOPERATOR_ID
0059563
Operator fromOPERATOR_START_DT
May 16, 2011

Controller

Controller IDCONTROLLER_ID
0049609
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Nov 9, 2004

Mine

Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Mine status at this pointMINE_STATUS
Intermittent
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (3)

Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

As MSHA records it, newest operator first.

Address of record

C & M Stone Company·Contact title Owner·Street not recorded, Knoxville AR 72845

MSHA says an address of record "does not represent the actual mine location."

Every field in the address record

Address

Business nameBUSINESS_NAME
C & M Stone Company
Contact titleCONTACT_TITLE
Owner
CityCITY
Knoxville
StateSTATE_ABBR
AR
State nameSTATE
Arkansas
ZIP codeZIP_CD
72845
CountryCOUNTRY
USA
FIPS state codeFIPS_STATE_CD
05

Mine

Mine IDMINE_ID
0302011
Mine name in this fileMINE_NAME
C & M Stone Company Cecil Quarry
Nearest townNEAREST_TOWN
Cecil
Mine typeMINE_TYPE_CD
Surface
Mine statusMINE_STATUS
Intermittent
Status sinceMINE_STATUS_DT
Oct 15, 2026
Primary commodity (SIC)PRIMARY_SIC_CD
Dimension Limestone
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (4)

StreetSTREET, PO boxPO_BOX, ProvincePROVINCE, Foreign postal codePOSTAL_CD

Sources. MSHA open government data files: Mines, Inspections, Violations, AssessedViolations, ContestedViolations, 107(a)OrdersIssued, Accidents, MinesProdYearly, ControllerOperatorHistory, AddressOfRecord. Field labels are shortened from MSHA's definition files, with MSHA's column name beside each. MSHA Mine Data Retrieval System·MSHA fatality report search·MSHA open government data

These are U.S. Department of Labor, Mine Safety and Health Administration records, reproduced as published. Citations can be contested, modified or vacated, and records that are contested or not yet final are included. SafetyRecord.org is not a consumer reporting agency. MSHA records as of Nov 20, 2026. Data and methodology