Skip to content
SafetyRecord logoSafetyRecord

Portable #1 Big Plant

Metal/Non-Metal, SurfaceConstruction Sand and GravelAmador, CaliforniaMine ID 0405495

Operator Custom Crushing Industries IncController not shownMSHA status Intermittent since Jan 20, 2023

What MSHA has on file for this mine

Citations and orders
93
since Sep 12, 2001 · 93 to the operator, 0 to contractors · 12 marked S&S
Imminent danger orders, section 107(a)
None on record
MSHA's list starts July 1, 2010
Accident, injury or illness reports
None on record
MSHA's file starts January 2000
Yearly employment and hours
8 years
one row per part of the mine

MSHA records as of Nov 13, 2026. Having MSHA inspection records is common for operating mines. Data and methodology

Inspections

Spot Inspection
Jun 11 to Jun 15, 2026Inspectors 1 | Hours on site 4

The inspection

BeganINSPECTION_BEGIN_DT
Jun 11, 2026
Closed outINSPECTION_END_DT
Jun 15, 2026
ActivityACTIVITY
Spot Inspection
Activity codeACTIVITY_CODE
E16
Program areaPROGRAM_AREA
M/NM--Spot Inspection
Event numberEVENT_NO
F036DEF
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4
Total inspection hoursSUM_TOTAL_INSP_HOURS
6

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2026
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Nov 18 to Nov 19, 2025Inspectors 1 | Hours on site 1.5

The inspection

BeganINSPECTION_BEGIN_DT
Nov 18, 2025
Closed outINSPECTION_END_DT
Nov 19, 2025
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
F023BA9
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
1.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
2.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2026
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Apr 17 to Apr 29, 2025Inspectors 2 | Hours on site 18

The inspection

BeganINSPECTION_BEGIN_DT
Apr 17, 2025
Closed outINSPECTION_END_DT
Apr 29, 2025
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6963986
InspectorsNBR_INSPECTOR
2
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
18
Total inspection hoursSUM_TOTAL_INSP_HOURS
48.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jul 17, 2024Inspectors 1 | Hours on site 5.5

The inspection

BeganINSPECTION_BEGIN_DT
Jul 17, 2024
Closed outINSPECTION_END_DT
Jul 17, 2024
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6877599
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
5.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
6

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Feb 6, 2024Inspectors 1 | Hours on site 3

The inspection

BeganINSPECTION_BEGIN_DT
Feb 6, 2024
Closed outINSPECTION_END_DT
Feb 6, 2024
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
7112424
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3
Total inspection hoursSUM_TOTAL_INSP_HOURS
7

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2024
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2024
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Compliance Follow-up Inspection
May 9, 2023Inspectors 1 | Hours on site 1

The inspection

BeganINSPECTION_BEGIN_DT
May 9, 2023
Closed outINSPECTION_END_DT
May 9, 2023
ActivityACTIVITY
Compliance Follow-up Inspection
Activity codeACTIVITY_CODE
E15
Program areaPROGRAM_AREA
M/NM--Compliance Follow-up Inspection
Event numberEVENT_NO
6874393
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
1
Total inspection hoursSUM_TOTAL_INSP_HOURS
3

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Apr 27, 2023Inspectors 1 | Hours on site 10.25

The inspection

BeganINSPECTION_BEGIN_DT
Apr 27, 2023
Closed outINSPECTION_END_DT
Apr 27, 2023
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6874387
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
10.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
13.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Compliance Follow-up Inspection
Aug 8, 2022Inspectors 1 | Hours on site 0.5

The inspection

BeganINSPECTION_BEGIN_DT
Aug 8, 2022
Closed outINSPECTION_END_DT
Aug 8, 2022
ActivityACTIVITY
Compliance Follow-up Inspection
Activity codeACTIVITY_CODE
E15
Program areaPROGRAM_AREA
M/NM--Compliance Follow-up Inspection
Event numberEVENT_NO
6873993
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
0.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
1

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jul 29 to Aug 1, 2022Inspectors 1 | Hours on site 7

The inspection

BeganINSPECTION_BEGIN_DT
Jul 29, 2022
Closed outINSPECTION_END_DT
Aug 1, 2022
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6873984
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
7
Total inspection hoursSUM_TOTAL_INSP_HOURS
11.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jun 1, 2021Inspectors 1 | Hours on site 3.25

The inspection

BeganINSPECTION_BEGIN_DT
Jun 1, 2021
Closed outINSPECTION_END_DT
Jun 1, 2021
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6873729
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
6.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2021
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jan 12, 2021Inspectors 1 | Hours on site 8.5

The inspection

BeganINSPECTION_BEGIN_DT
Jan 12, 2021
Closed outINSPECTION_END_DT
Jan 12, 2021
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6829487
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
8.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
11.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2021
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2021
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Apr 28, 2020Inspectors 1 | Hours on site 4

The inspection

BeganINSPECTION_BEGIN_DT
Apr 28, 2020
Closed outINSPECTION_END_DT
Apr 28, 2020
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6829417
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4
Total inspection hoursSUM_TOTAL_INSP_HOURS
6.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Oct 2 to Oct 4, 2019Inspectors 1 | Hours on site 5.25

The inspection

BeganINSPECTION_BEGIN_DT
Oct 2, 2019
Closed outINSPECTION_END_DT
Oct 4, 2019
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6828592
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
5.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
12

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Apr 16 to Apr 24, 2019Inspectors 1 | Hours on site 7.25

The inspection

BeganINSPECTION_BEGIN_DT
Apr 16, 2019
Closed outINSPECTION_END_DT
Apr 24, 2019
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6728194
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
7.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
19

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2019
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Spot Inspection
Apr 3 to Apr 4, 2018Inspectors 1 | Hours on site 3.75

The inspection

BeganINSPECTION_BEGIN_DT
Apr 3, 2018
Closed outINSPECTION_END_DT
Apr 4, 2018
ActivityACTIVITY
Spot Inspection
Activity codeACTIVITY_CODE
E16
Program areaPROGRAM_AREA
M/NM--Spot Inspection
Event numberEVENT_NO
6728420
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
7.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jan 3 to Jan 5, 2018Inspectors 3 | Hours on site 2.5

The inspection

BeganINSPECTION_BEGIN_DT
Jan 3, 2018
Closed outINSPECTION_END_DT
Jan 5, 2018
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6721962
InspectorsNBR_INSPECTOR
3
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
2.5
Total inspection hoursSUM_TOTAL_INSP_HOURS
11.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Mar 21 to Mar 23, 2017Inspectors 1 | Hours on site 12.75

The inspection

BeganINSPECTION_BEGIN_DT
Mar 21, 2017
Closed outINSPECTION_END_DT
Mar 23, 2017
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6721718
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
12.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
25.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
2
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Compliance Follow-up Inspection
Aug 1, 2016Inspectors 1 | Hours on site 1

The inspection

BeganINSPECTION_BEGIN_DT
Aug 1, 2016
Closed outINSPECTION_END_DT
Aug 1, 2016
ActivityACTIVITY
Compliance Follow-up Inspection
Activity codeACTIVITY_CODE
E15
Program areaPROGRAM_AREA
M/NM--Compliance Follow-up Inspection
Event numberEVENT_NO
6599189
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
1
Total inspection hoursSUM_TOTAL_INSP_HOURS
3.5

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Jul 18 to Jul 20, 2016Inspectors 1 | Hours on site 3.75

The inspection

BeganINSPECTION_BEGIN_DT
Jul 18, 2016
Closed outINSPECTION_END_DT
Jul 20, 2016
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6599181
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
3.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
9

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Mine Idle Activity
Jun 7, 2016Inspectors 1 | Hours on site 0.75

The inspection

BeganINSPECTION_BEGIN_DT
Jun 7, 2016
Closed outINSPECTION_END_DT
Jun 7, 2016
ActivityACTIVITY
Mine Idle Activity
Activity codeACTIVITY_CODE
E28
Program areaPROGRAM_AREA
M/NM--Mine Idle Activity
Event numberEVENT_NO
6663955
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
0.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
4

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2016
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2016
MSHA fiscal quarterFISCAL_QTR
3
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Mine Idle Activity
Jul 7, 2015Inspectors 1 | Hours on site 1

The inspection

BeganINSPECTION_BEGIN_DT
Jul 7, 2015
Closed outINSPECTION_END_DT
Jul 7, 2015
ActivityACTIVITY
Mine Idle Activity
Activity codeACTIVITY_CODE
E28
Program areaPROGRAM_AREA
M/NM--Mine Idle Activity
Event numberEVENT_NO
6721001
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
1
Total inspection hoursSUM_TOTAL_INSP_HOURS
8.75

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2015
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2015
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Aug 20, 2014Inspectors 1 | Hours on site 4.75

The inspection

BeganINSPECTION_BEGIN_DT
Aug 20, 2014
Closed outINSPECTION_END_DT
Aug 20, 2014
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1161845
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
4.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
10

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2014
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2014
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Aug 22, 2013Inspectors 2 | Hours on site 19

The inspection

BeganINSPECTION_BEGIN_DT
Aug 22, 2013
Closed outINSPECTION_END_DT
Aug 22, 2013
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
6652022
InspectorsNBR_INSPECTOR
2
Inspector's office codeINSPECT_OFFICE_CD
M7651
Hours on siteSUM_TOTAL_ON_SITE_HOURS
19
Total inspection hoursSUM_TOTAL_INSP_HOURS
24

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2013
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2013
MSHA fiscal quarterFISCAL_QTR
4
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Compliance Follow-up Inspection
Nov 14, 2011Inspectors 1 | Hours on site 0.75

The inspection

BeganINSPECTION_BEGIN_DT
Nov 14, 2011
Closed outINSPECTION_END_DT
Nov 14, 2011
ActivityACTIVITY
Compliance Follow-up Inspection
Activity codeACTIVITY_CODE
E15
Program areaPROGRAM_AREA
M/NM--Compliance Follow-up Inspection
Event numberEVENT_NO
1155592
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
0.75
Total inspection hoursSUM_TOTAL_INSP_HOURS
6.25

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2011
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2012
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

Regular Safety and Health Inspection
Nov 2 to Nov 3, 2011Inspectors 1 | Hours on site 8.25

The inspection

BeganINSPECTION_BEGIN_DT
Nov 2, 2011
Closed outINSPECTION_END_DT
Nov 3, 2011
ActivityACTIVITY
Regular Safety and Health Inspection
Activity codeACTIVITY_CODE
E01
Program areaPROGRAM_AREA
M/NM--Regular Safety and Health Inspection
Event numberEVENT_NO
1155591
InspectorsNBR_INSPECTOR
1
Inspector's office codeINSPECT_OFFICE_CD
M7821
Hours on siteSUM_TOTAL_ON_SITE_HOURS
8.25
Total inspection hoursSUM_TOTAL_INSP_HOURS
18

Who and when, as recorded

Operator at the timeOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Mine IDMINE_ID
0405495
Calendar yearCAL_YR
2011
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2012
MSHA fiscal quarterFISCAL_QTR
1
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Recorded as 0 (13)

Active working sectionsACTIVE_SECTIONS, Idle working sectionsIDLE_SECTIONS, Shaft or slope sinking areasSHAFT_SLOPE_SINK, Impoundment constructionIMPOUND_CONSTR, Building construction sitesBLDG_CONSTR_SITES, Dragline or shovel constructionDRAGLINES, Other construction areasUNCLASSIFIED_CONSTR, Air samplesSAMPLE_CNT_AIR, Spot dust samplesSAMPLE_CNT_DUSTSPOT, Survey samplesSAMPLE_CNT_DUSTSURVEY, Respiratory dust samplesSAMPLE_CNT_RESPDUST, Noise samplesSAMPLE_CNT_NOISE, Other samplesSAMPLE_CNT_OTHER

Recorded as N (10)

Company recordsCO_RECORDS, Surface area or underground mineSURF_UG_MINE, Surface mine or facilitySURF_FACILITY_MINE, Refuse pilesREFUSE_PILES, Explosives storageEXPLOSIVE_STORAGE, Outby areasOUTBY_AREAS, Major constructionMAJOR_CONSTR, Shafts or slopesSHAFTS_SLOPES, ImpoundmentsIMPOUNDMENTS, Coal areas not elsewhere classifiedMISC_AREA

Not recorded by MSHA (3)

Supervisor or trainee hours, on siteSUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE, Supervisor or trainee hours, totalSUM_TOTAL_INSP_HRS_SPVR_TRAINEE, Controller at the timeCONTROLLER_NAME

25 most recent of 43 inspections and other MSHA visits since Sep 12, 2001; activity names are MSHA's own text. Full list: MSHA Mine Data Retrieval System.

Citations and orders

Issued: Apr 24, 2025
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
5102105
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 24, 2025
Time issuedVIOLATION_ISSUE_TIME
1400
Date of occurrenceVIOLATION_OCCUR_DT
Jan 16, 2025
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 24, 2025
Originally due, timeORIG_TERM_DUE_TIME
1405
Latest dueLATEST_TERM_DUE_DT
Apr 24, 2025
Latest due, timeLATEST_TERM_DUE_TIME
1405
TerminatedTERMINATION_DT
Apr 24, 2025
Terminated, timeTERMINATION_TIME
1401
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Amount paidAMOUNT_PAID
151
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Final order dateFINAL_ORDER_ISSUE_DT
Jul 23, 2025
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 9, 2025
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6963986
Inspection beganINSPECTION_BEGIN_DT
Apr 17, 2025
Inspection closed outINSPECTION_END_DT
Apr 29, 2025
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Persons potentially affectedNO_AFFECTED, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 24, 2025
Type: Citation
Standard: 56.14100(a)
S&S: Y
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $398.00
Details

The citation

Citation or order numberVIOLATION_NO
5102107
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 24, 2025
Time issuedVIOLATION_ISSUE_TIME
1535
Date of occurrenceVIOLATION_OCCUR_DT
Apr 24, 2025
30 CFR part and sectionPART_SECTION
56.14100(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 25, 2025
Originally due, timeORIG_TERM_DUE_TIME
0735
Latest dueLATEST_TERM_DUE_DT
Apr 25, 2025
Latest due, timeLATEST_TERM_DUE_TIME
0735
TerminatedTERMINATION_DT
Apr 25, 2025
Terminated, timeTERMINATION_TIME
1037
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
398
Current proposed assessmentAMOUNT_DUE
398
Amount paidAMOUNT_PAID
398
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Final order dateFINAL_ORDER_ISSUE_DT
Jul 23, 2025
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 9, 2025
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6963986
Inspection beganINSPECTION_BEGIN_DT
Apr 17, 2025
Inspection closed outINSPECTION_END_DT
Apr 29, 2025
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 24, 2025
Type: Citation
Standard: 56.18002(a)
S&S: Y
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $398.00
Details

The citation

Citation or order numberVIOLATION_NO
5102106
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 24, 2025
Time issuedVIOLATION_ISSUE_TIME
1520
Date of occurrenceVIOLATION_OCCUR_DT
Apr 24, 2025
30 CFR part and sectionPART_SECTION
56.18002(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 25, 2025
Originally due, timeORIG_TERM_DUE_TIME
0730
Latest dueLATEST_TERM_DUE_DT
Apr 25, 2025
Latest due, timeLATEST_TERM_DUE_TIME
0730
TerminatedTERMINATION_DT
Apr 25, 2025
Terminated, timeTERMINATION_TIME
1040
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
398
Current proposed assessmentAMOUNT_DUE
398
Amount paidAMOUNT_PAID
398
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Final order dateFINAL_ORDER_ISSUE_DT
Jul 23, 2025
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 9, 2025
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6963986
Inspection beganINSPECTION_BEGIN_DT
Apr 17, 2025
Inspection closed outINSPECTION_END_DT
Apr 29, 2025
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 17, 2025
Type: Citation
Standard: 56.14100(b)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
5102104
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 17, 2025
Time issuedVIOLATION_ISSUE_TIME
1150
Date of occurrenceVIOLATION_OCCUR_DT
Apr 17, 2025
30 CFR part and sectionPART_SECTION
56.14100(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 29, 2025
Originally due, timeORIG_TERM_DUE_TIME
0905
Latest dueLATEST_TERM_DUE_DT
Apr 29, 2025
Latest due, timeLATEST_TERM_DUE_TIME
0905
TerminatedTERMINATION_DT
Apr 29, 2025
Terminated, timeTERMINATION_TIME
1512
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Amount paidAMOUNT_PAID
151
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Final order dateFINAL_ORDER_ISSUE_DT
Jul 23, 2025
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 9, 2025
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6963986
Inspection beganINSPECTION_BEGIN_DT
Apr 17, 2025
Inspection closed outINSPECTION_END_DT
Apr 29, 2025
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 17, 2025
Type: Citation
Standard: 46.9(a)
S&S: N
Negligence: HighNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
5102102
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 17, 2025
Time issuedVIOLATION_ISSUE_TIME
1337
Date of occurrenceVIOLATION_OCCUR_DT
Apr 17, 2025
30 CFR part and sectionPART_SECTION
46.9(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
HighNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 22, 2025
Originally due, timeORIG_TERM_DUE_TIME
1753
Latest dueLATEST_TERM_DUE_DT
Apr 22, 2025
Latest due, timeLATEST_TERM_DUE_TIME
1753
TerminatedTERMINATION_DT
Apr 22, 2025
Terminated, timeTERMINATION_TIME
1753
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Amount paidAMOUNT_PAID
151
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Final order dateFINAL_ORDER_ISSUE_DT
Jul 23, 2025
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 9, 2025
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6963986
Inspection beganINSPECTION_BEGIN_DT
Apr 17, 2025
Inspection closed outINSPECTION_END_DT
Apr 29, 2025
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (2)

Persons potentially affectedNO_AFFECTED, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 17, 2025
Type: Citation
Standard: 56.14100(b)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
5102103
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 17, 2025
Time issuedVIOLATION_ISSUE_TIME
1139
Date of occurrenceVIOLATION_OCCUR_DT
Apr 17, 2025
30 CFR part and sectionPART_SECTION
56.14100(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 29, 2025
Originally due, timeORIG_TERM_DUE_TIME
0900
Latest dueLATEST_TERM_DUE_DT
Apr 29, 2025
Latest due, timeLATEST_TERM_DUE_TIME
0900
TerminatedTERMINATION_DT
Apr 29, 2025
Terminated, timeTERMINATION_TIME
1508
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Amount paidAMOUNT_PAID
151
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Final order dateFINAL_ORDER_ISSUE_DT
Jul 23, 2025
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 9, 2025
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6963986
Inspection beganINSPECTION_BEGIN_DT
Apr 17, 2025
Inspection closed outINSPECTION_END_DT
Apr 29, 2025
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2025
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2025
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 27, 2023
Type: Citation
Standard: 56.14132(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $143.00
Details

The citation

Citation or order numberVIOLATION_NO
9507776
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 27, 2023
Time issuedVIOLATION_ISSUE_TIME
0920
Date of occurrenceVIOLATION_OCCUR_DT
Apr 27, 2023
30 CFR part and sectionPART_SECTION
56.14132(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
May 4, 2023
Originally due, timeORIG_TERM_DUE_TIME
0800
Latest dueLATEST_TERM_DUE_DT
May 4, 2023
Latest due, timeLATEST_TERM_DUE_TIME
0800
TerminatedTERMINATION_DT
May 9, 2023
Terminated, timeTERMINATION_TIME
1545
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
143
Current proposed assessmentAMOUNT_DUE
143
Amount paidAMOUNT_PAID
143
Bill first printedBILL_PRINT_DT
Jun 7, 2023
Final order dateFINAL_ORDER_ISSUE_DT
Jul 12, 2023
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 6, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6874387
Inspection beganINSPECTION_BEGIN_DT
Apr 27, 2023
Inspection closed outINSPECTION_END_DT
Apr 27, 2023
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 27, 2023
Type: Citation
Standard: 56.12016
S&S: Y
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $376.00
Details

The citation

Citation or order numberVIOLATION_NO
9507775
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 27, 2023
Time issuedVIOLATION_ISSUE_TIME
0815
Date of occurrenceVIOLATION_OCCUR_DT
Apr 27, 2023
30 CFR part and sectionPART_SECTION
56.12016
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 27, 2023
Originally due, timeORIG_TERM_DUE_TIME
0845
Latest dueLATEST_TERM_DUE_DT
Apr 27, 2023
Latest due, timeLATEST_TERM_DUE_TIME
0845
TerminatedTERMINATION_DT
Apr 27, 2023
Terminated, timeTERMINATION_TIME
0825
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
376
Current proposed assessmentAMOUNT_DUE
376
Amount paidAMOUNT_PAID
376
Bill first printedBILL_PRINT_DT
Jun 7, 2023
Final order dateFINAL_ORDER_ISSUE_DT
Jul 12, 2023
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 6, 2023
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6874387
Inspection beganINSPECTION_BEGIN_DT
Apr 27, 2023
Inspection closed outINSPECTION_END_DT
Apr 27, 2023
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2023
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2023
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (4)

From a 103(g) written noticeWRITTEN_NOTICE, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 29, 2022
Type: Citation
Standard: 56.3200
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9502271
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 29, 2022
Time issuedVIOLATION_ISSUE_TIME
1145
Date of occurrenceVIOLATION_OCCUR_DT
Jul 29, 2022
30 CFR part and sectionPART_SECTION
56.3200
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Aug 1, 2022
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Aug 1, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Aug 8, 2022
Terminated, timeTERMINATION_TIME
0930
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Amount paidAMOUNT_PAID
133
Bill first printedBILL_PRINT_DT
Sep 7, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Oct 12, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 20, 2022
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6873984
Inspection beganINSPECTION_BEGIN_DT
Jul 29, 2022
Inspection closed outINSPECTION_END_DT
Aug 1, 2022
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jul 29, 2022
Type: Citation
Standard: 56.14132(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $133.00
Details

The citation

Citation or order numberVIOLATION_NO
9502272
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jul 29, 2022
Time issuedVIOLATION_ISSUE_TIME
1315
Date of occurrenceVIOLATION_OCCUR_DT
Jul 29, 2022
30 CFR part and sectionPART_SECTION
56.14132(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jul 29, 2022
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Jul 29, 2022
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Jul 29, 2022
Terminated, timeTERMINATION_TIME
1330
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
133
Current proposed assessmentAMOUNT_DUE
133
Amount paidAMOUNT_PAID
133
Bill first printedBILL_PRINT_DT
Sep 7, 2022
Final order dateFINAL_ORDER_ISSUE_DT
Oct 12, 2022
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Sep 20, 2022
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6873984
Inspection beganINSPECTION_BEGIN_DT
Jul 29, 2022
Inspection closed outINSPECTION_END_DT
Aug 1, 2022
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2022
Calendar quarterCAL_QTR
3
MSHA fiscal yearFISCAL_YR
2022
MSHA fiscal quarterFISCAL_QTR
4

Recorded as 0 (1)

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 28, 2020
Type: Citation
Standard: 56.16001
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $123.00
Details

The citation

Citation or order numberVIOLATION_NO
9502125
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 28, 2020
Time issuedVIOLATION_ISSUE_TIME
0956
Date of occurrenceVIOLATION_OCCUR_DT
Apr 28, 2020
30 CFR part and sectionPART_SECTION
56.16001
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 28, 2020
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Apr 28, 2020
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Apr 28, 2020
Terminated, timeTERMINATION_TIME
1054
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
123
Current proposed assessmentAMOUNT_DUE
123
Amount paidAMOUNT_PAID
123
Bill first printedBILL_PRINT_DT
Jun 15, 2020
Final order dateFINAL_ORDER_ISSUE_DT
Jul 24, 2020
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 7, 2020
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
5
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6829417
Inspection beganINSPECTION_BEGIN_DT
Apr 28, 2020
Inspection closed outINSPECTION_END_DT
Apr 28, 2020
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2020
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Oct 2, 2019
Type: Citation
Standard: 56.12004
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $121.00
Details

The citation

Citation or order numberVIOLATION_NO
9437521
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Oct 2, 2019
Time issuedVIOLATION_ISSUE_TIME
1125
Date of occurrenceVIOLATION_OCCUR_DT
Oct 2, 2019
30 CFR part and sectionPART_SECTION
56.12004
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 2, 2019
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Oct 2, 2019
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Oct 2, 2019
Terminated, timeTERMINATION_TIME
1135
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
121
Current proposed assessmentAMOUNT_DUE
121
Amount paidAMOUNT_PAID
121
Bill first printedBILL_PRINT_DT
Nov 6, 2019
Final order dateFINAL_ORDER_ISSUE_DT
Dec 12, 2019
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 27, 2019
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6828592
Inspection beganINSPECTION_BEGIN_DT
Oct 2, 2019
Inspection closed outINSPECTION_END_DT
Oct 4, 2019
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
1

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Oct 2, 2019
Type: Citation
Standard: 56.14112(a)(1)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $121.00
Details

The citation

Citation or order numberVIOLATION_NO
9437522
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Oct 2, 2019
Time issuedVIOLATION_ISSUE_TIME
1155
Date of occurrenceVIOLATION_OCCUR_DT
Oct 2, 2019
30 CFR part and sectionPART_SECTION
56.14112(a)(1)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Oct 3, 2019
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Oct 3, 2019
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Oct 4, 2019
Terminated, timeTERMINATION_TIME
0800
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
121
Current proposed assessmentAMOUNT_DUE
121
Amount paidAMOUNT_PAID
121
Bill first printedBILL_PRINT_DT
Nov 6, 2019
Final order dateFINAL_ORDER_ISSUE_DT
Dec 12, 2019
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Nov 27, 2019
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6828592
Inspection beganINSPECTION_BEGIN_DT
Oct 2, 2019
Inspection closed outINSPECTION_END_DT
Oct 4, 2019
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
4
MSHA fiscal yearFISCAL_YR
2020
MSHA fiscal quarterFISCAL_QTR
1

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 18, 2019
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $121.00
Details

The citation

Citation or order numberVIOLATION_NO
9377845
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 18, 2019
Time issuedVIOLATION_ISSUE_TIME
1400
Date of occurrenceVIOLATION_OCCUR_DT
Apr 18, 2019
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 18, 2019
Originally due, timeORIG_TERM_DUE_TIME
1401
Latest dueLATEST_TERM_DUE_DT
Apr 18, 2019
Latest due, timeLATEST_TERM_DUE_TIME
1401
TerminatedTERMINATION_DT
Apr 18, 2019
Terminated, timeTERMINATION_TIME
1405
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
121
Current proposed assessmentAMOUNT_DUE
121
Amount paidAMOUNT_PAID
121
Bill first printedBILL_PRINT_DT
Jun 13, 2019
Final order dateFINAL_ORDER_ISSUE_DT
Jul 17, 2019
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 8, 2019
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6728194
Inspection beganINSPECTION_BEGIN_DT
Apr 16, 2019
Inspection closed outINSPECTION_END_DT
Apr 24, 2019
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2019
MSHA fiscal quarterFISCAL_QTR
3

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 17, 2019
Type: Citation
Standard: 56.14107(a)
S&S: N
Negligence: LowNegligence
Issued to: Operator
Proposed penalty: $121.00
Details

The citation

Citation or order numberVIOLATION_NO
9377843
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 17, 2019
Time issuedVIOLATION_ISSUE_TIME
1545
Date of occurrenceVIOLATION_OCCUR_DT
Apr 17, 2019
30 CFR part and sectionPART_SECTION
56.14107(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
LowNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 18, 2019
Originally due, timeORIG_TERM_DUE_TIME
1530
Latest dueLATEST_TERM_DUE_DT
Apr 18, 2019
Latest due, timeLATEST_TERM_DUE_TIME
1530
TerminatedTERMINATION_DT
Apr 18, 2019
Terminated, timeTERMINATION_TIME
1145
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
121
Current proposed assessmentAMOUNT_DUE
121
Amount paidAMOUNT_PAID
121
Bill first printedBILL_PRINT_DT
Jun 13, 2019
Final order dateFINAL_ORDER_ISSUE_DT
Jul 17, 2019
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 8, 2019
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6728194
Inspection beganINSPECTION_BEGIN_DT
Apr 16, 2019
Inspection closed outINSPECTION_END_DT
Apr 24, 2019
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2019
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 17, 2019
Type: Citation
Standard: 56.11001
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $121.00
Details

The citation

Citation or order numberVIOLATION_NO
9377844
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 17, 2019
Time issuedVIOLATION_ISSUE_TIME
1650
Date of occurrenceVIOLATION_OCCUR_DT
Apr 17, 2019
30 CFR part and sectionPART_SECTION
56.11001
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 18, 2019
Originally due, timeORIG_TERM_DUE_TIME
1530
Latest dueLATEST_TERM_DUE_DT
Apr 18, 2019
Latest due, timeLATEST_TERM_DUE_TIME
1530
TerminatedTERMINATION_DT
Apr 18, 2019
Terminated, timeTERMINATION_TIME
1150
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
121
Current proposed assessmentAMOUNT_DUE
121
Amount paidAMOUNT_PAID
121
Bill first printedBILL_PRINT_DT
Jun 13, 2019
Final order dateFINAL_ORDER_ISSUE_DT
Jul 17, 2019
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jul 8, 2019
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6728194
Inspection beganINSPECTION_BEGIN_DT
Apr 16, 2019
Inspection closed outINSPECTION_END_DT
Apr 24, 2019
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2019
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2019
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (5)

From a 103(g) written noticeWRITTEN_NOTICE, Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (13)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 3, 2018
Type: Citation
Standard: 56.20003(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
9377142
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 3, 2018
Time issuedVIOLATION_ISSUE_TIME
1215
Date of occurrenceVIOLATION_OCCUR_DT
Apr 3, 2018
30 CFR part and sectionPART_SECTION
56.20003(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 3, 2018
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Apr 3, 2018
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Apr 3, 2018
Terminated, timeTERMINATION_TIME
1510
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Amount paidAMOUNT_PAID
151
Bill first printedBILL_PRINT_DT
May 17, 2018
Final order dateFINAL_ORDER_ISSUE_DT
Jul 1, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 6, 2018
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
13
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6728420
Inspection beganINSPECTION_BEGIN_DT
Apr 3, 2018
Inspection closed outINSPECTION_END_DT
Apr 4, 2018
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 3, 2018
Type: Citation
Standard: 56.12004
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $151.00
Details

The citation

Citation or order numberVIOLATION_NO
9377141
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 3, 2018
Time issuedVIOLATION_ISSUE_TIME
1145
Date of occurrenceVIOLATION_OCCUR_DT
Apr 3, 2018
30 CFR part and sectionPART_SECTION
56.12004
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 3, 2018
Originally due, timeORIG_TERM_DUE_TIME
1630
Latest dueLATEST_TERM_DUE_DT
Apr 3, 2018
Latest due, timeLATEST_TERM_DUE_TIME
1630
TerminatedTERMINATION_DT
Apr 3, 2018
Terminated, timeTERMINATION_TIME
1525
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
151
Current proposed assessmentAMOUNT_DUE
151
Amount paidAMOUNT_PAID
151
Bill first printedBILL_PRINT_DT
May 17, 2018
Final order dateFINAL_ORDER_ISSUE_DT
Jul 1, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 6, 2018
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
13
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6728420
Inspection beganINSPECTION_BEGIN_DT
Apr 3, 2018
Inspection closed outINSPECTION_END_DT
Apr 4, 2018
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Apr 3, 2018
Type: Citation
Standard: 56.12032
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $502.00
Details

The citation

Citation or order numberVIOLATION_NO
9377140
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Apr 3, 2018
Time issuedVIOLATION_ISSUE_TIME
1130
Date of occurrenceVIOLATION_OCCUR_DT
Apr 3, 2018
30 CFR part and sectionPART_SECTION
56.12032
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Apr 3, 2018
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Apr 3, 2018
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Apr 3, 2018
Terminated, timeTERMINATION_TIME
1520
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
502
Current proposed assessmentAMOUNT_DUE
502
Amount paidAMOUNT_PAID
502
Bill first printedBILL_PRINT_DT
May 17, 2018
Final order dateFINAL_ORDER_ISSUE_DT
Jul 1, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 6, 2018
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
13
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6728420
Inspection beganINSPECTION_BEGIN_DT
Apr 3, 2018
Inspection closed outINSPECTION_END_DT
Apr 4, 2018
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
2
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
3

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jan 4, 2018
Type: Citation
Standard: 56.13011
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $502.00
Details

The citation

Citation or order numberVIOLATION_NO
8879939
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jan 4, 2018
Time issuedVIOLATION_ISSUE_TIME
1410
Date of occurrenceVIOLATION_OCCUR_DT
Jan 4, 2018
30 CFR part and sectionPART_SECTION
56.13011
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jan 5, 2018
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Jan 5, 2018
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Jan 5, 2018
Terminated, timeTERMINATION_TIME
1330
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
502
Current proposed assessmentAMOUNT_DUE
502
Amount paidAMOUNT_PAID
502
Bill first printedBILL_PRINT_DT
Feb 15, 2018
Final order dateFINAL_ORDER_ISSUE_DT
Apr 1, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Mar 7, 2018
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
16
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6721962
Inspection beganINSPECTION_BEGIN_DT
Jan 3, 2018
Inspection closed outINSPECTION_END_DT
Jan 5, 2018
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
2

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jan 4, 2018
Type: Citation
Standard: 50.30(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $118.00
Details

The citation

Citation or order numberVIOLATION_NO
8879940
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jan 4, 2018
Time issuedVIOLATION_ISSUE_TIME
1420
Date of occurrenceVIOLATION_OCCUR_DT
Jan 4, 2018
30 CFR part and sectionPART_SECTION
50.30(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
NoLikelihood
Expected injury or illnessINJ_ILLNESS
NoLostDays
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jan 5, 2018
Originally due, timeORIG_TERM_DUE_TIME
1200
Latest dueLATEST_TERM_DUE_DT
Jan 5, 2018
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
Jan 5, 2018
Terminated, timeTERMINATION_TIME
1200
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
118
Current proposed assessmentAMOUNT_DUE
118
Amount paidAMOUNT_PAID
118
Bill first printedBILL_PRINT_DT
Feb 15, 2018
Final order dateFINAL_ORDER_ISSUE_DT
Apr 1, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Mar 7, 2018
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
16
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6721962
Inspection beganINSPECTION_BEGIN_DT
Jan 3, 2018
Inspection closed outINSPECTION_END_DT
Jan 5, 2018
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
2

Recorded as 0 (1)

Persons potentially affectedNO_AFFECTED

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Jan 4, 2018
Type: Citation
Standard: 56.13015
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $502.00
Details

The citation

Citation or order numberVIOLATION_NO
8879938
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Jan 4, 2018
Time issuedVIOLATION_ISSUE_TIME
1400
Date of occurrenceVIOLATION_OCCUR_DT
Jan 4, 2018
30 CFR part and sectionPART_SECTION
56.13015
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Jan 12, 2018
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Apr 21, 2018
Latest due, timeLATEST_TERM_DUE_TIME
1200
TerminatedTERMINATION_DT
Apr 23, 2018
Terminated, timeTERMINATION_TIME
1045
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
502
Current proposed assessmentAMOUNT_DUE
502
Amount paidAMOUNT_PAID
502
Bill first printedBILL_PRINT_DT
Feb 15, 2018
Final order dateFINAL_ORDER_ISSUE_DT
Apr 1, 2018
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Mar 7, 2018
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
16
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6721962
Inspection beganINSPECTION_BEGIN_DT
Jan 3, 2018
Inspection closed outINSPECTION_END_DT
Jan 5, 2018
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2018
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2018
MSHA fiscal quarterFISCAL_QTR
2

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Mar 21, 2017
Type: Citation
Standard: 56.9300(b)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $116.00
Details

The citation

Citation or order numberVIOLATION_NO
8991460
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Mar 21, 2017
Time issuedVIOLATION_ISSUE_TIME
0845
Date of occurrenceVIOLATION_OCCUR_DT
Mar 21, 2017
30 CFR part and sectionPART_SECTION
56.9300(b)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
LostDays
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Mar 21, 2017
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Mar 21, 2017
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Mar 21, 2017
Terminated, timeTERMINATION_TIME
1130
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
116
Current proposed assessmentAMOUNT_DUE
116
Amount paidAMOUNT_PAID
116
Bill first printedBILL_PRINT_DT
May 18, 2017
Final order dateFINAL_ORDER_ISSUE_DT
Jul 2, 2017
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 13, 2017
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6721718
Inspection beganINSPECTION_BEGIN_DT
Mar 21, 2017
Inspection closed outINSPECTION_END_DT
Mar 23, 2017
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
2

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Mar 21, 2017
Type: Citation
Standard: 56.14107(a)
S&S: N
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $116.00
Details

The citation

Citation or order numberVIOLATION_NO
8991462
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Mar 21, 2017
Time issuedVIOLATION_ISSUE_TIME
0920
Date of occurrenceVIOLATION_OCCUR_DT
Mar 21, 2017
30 CFR part and sectionPART_SECTION
56.14107(a)
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

LikelihoodLIKELIHOOD
Unlikely
Expected injury or illnessINJ_ILLNESS
Permanent
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Mar 21, 2017
Originally due, timeORIG_TERM_DUE_TIME
1500
Latest dueLATEST_TERM_DUE_DT
Mar 21, 2017
Latest due, timeLATEST_TERM_DUE_TIME
1500
TerminatedTERMINATION_DT
Mar 21, 2017
Terminated, timeTERMINATION_TIME
1350
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
116
Current proposed assessmentAMOUNT_DUE
116
Amount paidAMOUNT_PAID
116
Bill first printedBILL_PRINT_DT
May 18, 2017
Final order dateFINAL_ORDER_ISSUE_DT
Jul 2, 2017
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 13, 2017
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6721718
Inspection beganINSPECTION_BEGIN_DT
Mar 21, 2017
Inspection closed outINSPECTION_END_DT
Mar 23, 2017
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
2

Recorded as N (4)

Significant and substantialSIG_SUB, Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

Issued: Mar 21, 2017
Type: Citation
Standard: 56.12028
S&S: Y
Negligence: ModNegligence
Issued to: Operator
Proposed penalty: $330.00
Details

The citation

Citation or order numberVIOLATION_NO
8991465
TypeCIT_ORD_SAFE
Citation
IssuedVIOLATION_ISSUE_DT
Mar 21, 2017
Time issuedVIOLATION_ISSUE_TIME
1240
Date of occurrenceVIOLATION_OCCUR_DT
Mar 21, 2017
30 CFR part and sectionPART_SECTION
56.12028
Section of the Act, primarySECTION_OF_ACT_1
104(a)
Primary mine or millPRIMARY_OR_MILL
Primary

Gravity and negligence, as the inspector recorded them

Significant and substantialSIG_SUB
Y
LikelihoodLIKELIHOOD
Reasonably
Expected injury or illnessINJ_ILLNESS
Fatal
Persons potentially affectedNO_AFFECTED
1
NegligenceNEGLIGENCE
ModNegligence

Abatement

Originally dueORIG_TERM_DUE_DT
Mar 22, 2017
Originally due, timeORIG_TERM_DUE_TIME
1600
Latest dueLATEST_TERM_DUE_DT
Mar 22, 2017
Latest due, timeLATEST_TERM_DUE_TIME
1600
TerminatedTERMINATION_DT
Mar 22, 2017
Terminated, timeTERMINATION_TIME
0800
Termination typeTERMINATION_TYPE
Terminated

Penalty and contest

Proposed penaltyPROPOSED_PENALTY
330
Current proposed assessmentAMOUNT_DUE
330
Amount paidAMOUNT_PAID
330
Bill first printedBILL_PRINT_DT
May 18, 2017
Final order dateFINAL_ORDER_ISSUE_DT
Jul 2, 2017
Last actionLAST_ACTION_CD
Paid
Last action dateLAST_ACTION_DT
Jun 13, 2017
Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Operator's inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2

Who, inspection and period

Issued toVIOLATOR_TYPE_CD
Operator
Operator at the timeVIOLATOR_NAME
Custom Crushing Industries Inc
Operator IDVIOLATOR_ID
0106885
Controller IDCONTROLLER_ID
0107341
Inspection eventEVENT_NO
6721718
Inspection beganINSPECTION_BEGIN_DT
Mar 21, 2017
Inspection closed outINSPECTION_END_DT
Mar 23, 2017
Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine type in this fileMINE_TYPE
Surface
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Calendar yearCAL_YR
2017
Calendar quarterCAL_QTR
1
MSHA fiscal yearFISCAL_YR
2017
MSHA fiscal quarterFISCAL_QTR
2

Recorded as N (3)

Special assessmentSPECIAL_ASSESS, Assessment generated indicatorASMT_GENERATED_IND, ContestedCONTESTED_IND

Not recorded by MSHA (14)

Section of the ActSECTION_OF_ACT, Section of the Act, secondarySECTION_OF_ACT_2, Enforcement areaENFORCEMENT_AREA, From a 103(g) written noticeWRITTEN_NOTICE, Preceding citationINITIAL_VIOL_NO, Replaced by orderREPLACED_BY_ORDER_NO, VacatedVACATE_DT, Vacated, timeVACATE_TIME, Advised of right to a conferenceRIGHT_TO_CONF_DT, Most recent docket status dateCONTESTED_DT, Docket numberDOCKET_NO, Docket statusDOCKET_STATUS_CD, Contractor IDCONTRACTOR_ID, Controller at the timeCONTROLLER_NAME

93 citations and orders since Sep 12, 2001: 93 issued to the operator, 0 to contractors working at the mine; the 25 most recent are listed. Proposed penalty is MSHA's original proposed amount, before any change from a contested case. Citations can be contested, modified or vacated.

Penalties as assessed

Issued: Apr 24, 2025
Citation number: 5102107
Standard: 56.14100(a)
Proposed penalty: $398.00
Current assessment: $398.00
Paid against proposed penalty: $398.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
5102107
Assessment control numberASSESS_CASE_NO
000622046
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 9, 2025
Citation issuedISSUE_DT
Apr 24, 2025
Date of occurrenceOCCURRENCE_DT
Apr 24, 2025
Final order dateFINAL_ORDER_DT
Jul 23, 2025
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 23, 2025
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
398.00
Current assessmentCURRENT_ASSESSMENT_AMT
398.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
398.00

Penalty points

Violation history pointsPENALTY_POINTS
72
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Operator hours worked at the mineVIOLATOR_MINE_HRS
9190
Size of mineSIZE_OF_MINE
9190
Controller hours workedCONTROLLER_HRS
20376
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20376
History period startHISTORY_START_DT
Jan 24, 2024
History period endHISTORY_END_DT
Apr 23, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6963986
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 24, 2025
Citation number: 5102105
Standard: 50.30(a)
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $151.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
5102105
Assessment control numberASSESS_CASE_NO
000622046
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 9, 2025
Citation issuedISSUE_DT
Apr 24, 2025
Date of occurrenceOCCURRENCE_DT
Jan 16, 2025
Final order dateFINAL_ORDER_DT
Jul 23, 2025
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 23, 2025
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
151.00

Penalty points

Violation history pointsPENALTY_POINTS
11
Negligence pointsNEGLIGENCE_POINTS
10
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Operator hours worked at the mineVIOLATOR_MINE_HRS
9190
Size of mineSIZE_OF_MINE
9190
Controller hours workedCONTROLLER_HRS
20376
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20376
History period startHISTORY_START_DT
Oct 16, 2023
History period endHISTORY_END_DT
Jan 15, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6963986
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (18)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 24, 2025
Citation number: 5102106
Standard: 56.18002(a)
Proposed penalty: $398.00
Current assessment: $398.00
Paid against proposed penalty: $398.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
5102106
Assessment control numberASSESS_CASE_NO
000622046
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 9, 2025
Citation issuedISSUE_DT
Apr 24, 2025
Date of occurrenceOCCURRENCE_DT
Apr 24, 2025
Final order dateFINAL_ORDER_DT
Jul 23, 2025
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 23, 2025
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.18002(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
398.00
Current assessmentCURRENT_ASSESSMENT_AMT
398.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
398.00

Penalty points

Violation history pointsPENALTY_POINTS
72
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Operator hours worked at the mineVIOLATOR_MINE_HRS
9190
Size of mineSIZE_OF_MINE
9190
Controller hours workedCONTROLLER_HRS
20376
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20376
History period startHISTORY_START_DT
Jan 24, 2024
History period endHISTORY_END_DT
Apr 23, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6963986
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 17, 2025
Citation number: 5102102
Standard: 46.9(a)
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $151.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
5102102
Assessment control numberASSESS_CASE_NO
000622046
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 9, 2025
Citation issuedISSUE_DT
Apr 17, 2025
Date of occurrenceOCCURRENCE_DT
Apr 17, 2025
Final order dateFINAL_ORDER_DT
Jul 23, 2025
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 23, 2025
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
46.9(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
151.00

Penalty points

Violation history pointsPENALTY_POINTS
36
Negligence pointsNEGLIGENCE_POINTS
35
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Operator hours worked at the mineVIOLATOR_MINE_HRS
9190
Size of mineSIZE_OF_MINE
9190
Controller hours workedCONTROLLER_HRS
20376
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20376
History period startHISTORY_START_DT
Jan 17, 2024
History period endHISTORY_END_DT
Apr 16, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6963986
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (18)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 17, 2025
Citation number: 5102103
Standard: 56.14100(b)
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $151.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
5102103
Assessment control numberASSESS_CASE_NO
000622046
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 9, 2025
Citation issuedISSUE_DT
Apr 17, 2025
Date of occurrenceOCCURRENCE_DT
Apr 17, 2025
Final order dateFINAL_ORDER_DT
Jul 23, 2025
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 23, 2025
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
151.00

Penalty points

Violation history pointsPENALTY_POINTS
37
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Operator hours worked at the mineVIOLATOR_MINE_HRS
9190
Size of mineSIZE_OF_MINE
9190
Controller hours workedCONTROLLER_HRS
20376
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20376
History period startHISTORY_START_DT
Jan 17, 2024
History period endHISTORY_END_DT
Apr 16, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6963986
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 17, 2025
Citation number: 5102104
Standard: 56.14100(b)
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $151.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
5102104
Assessment control numberASSESS_CASE_NO
000622046
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 9, 2025
Citation issuedISSUE_DT
Apr 17, 2025
Date of occurrenceOCCURRENCE_DT
Apr 17, 2025
Final order dateFINAL_ORDER_DT
Jul 23, 2025
Bill first printedBILL_PRINT_DT
Jun 11, 2025
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2025
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 23, 2025
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14100(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
151.00

Penalty points

Violation history pointsPENALTY_POINTS
37
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Operator hours worked at the mineVIOLATOR_MINE_HRS
9190
Size of mineSIZE_OF_MINE
9190
Controller hours workedCONTROLLER_HRS
20376
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20376
History period startHISTORY_START_DT
Jan 17, 2024
History period endHISTORY_END_DT
Apr 16, 2025

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6963986
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 27, 2023
Citation number: 9507775
Standard: 56.12016
Proposed penalty: $376.00
Current assessment: $376.00
Paid against proposed penalty: $376.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9507775
Assessment control numberASSESS_CASE_NO
000578497
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 6, 2023
Citation issuedISSUE_DT
Apr 27, 2023
Date of occurrenceOCCURRENCE_DT
Apr 27, 2023
Final order dateFINAL_ORDER_DT
Jul 12, 2023
Bill first printedBILL_PRINT_DT
Jun 7, 2023
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2023
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 12, 2023
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12016
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
376.00
Current assessmentCURRENT_ASSESSMENT_AMT
376.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
376.00

Penalty points

Violation history pointsPENALTY_POINTS
72
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
7412
Size of mineSIZE_OF_MINE
7412
Controller hours workedCONTROLLER_HRS
9747
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
9747
History period startHISTORY_START_DT
Jan 27, 2022
History period endHISTORY_END_DT
Apr 26, 2023

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6874387
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (13)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 27, 2023
Citation number: 9507776
Standard: 56.14132(a)
Proposed penalty: $143.00
Current assessment: $143.00
Paid against proposed penalty: $143.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9507776
Assessment control numberASSESS_CASE_NO
000578497
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 6, 2023
Citation issuedISSUE_DT
Apr 27, 2023
Date of occurrenceOCCURRENCE_DT
Apr 27, 2023
Final order dateFINAL_ORDER_DT
Jul 12, 2023
Bill first printedBILL_PRINT_DT
Jun 7, 2023
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2023
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 12, 2023
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14132(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
143.00
Current assessmentCURRENT_ASSESSMENT_AMT
143.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
143.00

Penalty points

Violation history pointsPENALTY_POINTS
52
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
2
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
1
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
1
Repeat violations per inspection dayRPID
0.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
7412
Size of mineSIZE_OF_MINE
7412
Controller hours workedCONTROLLER_HRS
9747
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
9747
History period startHISTORY_START_DT
Jan 27, 2022
History period endHISTORY_END_DT
Apr 26, 2023

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6874387
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (11)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 29, 2022
Citation number: 9502272
Standard: 56.14132(a)
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $133.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9502272
Assessment control numberASSESS_CASE_NO
000562346
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 20, 2022
Citation issuedISSUE_DT
Jul 29, 2022
Date of occurrenceOCCURRENCE_DT
Jul 29, 2022
Final order dateFINAL_ORDER_DT
Oct 12, 2022
Bill first printedBILL_PRINT_DT
Sep 7, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 12, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14132(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
133.00

Penalty points

Violation history pointsPENALTY_POINTS
52
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
7999
Size of mineSIZE_OF_MINE
7999
Controller hours workedCONTROLLER_HRS
15012
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
15012
History period startHISTORY_START_DT
Apr 29, 2021
History period endHISTORY_END_DT
Jul 28, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6873984
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jul 29, 2022
Citation number: 9502271
Standard: 56.3200
Proposed penalty: $133.00
Current assessment: $133.00
Paid against proposed penalty: $133.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9502271
Assessment control numberASSESS_CASE_NO
000562346
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Sep 20, 2022
Citation issuedISSUE_DT
Jul 29, 2022
Date of occurrenceOCCURRENCE_DT
Jul 29, 2022
Final order dateFINAL_ORDER_DT
Oct 12, 2022
Bill first printedBILL_PRINT_DT
Sep 7, 2022
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2022
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Oct 12, 2022
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.3200
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
133.00
Current assessmentCURRENT_ASSESSMENT_AMT
133.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
133.00

Penalty points

Violation history pointsPENALTY_POINTS
52
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1
Operator hours worked at the mineVIOLATOR_MINE_HRS
7999
Size of mineSIZE_OF_MINE
7999
Controller hours workedCONTROLLER_HRS
15012
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
15012
History period startHISTORY_START_DT
Apr 29, 2021
History period endHISTORY_END_DT
Jul 28, 2022

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6873984
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Assessed violations in the history periodVIOLATOR_VIOLATION_CNT, Violations per inspection dayVPID, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 28, 2020
Citation number: 9502125
Standard: 56.16001
Proposed penalty: $123.00
Current assessment: $123.00
Paid against proposed penalty: $123.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9502125
Assessment control numberASSESS_CASE_NO
000515956
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 7, 2020
Citation issuedISSUE_DT
Apr 28, 2020
Date of occurrenceOCCURRENCE_DT
Apr 28, 2020
Final order dateFINAL_ORDER_DT
Jul 24, 2020
Bill first printedBILL_PRINT_DT
Jun 15, 2020
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2020
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 24, 2020
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.16001
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
123.00
Current assessmentCURRENT_ASSESSMENT_AMT
123.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
123.00

Penalty points

Violation history pointsPENALTY_POINTS
37
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
5
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
1.67
Operator hours worked at the mineVIOLATOR_MINE_HRS
6908
Size of mineSIZE_OF_MINE
6908
Controller hours workedCONTROLLER_HRS
16391
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
16391
History period startHISTORY_START_DT
Jan 28, 2019
History period endHISTORY_END_DT
Apr 27, 2020

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6829417
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (13)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Oct 2, 2019
Citation number: 9437522
Standard: 56.14112(a)(1)
Proposed penalty: $121.00
Current assessment: $121.00
Paid against proposed penalty: $121.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9437522
Assessment control numberASSESS_CASE_NO
000503276
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 27, 2019
Citation issuedISSUE_DT
Oct 2, 2019
Date of occurrenceOCCURRENCE_DT
Oct 2, 2019
Final order dateFINAL_ORDER_DT
Dec 12, 2019
Bill first printedBILL_PRINT_DT
Nov 6, 2019
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2020
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 12, 2019
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14112(a)(1)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
121.00
Current assessmentCURRENT_ASSESSMENT_AMT
121.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
121.00

Penalty points

Violation history pointsPENALTY_POINTS
42
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
10
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
1.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
6534
Size of mineSIZE_OF_MINE
6534
Controller hours workedCONTROLLER_HRS
17670
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
17670
History period startHISTORY_START_DT
Jul 2, 2018
History period endHISTORY_END_DT
Oct 1, 2019

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6828592
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (13)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Oct 2, 2019
Citation number: 9437521
Standard: 56.12004
Proposed penalty: $121.00
Current assessment: $121.00
Paid against proposed penalty: $121.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9437521
Assessment control numberASSESS_CASE_NO
000503276
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Nov 27, 2019
Citation issuedISSUE_DT
Oct 2, 2019
Date of occurrenceOCCURRENCE_DT
Oct 2, 2019
Final order dateFINAL_ORDER_DT
Dec 12, 2019
Bill first printedBILL_PRINT_DT
Nov 6, 2019
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2020
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Dec 12, 2019
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12004
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
121.00
Current assessmentCURRENT_ASSESSMENT_AMT
121.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
121.00

Penalty points

Violation history pointsPENALTY_POINTS
52
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
3
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
1.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
6534
Size of mineSIZE_OF_MINE
6534
Controller hours workedCONTROLLER_HRS
17670
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
17670
History period startHISTORY_START_DT
Jul 2, 2018
History period endHISTORY_END_DT
Oct 1, 2019

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6828592
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (13)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 18, 2019
Citation number: 9377845
Standard: 50.30(a)
Proposed penalty: $121.00
Current assessment: $121.00
Paid against proposed penalty: $121.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9377845
Assessment control numberASSESS_CASE_NO
000493260
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 8, 2019
Citation issuedISSUE_DT
Apr 18, 2019
Date of occurrenceOCCURRENCE_DT
Apr 18, 2019
Final order dateFINAL_ORDER_DT
Jul 17, 2019
Bill first printedBILL_PRINT_DT
Jun 13, 2019
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2019
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 17, 2019
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
121.00
Current assessmentCURRENT_ASSESSMENT_AMT
121.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
121.00

Penalty points

Violation history pointsPENALTY_POINTS
21
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
3
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
1
Repeat violations per inspection dayRPID
0.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
6534
Size of mineSIZE_OF_MINE
6534
Controller hours workedCONTROLLER_HRS
17670
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
17670
History period startHISTORY_START_DT
Jan 18, 2018
History period endHISTORY_END_DT
Apr 17, 2019

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6728194
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (14)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 17, 2019
Citation number: 9377844
Standard: 56.11001
Proposed penalty: $121.00
Current assessment: $121.00
Paid against proposed penalty: $121.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9377844
Assessment control numberASSESS_CASE_NO
000493260
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 8, 2019
Citation issuedISSUE_DT
Apr 17, 2019
Date of occurrenceOCCURRENCE_DT
Apr 17, 2019
Final order dateFINAL_ORDER_DT
Jul 17, 2019
Bill first printedBILL_PRINT_DT
Jun 13, 2019
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2019
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 17, 2019
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.11001
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
121.00
Current assessmentCURRENT_ASSESSMENT_AMT
121.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
121.00

Penalty points

Violation history pointsPENALTY_POINTS
37
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1
Violations per inspection dayVPID
6
Operator hours worked at the mineVIOLATOR_MINE_HRS
6534
Size of mineSIZE_OF_MINE
6534
Controller hours workedCONTROLLER_HRS
17670
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
17670
History period startHISTORY_START_DT
Jan 17, 2018
History period endHISTORY_END_DT
Apr 16, 2019

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6728194
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (13)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 17, 2019
Citation number: 9377843
Standard: 56.14107(a)
Proposed penalty: $121.00
Current assessment: $121.00
Paid against proposed penalty: $121.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9377843
Assessment control numberASSESS_CASE_NO
000493260
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jul 8, 2019
Citation issuedISSUE_DT
Apr 17, 2019
Date of occurrenceOCCURRENCE_DT
Apr 17, 2019
Final order dateFINAL_ORDER_DT
Jul 17, 2019
Bill first printedBILL_PRINT_DT
Jun 13, 2019
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2019
Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT
Jul 17, 2019
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.14107(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
121.00
Current assessmentCURRENT_ASSESSMENT_AMT
121.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
121.00

Penalty points

Violation history pointsPENALTY_POINTS
27
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
10
Mine size pointsMINE_SIZE_POINTS
1

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
1
Violations per inspection dayVPID
6
Operator hours worked at the mineVIOLATOR_MINE_HRS
6534
Size of mineSIZE_OF_MINE
6534
Controller hours workedCONTROLLER_HRS
17670
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
17670
History period startHISTORY_START_DT
Jan 17, 2018
History period endHISTORY_END_DT
Apr 16, 2019

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6728194
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (13)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (1)

Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 3, 2018
Citation number: 9377140
Standard: 56.12032
Proposed penalty: $502.00
Current assessment: $502.00
Paid against proposed penalty: $502.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9377140
Assessment control numberASSESS_CASE_NO
000465181
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 6, 2018
Citation issuedISSUE_DT
Apr 3, 2018
Date of occurrenceOCCURRENCE_DT
Apr 3, 2018
Final order dateFINAL_ORDER_DT
Jul 1, 2018
Bill first printedBILL_PRINT_DT
May 17, 2018
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12032
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
502.00
Current assessmentCURRENT_ASSESSMENT_AMT
502.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
502.00

Penalty points

Violation history pointsPENALTY_POINTS
78
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25
Mine size pointsMINE_SIZE_POINTS
2

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
13
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
3.25
Operator hours worked at the mineVIOLATOR_MINE_HRS
11062
Size of mineSIZE_OF_MINE
11062
Controller hours workedCONTROLLER_HRS
20439
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20439
History period startHISTORY_START_DT
Jan 3, 2017
History period endHISTORY_END_DT
Apr 2, 2018

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6728420
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 3, 2018
Citation number: 9377141
Standard: 56.12004
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $151.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9377141
Assessment control numberASSESS_CASE_NO
000465181
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 6, 2018
Citation issuedISSUE_DT
Apr 3, 2018
Date of occurrenceOCCURRENCE_DT
Apr 3, 2018
Final order dateFINAL_ORDER_DT
Jul 1, 2018
Bill first printedBILL_PRINT_DT
May 17, 2018
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12004
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
151.00

Penalty points

Violation history pointsPENALTY_POINTS
63
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25
Mine size pointsMINE_SIZE_POINTS
2

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
13
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
3.25
Operator hours worked at the mineVIOLATOR_MINE_HRS
11062
Size of mineSIZE_OF_MINE
11062
Controller hours workedCONTROLLER_HRS
20439
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20439
History period startHISTORY_START_DT
Jan 3, 2017
History period endHISTORY_END_DT
Apr 2, 2018

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6728420
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Apr 3, 2018
Citation number: 9377142
Standard: 56.20003(a)
Proposed penalty: $151.00
Current assessment: $151.00
Paid against proposed penalty: $151.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
9377142
Assessment control numberASSESS_CASE_NO
000465181
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 6, 2018
Citation issuedISSUE_DT
Apr 3, 2018
Date of occurrenceOCCURRENCE_DT
Apr 3, 2018
Final order dateFINAL_ORDER_DT
Jul 1, 2018
Bill first printedBILL_PRINT_DT
May 17, 2018
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.20003(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
151.00
Current assessmentCURRENT_ASSESSMENT_AMT
151.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
151.00

Penalty points

Violation history pointsPENALTY_POINTS
63
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25
Mine size pointsMINE_SIZE_POINTS
2

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
13
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
4
Violations per inspection dayVPID
3.25
Repeat violationsVIOLATOR_REPEATED_VIOL_CNT
2
Repeat violations per inspection dayRPID
0.5
Operator hours worked at the mineVIOLATOR_MINE_HRS
11062
Size of mineSIZE_OF_MINE
11062
Controller hours workedCONTROLLER_HRS
20439
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20439
History period startHISTORY_START_DT
Jan 3, 2017
History period endHISTORY_END_DT
Apr 2, 2018

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6728420
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (10)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jan 4, 2018
Citation number: 8879939
Standard: 56.13011
Proposed penalty: $502.00
Current assessment: $502.00
Paid against proposed penalty: $502.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8879939
Assessment control numberASSESS_CASE_NO
000458919
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Mar 7, 2018
Citation issuedISSUE_DT
Jan 4, 2018
Date of occurrenceOCCURRENCE_DT
Jan 4, 2018
Final order dateFINAL_ORDER_DT
Apr 1, 2018
Bill first printedBILL_PRINT_DT
Feb 15, 2018
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.13011
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
502.00
Current assessmentCURRENT_ASSESSMENT_AMT
502.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
502.00

Penalty points

Violation history pointsPENALTY_POINTS
78
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25
Mine size pointsMINE_SIZE_POINTS
2

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
16
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
5.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
11062
Size of mineSIZE_OF_MINE
11062
Controller hours workedCONTROLLER_HRS
20439
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20439
History period startHISTORY_START_DT
Oct 4, 2016
History period endHISTORY_END_DT
Jan 3, 2018

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6721962
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jan 4, 2018
Citation number: 8879938
Standard: 56.13015
Proposed penalty: $502.00
Current assessment: $502.00
Paid against proposed penalty: $502.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8879938
Assessment control numberASSESS_CASE_NO
000458919
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Mar 7, 2018
Citation issuedISSUE_DT
Jan 4, 2018
Date of occurrenceOCCURRENCE_DT
Jan 4, 2018
Final order dateFINAL_ORDER_DT
Apr 1, 2018
Bill first printedBILL_PRINT_DT
Feb 15, 2018
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.13015
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
502.00
Current assessmentCURRENT_ASSESSMENT_AMT
502.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
502.00

Penalty points

Violation history pointsPENALTY_POINTS
78
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25
Mine size pointsMINE_SIZE_POINTS
2

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
16
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
5.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
11062
Size of mineSIZE_OF_MINE
11062
Controller hours workedCONTROLLER_HRS
20439
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20439
History period startHISTORY_START_DT
Oct 4, 2016
History period endHISTORY_END_DT
Jan 3, 2018

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6721962
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (12)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Jan 4, 2018
Citation number: 8879940
Standard: 50.30(a)
Proposed penalty: $118.00
Current assessment: $118.00
Paid against proposed penalty: $118.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8879940
Assessment control numberASSESS_CASE_NO
000458919
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Mar 7, 2018
Citation issuedISSUE_DT
Jan 4, 2018
Date of occurrenceOCCURRENCE_DT
Jan 4, 2018
Final order dateFINAL_ORDER_DT
Apr 1, 2018
Bill first printedBILL_PRINT_DT
Feb 15, 2018
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2018
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
50.30(a)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
118.00
Current assessmentCURRENT_ASSESSMENT_AMT
118.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
118.00

Penalty points

Violation history pointsPENALTY_POINTS
47
Negligence pointsNEGLIGENCE_POINTS
20
Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS
25
Mine size pointsMINE_SIZE_POINTS
2

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
16
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
3
Violations per inspection dayVPID
5.33
Operator hours worked at the mineVIOLATOR_MINE_HRS
11062
Size of mineSIZE_OF_MINE
11062
Controller hours workedCONTROLLER_HRS
20439
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20439
History period startHISTORY_START_DT
Oct 4, 2016
History period endHISTORY_END_DT
Jan 3, 2018

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6721962
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (15)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Mar 21, 2017
Citation number: 8991464
Standard: 46.9(b)(5)
Proposed penalty: $116.00
Current assessment: $116.00
Paid against proposed penalty: $116.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8991464
Assessment control numberASSESS_CASE_NO
000438831
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 13, 2017
Citation issuedISSUE_DT
Mar 21, 2017
Date of occurrenceOCCURRENCE_DT
Mar 21, 2017
Final order dateFINAL_ORDER_DT
Jul 2, 2017
Bill first printedBILL_PRINT_DT
May 18, 2017
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2017
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
46.9(b)(5)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
116.00
Current assessmentCURRENT_ASSESSMENT_AMT
116.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
116.00

Penalty points

Violation history pointsPENALTY_POINTS
22
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
2

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
3
Operator hours worked at the mineVIOLATOR_MINE_HRS
14709
Size of mineSIZE_OF_MINE
14709
Controller hours workedCONTROLLER_HRS
20709
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20709
History period startHISTORY_START_DT
Dec 21, 2015
History period endHISTORY_END_DT
Mar 20, 2017

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6721718
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (16)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Persons potentially affected pointsGRAVITY_PERSONS_POINTS, Injury severity pointsGRAVITY_INJURY_POINTS, Likelihood pointsGRAVITY_LIKELIHOOD_POINTS, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Mar 21, 2017
Citation number: 8991465
Standard: 56.12028
Proposed penalty: $330.00
Current assessment: $330.00
Paid against proposed penalty: $330.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8991465
Assessment control numberASSESS_CASE_NO
000438831
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 13, 2017
Citation issuedISSUE_DT
Mar 21, 2017
Date of occurrenceOCCURRENCE_DT
Mar 21, 2017
Final order dateFINAL_ORDER_DT
Jul 2, 2017
Bill first printedBILL_PRINT_DT
May 18, 2017
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2017
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.12028
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Significant and substantialSIG_SUB_IND
Y
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
330.00
Current assessmentCURRENT_ASSESSMENT_AMT
330.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
330.00

Penalty points

Violation history pointsPENALTY_POINTS
73
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
20
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
30
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
2

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
3
Operator hours worked at the mineVIOLATOR_MINE_HRS
14709
Size of mineSIZE_OF_MINE
14709
Controller hours workedCONTROLLER_HRS
20709
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20709
History period startHISTORY_START_DT
Dec 21, 2015
History period endHISTORY_END_DT
Mar 20, 2017

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6721718
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (13)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (1)

Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

Issued: Mar 21, 2017
Citation number: 8991460
Standard: 56.9300(b)
Proposed penalty: $116.00
Current assessment: $116.00
Paid against proposed penalty: $116.00
Case status: Closed
Details

The assessment

Citation or order numberVIOLATION_NO
8991460
Assessment control numberASSESS_CASE_NO
000438831
Assessment typeASSESS_TYPE_CD
Regular
Case statusASSESS_CASE_STATUS_CD
Closed
Case status dateASSESS_CASE_STATUS_DT
Jun 13, 2017
Citation issuedISSUE_DT
Mar 21, 2017
Date of occurrenceOCCURRENCE_DT
Mar 21, 2017
Final order dateFINAL_ORDER_DT
Jul 2, 2017
Bill first printedBILL_PRINT_DT
May 18, 2017
Bill print fiscal yearBILL_PRINT_FISCAL_YR
2017
Citation typeCITATION_TYPE_CD
Citation
30 CFR standardCFR_STANDARD_CD
56.9300(b)
Section of the Act, primaryPRIMARY_ACTION_CD
104(a)
Good faith reduction appliedGOOD_FAITH_IND
Y

Amounts

Proposed penaltyPROPOSED_PENALTY_AMT
116.00
Current assessmentCURRENT_ASSESSMENT_AMT
116.00
Paid against proposed penaltyPAID_PROPOSED_PENALTY_AMT
116.00

Penalty points

Violation history pointsPENALTY_POINTS
38
Persons potentially affected pointsGRAVITY_PERSONS_POINTS
1
Injury severity pointsGRAVITY_INJURY_POINTS
5
Likelihood pointsGRAVITY_LIKELIHOOD_POINTS
10
Negligence pointsNEGLIGENCE_POINTS
20
Mine size pointsMINE_SIZE_POINTS
2

Inputs to the penalty calculation

Assessed violations in the history periodVIOLATOR_VIOLATION_CNT
6
Inspections in the history periodVIOLATOR_INSPECTION_DAY_CNT
2
Violations per inspection dayVPID
3
Operator hours worked at the mineVIOLATOR_MINE_HRS
14709
Size of mineSIZE_OF_MINE
14709
Controller hours workedCONTROLLER_HRS
20709
Size of controlling entitySIZE_OF_CONTROLLING_ENTITY
20709
History period startHISTORY_START_DT
Dec 21, 2015
History period endHISTORY_END_DT
Mar 20, 2017

Who

Issued toVIOLATOR_TYPE_CD
Operator
Name at the time of the assessmentVIOLATOR_NAME
Custom Crushing Industries Inc
IDVIOLATOR_ID
0106885
Operator start at the mine, as assessedVIOLATOR_START_DT
Sep 28, 2009
Operator end at the mine, as assessedVIOLATOR_END_DT
Sep 9, 9999 (as recorded by MSHA, after the file date)
Inspection eventEVENT_NBR
6721718
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
MSHA office codeOFFICE_CD
M7821

Recorded as 0 (13)

Mine Act interestMINEACT_INTEREST_AMT, Excessive late payment interestEXLATE_INTEREST_AMT, Paid against Mine Act interestPAID_MINEACT_INTEREST_AMT, Paid against late payment interestPAID_EXLATE_INTEREST_AMT, Contractor size pointsCONTRACTOR_SIZE_POINTS, Good faith pointsGOOD_FAITH_POINTS, Violations per inspection day pointsVIOLATION_PER_INSP_DAY_POINTS, Repeated violation pointsVIOLATOR_REPEATED_VIOL_POINTS, Controller size pointsCONTROLLER_SIZE_POINTS, Repeat violationsVIOLATOR_REPEATED_VIOL_CNT, Repeat violations per inspection dayRPID, Operator tonnageVIOLATOR_PRODUCTION_AMT, Controller tonnageCONTROLLER_PRODUCTION_AMT

Recorded as N (2)

Significant and substantialSIG_SUB_IND, Excessive history indicatorEXCESSIVE_HISTORY_IND

Not recorded by MSHA (2)

Delinquent date set by MSHA (not by itself a delinquency)DELINQUENT_DT, Mine Act sectionMINE_ACT_SECTION_CD

25 most recent of 93 assessed citations and orders. Amounts are MSHA's per-citation values; case status is MSHA's own (Closed, Invalid, Printed or Received).

Contested citations and decisions

Contested: Oct 3, 2016
Citation issued: Jul 18, 2016
Docket: WEST 2017-0004
Standard: 56.11002
Proposed penalty: $114.00
Penalty after decision: $114.00
Decided: Apr 12, 2017
Decision type: Dismissal
Details

The contest

Citation or order numberCITATION_NO
8873566
Citation issuedCITATION_ISSUE_DT
Jul 18, 2016
Hearing request receivedCONTEST_DT
Oct 3, 2016
Docket numberDOCKET_NO
WEST 2017-0004
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Margaret
Judge, last nameJUDGE_LAST_NAME
Miller
Decision typeDOCKET_DECISION_TYPE_CODE
Dismissal
DecidedDECISION_DT
Apr 12, 2017
Petition duePETITION_DUE_DT
Nov 17, 2016
Petition filedPETITION_FILED_DT
Oct 11, 2016

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
114.00
Penalty after the decisionDECISION_PENALTY_AMT
114.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.11002
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
LostDays
Negligence when contestedORIGINAL_NEGLIGENCE
LowNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant

Other fields

ISSUING_FIELD_OFFICE
M7821

Recorded as N (1)

S&S when contestedORIGINAL_SIG_SUB_IND

Not recorded by MSHA (9)

Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE, Type when decidedDECISION_CITATION_TYPE_CODE, Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE, S&S when decidedDECISION_SIG_SUB_IND, Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD, Persons potentially affected when decidedDECISION_GRAVITY_PERSONS, Expected injury or illness when decidedDECISION_GRAVITY_INJURY, Negligence when decidedDECISION_NEGLIGENCE

Contested: Oct 3, 2016
Citation issued: Jul 18, 2016
Docket: WEST 2017-0004
Standard: 56.20003(a)
Proposed penalty: $114.00
Penalty after decision: $114.00
Decided: Apr 12, 2017
Decision type: Dismissal
Details

The contest

Citation or order numberCITATION_NO
8873568
Citation issuedCITATION_ISSUE_DT
Jul 18, 2016
Hearing request receivedCONTEST_DT
Oct 3, 2016
Docket numberDOCKET_NO
WEST 2017-0004
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Margaret
Judge, last nameJUDGE_LAST_NAME
Miller
Decision typeDOCKET_DECISION_TYPE_CODE
Dismissal
DecidedDECISION_DT
Apr 12, 2017
Petition duePETITION_DUE_DT
Nov 17, 2016
Petition filedPETITION_FILED_DT
Oct 11, 2016

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
114.00
Penalty after the decisionDECISION_PENALTY_AMT
114.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.20003(a)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
LostDays
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant

Other fields

ISSUING_FIELD_OFFICE
M7821

Not recorded by MSHA (9)

Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE, Type when decidedDECISION_CITATION_TYPE_CODE, Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE, S&S when decidedDECISION_SIG_SUB_IND, Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD, Persons potentially affected when decidedDECISION_GRAVITY_PERSONS, Expected injury or illness when decidedDECISION_GRAVITY_INJURY, Negligence when decidedDECISION_NEGLIGENCE

Contested: Oct 3, 2016
Citation issued: Jul 18, 2016
Docket: WEST 2017-0004
Standard: 46.9(d)(2)
Proposed penalty: $114.00
Penalty after decision: $114.00
Decided: Apr 12, 2017
Decision type: Dismissal
Details

The contest

Citation or order numberCITATION_NO
8873574
Citation issuedCITATION_ISSUE_DT
Jul 18, 2016
Hearing request receivedCONTEST_DT
Oct 3, 2016
Docket numberDOCKET_NO
WEST 2017-0004
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Margaret
Judge, last nameJUDGE_LAST_NAME
Miller
Decision typeDOCKET_DECISION_TYPE_CODE
Dismissal
DecidedDECISION_DT
Apr 12, 2017
Petition duePETITION_DUE_DT
Nov 17, 2016
Petition filedPETITION_FILED_DT
Oct 11, 2016

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
114.00
Penalty after the decisionDECISION_PENALTY_AMT
114.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
46.9(d)(2)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
NoLikelihood
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
NoLostDays
Negligence when contestedORIGINAL_NEGLIGENCE
LowNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant

Other fields

ISSUING_FIELD_OFFICE
M7821

Recorded as 0 (1)

Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS

Recorded as N (1)

S&S when contestedORIGINAL_SIG_SUB_IND

Not recorded by MSHA (9)

Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE, Type when decidedDECISION_CITATION_TYPE_CODE, Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE, S&S when decidedDECISION_SIG_SUB_IND, Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD, Persons potentially affected when decidedDECISION_GRAVITY_PERSONS, Expected injury or illness when decidedDECISION_GRAVITY_INJURY, Negligence when decidedDECISION_NEGLIGENCE

Contested: Oct 3, 2016
Citation issued: Jul 18, 2016
Docket: WEST 2017-0004
Standard: 56.20003(a)
Proposed penalty: $114.00
Penalty after decision: $114.00
Decided: Apr 12, 2017
Decision type: Dismissal
Details

The contest

Citation or order numberCITATION_NO
8873570
Citation issuedCITATION_ISSUE_DT
Jul 18, 2016
Hearing request receivedCONTEST_DT
Oct 3, 2016
Docket numberDOCKET_NO
WEST 2017-0004
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Margaret
Judge, last nameJUDGE_LAST_NAME
Miller
Decision typeDOCKET_DECISION_TYPE_CODE
Dismissal
DecidedDECISION_DT
Apr 12, 2017
Petition duePETITION_DUE_DT
Nov 17, 2016
Petition filedPETITION_FILED_DT
Oct 11, 2016

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
114.00
Penalty after the decisionDECISION_PENALTY_AMT
114.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.20003(a)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
LostDays
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant

Other fields

ISSUING_FIELD_OFFICE
M7821

Not recorded by MSHA (9)

Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE, Type when decidedDECISION_CITATION_TYPE_CODE, Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE, S&S when decidedDECISION_SIG_SUB_IND, Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD, Persons potentially affected when decidedDECISION_GRAVITY_PERSONS, Expected injury or illness when decidedDECISION_GRAVITY_INJURY, Negligence when decidedDECISION_NEGLIGENCE

Contested: Dec 23, 2013
Citation issued: Aug 22, 2013
Docket: WEST 2014-179M
Standard: 56.11002
Proposed penalty: $127.00
Penalty after decision: $127.00
Decided: Aug 20, 2014
Decision type: Default
Details

The contest

Citation or order numberCITATION_NO
8685566
Citation issuedCITATION_ISSUE_DT
Aug 22, 2013
Hearing request receivedCONTEST_DT
Dec 23, 2013
Docket numberDOCKET_NO
WEST 2014-179M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Default
DecidedDECISION_DT
Aug 20, 2014
Petition duePETITION_DUE_DT
Feb 6, 2014
Petition filedPETITION_FILED_DT
Jan 17, 2014

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
127.00
Penalty after the decisionDECISION_PENALTY_AMT
127.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.11002
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Permanent
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR701
MSHA representative officeMSHA_REP_OFFICE_NAME
Denver

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant

Other fields

ISSUING_FIELD_OFFICE
M7651

Not recorded by MSHA (9)

Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE, Type when decidedDECISION_CITATION_TYPE_CODE, Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE, S&S when decidedDECISION_SIG_SUB_IND, Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD, Persons potentially affected when decidedDECISION_GRAVITY_PERSONS, Expected injury or illness when decidedDECISION_GRAVITY_INJURY, Negligence when decidedDECISION_NEGLIGENCE

Contested: Dec 23, 2013
Citation issued: Aug 22, 2013
Docket: WEST 2014-179M
Standard: 56.11012
Proposed penalty: $127.00
Penalty after decision: $127.00
Decided: Aug 20, 2014
Decision type: Default
Details

The contest

Citation or order numberCITATION_NO
8766396
Citation issuedCITATION_ISSUE_DT
Aug 22, 2013
Hearing request receivedCONTEST_DT
Dec 23, 2013
Docket numberDOCKET_NO
WEST 2014-179M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Default
DecidedDECISION_DT
Aug 20, 2014
Petition duePETITION_DUE_DT
Feb 6, 2014
Petition filedPETITION_FILED_DT
Jan 17, 2014

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
127.00
Penalty after the decisionDECISION_PENALTY_AMT
127.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.11012
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Permanent
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
SOL
MSHA representative office codeMSHA_REP_OFFICE_CODE
SR701
MSHA representative officeMSHA_REP_OFFICE_NAME
Denver

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant

Other fields

ISSUING_FIELD_OFFICE
M7651

Not recorded by MSHA (9)

Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE, Type when decidedDECISION_CITATION_TYPE_CODE, Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE, S&S when decidedDECISION_SIG_SUB_IND, Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD, Persons potentially affected when decidedDECISION_GRAVITY_PERSONS, Expected injury or illness when decidedDECISION_GRAVITY_INJURY, Negligence when decidedDECISION_NEGLIGENCE

Contested: Jan 9, 2012
Citation issued: Nov 3, 2011
Docket: WEST 2012-384M
Standard: 56.14107(a)
Proposed penalty: $108.00
Penalty after decision: $100.00
Decided: Oct 10, 2012
Decision type: Settlement
Details

The contest

Citation or order numberCITATION_NO
8603598
Citation issuedCITATION_ISSUE_DT
Nov 3, 2011
Hearing request receivedCONTEST_DT
Jan 9, 2012
Docket numberDOCKET_NO
WEST 2012-384M
Assessment typeASSESS_TYPE_CODE
Regular
Decided byDOCKET_DECISION_BY_CODE
ALJ
Judge, first nameJUDGE_FIRST_NAME
Robert
Judge, last nameJUDGE_LAST_NAME
Lesnick
Decision typeDOCKET_DECISION_TYPE_CODE
Settlement
DecidedDECISION_DT
Oct 10, 2012
Petition duePETITION_DUE_DT
Feb 23, 2012
Petition filedPETITION_FILED_DT
Jan 26, 2012

Penalty

Proposed penalty when contestedPROPOSED_PENALTY_AMT
108.00
Penalty after the decisionDECISION_PENALTY_AMT
100.00

When contested, and when decided

30 CFR standardCFR_STANDARD_CODE
56.14107(a)
Type when contestedORIGINAL_CITATION_TYPE_CODE
Citation
Type when decidedDECISION_CITATION_TYPE_CODE
Citation
Section of the Act when contestedORIGINAL_PRIMARY_ACTION_CODE
104(a)
Section of the Act when decidedDECISION_PRIMARY_ACTION_CODE
104(a)
S&S when contestedORIGINAL_SIG_SUB_IND
Y
Likelihood when contestedORIGINAL_GRAVITY_LIKELIHOOD
Reasonably
Likelihood when decidedDECISION_GRAVITY_LIKELIHOOD
Unlikely
Persons potentially affected when contestedORIGINAL_GRAVITY_PERSONS
1
Persons potentially affected when decidedDECISION_GRAVITY_PERSONS
1
Expected injury or illness when contestedORIGINAL_GRAVITY_INJURY
Permanent
Expected injury or illness when decidedDECISION_GRAVITY_INJURY
Permanent
Negligence when contestedORIGINAL_NEGLIGENCE
ModNegligence
Negligence when decidedDECISION_NEGLIGENCE
ModNegligence

MSHA offices

Issuing program areaISSUING_PROGRAM_AREA
M/NM
Issuing districtISSUING_DISTRICT
M7000
MSHA representative program areaMSHA_REP_PROGRAM_AREA_CODE
M/NM
MSHA representative office codeMSHA_REP_OFFICE_CODE
M7000
MSHA representative officeMSHA_REP_OFFICE_NAME
Vacaville District

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant

Other fields

ISSUING_FIELD_OFFICE
M7821

Recorded as N (1)

S&S when decidedDECISION_SIG_SUB_IND

Not recorded by MSHA (2)

Petition extension datePETITION_EXTENSION_DT, Mine Act sectionMINE_ACT_SECTION_CODE

7 contested citations and orders; decision types are MSHA's own text.

Employment and hours worked

Year: 2026
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 4
Hours worked: 7,392
Details

The report

YearCALENDAR_YR
2026
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
4
Hours workedANNUAL_HRS
7392
Average hours per employeeAVG_EMPLOYEE_HOURS
1848

Mine

Mine IDMINE_ID
0405495
Mine name in this fileCURR_MINE_NM
Portable #1 Big Plant
StateSTATE_ABBR
CA
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2025
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 4
Hours worked: 6,624
Details

The report

YearCALENDAR_YR
2025
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
4
Hours workedANNUAL_HRS
6624
Average hours per employeeAVG_EMPLOYEE_HOURS
1656

Mine

Mine IDMINE_ID
0405495
Mine name in this fileCURR_MINE_NM
Portable #1 Big Plant
StateSTATE_ABBR
CA
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2024
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 4
Hours worked: 9,190
Details

The report

YearCALENDAR_YR
2024
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
4
Hours workedANNUAL_HRS
9190
Average hours per employeeAVG_EMPLOYEE_HOURS
2298

Mine

Mine IDMINE_ID
0405495
Mine name in this fileCURR_MINE_NM
Portable #1 Big Plant
StateSTATE_ABBR
CA
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2023
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 3
Hours worked: 7,166
Details

The report

YearCALENDAR_YR
2023
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
3
Hours workedANNUAL_HRS
7166
Average hours per employeeAVG_EMPLOYEE_HOURS
2389

Mine

Mine IDMINE_ID
0405495
Mine name in this fileCURR_MINE_NM
Portable #1 Big Plant
StateSTATE_ABBR
CA
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2022
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 4
Hours worked: 7,412
Details

The report

YearCALENDAR_YR
2022
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
4
Hours workedANNUAL_HRS
7412
Average hours per employeeAVG_EMPLOYEE_HOURS
1853

Mine

Mine IDMINE_ID
0405495
Mine name in this fileCURR_MINE_NM
Portable #1 Big Plant
StateSTATE_ABBR
CA
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2021
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 100
Details

The report

YearCALENDAR_YR
2021
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
100
Average hours per employeeAVG_EMPLOYEE_HOURS
100

Mine

Mine IDMINE_ID
0405495
Mine name in this fileCURR_MINE_NM
Portable #1 Big Plant
StateSTATE_ABBR
CA
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2021
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 4
Hours worked: 7,999
Details

The report

YearCALENDAR_YR
2021
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
4
Hours workedANNUAL_HRS
7999
Average hours per employeeAVG_EMPLOYEE_HOURS
2000

Mine

Mine IDMINE_ID
0405495
Mine name in this fileCURR_MINE_NM
Portable #1 Big Plant
StateSTATE_ABBR
CA
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2020
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 4
Hours worked: 9,173
Details

The report

YearCALENDAR_YR
2020
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
4
Hours workedANNUAL_HRS
9173
Average hours per employeeAVG_EMPLOYEE_HOURS
2293

Mine

Mine IDMINE_ID
0405495
Mine name in this fileCURR_MINE_NM
Portable #1 Big Plant
StateSTATE_ABBR
CA
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2019
Part of mine: OFFICE WORKERS AT MINE SITE
Average employees: 1
Hours worked: 534
Details

The report

YearCALENDAR_YR
2019
Part of the mineSUBUNIT_DESC
OFFICE WORKERS AT MINE SITE
Part of the mine codeSUBUNIT_CD
99
Average employeesAVG_ANNUAL_EMPL
1
Hours workedANNUAL_HRS
534
Average hours per employeeAVG_EMPLOYEE_HOURS
534

Mine

Mine IDMINE_ID
0405495
Mine name in this fileCURR_MINE_NM
Portable #1 Big Plant
StateSTATE_ABBR
CA
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

Year: 2019
Part of mine: STRIP, QUARY, OPEN PIT
Average employees: 4
Hours worked: 6,908
Details

The report

YearCALENDAR_YR
2019
Part of the mineSUBUNIT_DESC
STRIP, QUARY, OPEN PIT
Part of the mine codeSUBUNIT_CD
03
Average employeesAVG_ANNUAL_EMPL
4
Hours workedANNUAL_HRS
6908
Average hours per employeeAVG_EMPLOYEE_HOURS
1727

Mine

Mine IDMINE_ID
0405495
Mine name in this fileCURR_MINE_NM
Portable #1 Big Plant
StateSTATE_ABBR
CA
Coal or Metal/Non-MetalC_M_IND
M

Recorded as 0 (1)

Coal productionANNUAL_COAL_PROD

What the operator reported to MSHA for the 8 most recent years, one row per part of the mine, as MSHA files them. Rows are not added together.

Mine details

MSHA field office
Vacaville CA Field Office
Nearest town
various
Days worked per week
6
Hours per shift
12
Production shifts per day
1
Maintenance shifts per day
0
Employees, current record
3
Tailing ponds
0
103(i) spot inspection status
Never Had 103I Status
Safety committee
N
Portable operation
Y
Every field in MSHA's mine record

The mine

Mine nameCURRENT_MINE_NAME
Portable #1 Big Plant
Mine IDMINE_ID
0405495
Coal or Metal/Non-MetalCOAL_METAL_IND
M
Mine typeCURRENT_MINE_TYPE
Surface
Current statusCURRENT_MINE_STATUS
Intermittent
Status sinceCURRENT_STATUS_DT
Jan 20, 2023
Legal entity typeCOMPANY_TYPE
Corporation
Portable minePORTABLE_OPERATION
Y
Portable mine FIPS state codePORTABLE_FIPS_ST_CD
06

Operator and controller

OperatorCURRENT_OPERATOR_NAME
Custom Crushing Industries Inc
Operator IDCURRENT_OPERATOR_ID
0106885
Controller IDCURRENT_CONTROLLER_ID
0107341
Start of the operating periodCURRENT_CONTROLLER_BEGIN_DT
Sep 28, 2009

Location and MSHA office

StateSTATE
CA
Bureau of Mines state codeBOM_STATE_CD
04
FIPS county codeFIPS_CNTY_CD
005
FIPS county nameFIPS_CNTY_NM
Amador
Nearest townNEAREST_TOWN
various
MSHA districtDISTRICT
M7
MSHA office codeOFFICE_CD
M7821
MSHA officeOFFICE_NAME
Vacaville CA Field Office
Driving miles from the MSHA officeMILES_FROM_OFFICE
100
Most recent assessment control numberASSESS_CTRL_NO
000622046

Commodity

Primary commodity (SIC)PRIMARY_SIC
Construction Sand and Gravel
Primary commodity codePRIMARY_SIC_CD
144200
Primary SIC codePRIMARY_SIC_CD_1
1442
Primary SIC suffixPRIMARY_SIC_CD_SFX
00
Primary industry groupPRIMARY_CANVASS
SandAndGravel
Primary industry group codePRIMARY_CANVASS_CD
5

Operations, from the Mine Information Form

Days operating per weekDAYS_PER_WEEK
6
Hours per shiftHOURS_PER_SHIFT
12
Production shifts per dayPROD_SHIFTS_PER_DAY
1
Workers employedNO_EMPLOYEES
3
MSHA restricted from enforcing Part 48 trainingPART48_TRAINING
Y
103(i) statusCURRENT_103I
Never Had 103I Status

Recorded as 0 (2)

Maintenance-only shifts per dayMAINT_SHIFTS_PER_DAY, Tailing pondsNO_TAILING_PONDS

Recorded as N (4)

Pillar recovery usedPILLAR_RECOVERY_USED, Highwall miner usedHIGHWALL_MINER_USED, Multiple pitsMULTIPLE_PITS, Safety committeeSAFETY_COMMITTEE_IND

Not recorded by MSHA (14)

ControllerCURRENT_CONTROLLER_NAME, Congressional districtCONG_DIST_CD, Secondary commodity (SIC)SECONDARY_SIC, Secondary commodity codeSECONDARY_SIC_CD, Secondary SIC codeSECONDARY_SIC_CD_1, Secondary SIC suffixSECONDARY_SIC_CD_SFX, Secondary industry groupSECONDARY_CANVASS, Secondary industry group codeSECONDARY_CANVASS_CD, Average mining height, inchesAVG_MINE_HEIGHT, Mine gas categoryMINE_GAS_CATEGORY_CD, Methane liberation, cu ft per 24 hMETHANE_LIBERATION, Producing pitsNO_PRODUCING_PITS, Non-producing pitsNO_NONPRODUCING_PITS, 103(i) status sinceCURRENT_103I_DT

Operator and controller history

Operator: Custom Crushing Industries Inc
From: Sep 28, 2009
To: No end date
Controller: Not shown
From : Jul 1, 2011
To : No end date
Details

Operator

OperatorOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Operator fromOPERATOR_START_DT
Sep 28, 2009

Controller

Controller IDCONTROLLER_ID
0107341
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Jul 1, 2011

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine status at this pointMINE_STATUS
Intermittent
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (3)

Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

Operator: Custom Crushing Industries Inc
From: Sep 28, 2009
To: No end date
Controller: Not shown
From : Jul 1, 2011
To : No end date
Details

Operator

OperatorOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Operator fromOPERATOR_START_DT
Sep 28, 2009

Controller

Controller IDCONTROLLER_ID
0107341
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Jul 1, 2011

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine status at this pointMINE_STATUS
Intermittent
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (3)

Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

Operator: Custom Crushing Industries Inc
From: Sep 28, 2009
To: No end date
Controller: Not shown
From : Sep 28, 2009
To : Jun 30, 2011
Details

Operator

OperatorOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Operator fromOPERATOR_START_DT
Sep 28, 2009

Controller

Controller IDCONTROLLER_ID
0090533
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Sep 28, 2009
Controller toCONTROLLER_END_DT
Jun 30, 2011

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine status at this pointMINE_STATUS
Intermittent
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (2)

Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME

Operator: Custom Crushing Industries Inc
From: Sep 28, 2009
To: No end date
Controller: Not shown
From : Sep 28, 2009
To : Jun 30, 2011
Details

Operator

OperatorOPERATOR_NAME
Custom Crushing Industries Inc
Operator IDOPERATOR_ID
0106885
Operator fromOPERATOR_START_DT
Sep 28, 2009

Controller

Controller IDCONTROLLER_ID
0090533
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Sep 28, 2009
Controller toCONTROLLER_END_DT
Jun 30, 2011

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine status at this pointMINE_STATUS
Intermittent
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (2)

Operator toOPERATOR_END_DT, ControllerCONTROLLER_NAME

Operator: Custom Crushing Industries Llc
From: Aug 1, 2001
To: Sep 27, 2009
Controller: Not shown
From : Aug 1, 2001
To : No end date
Details

Operator

OperatorOPERATOR_NAME
Custom Crushing Industries Llc
Operator IDOPERATOR_ID
L18614
Operator fromOPERATOR_START_DT
Aug 1, 2001
Operator toOPERATOR_END_DT
Sep 27, 2009

Controller

Controller IDCONTROLLER_ID
M34122
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Aug 1, 2001

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine status at this pointMINE_STATUS
Intermittent
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (2)

ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

Operator: Custom Crushing Industries Llc
From: Aug 1, 2001
To: Sep 27, 2009
Controller: Not shown
From : Aug 1, 2001
To : No end date
Details

Operator

OperatorOPERATOR_NAME
Custom Crushing Industries Llc
Operator IDOPERATOR_ID
L18614
Operator fromOPERATOR_START_DT
Aug 1, 2001
Operator toOPERATOR_END_DT
Sep 27, 2009

Controller

Controller IDCONTROLLER_ID
M34122
Company or personCONTROLLER_TYPE
PERSON
Controller fromCONTROLLER_START_DT
Aug 1, 2001

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Mine status at this pointMINE_STATUS
Intermittent
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (2)

ControllerCONTROLLER_NAME, Controller toCONTROLLER_END_DT

As MSHA records it, newest operator first.

Address of record

Custom Crushing Industries Inc·Contact title President·Street not recorded, Yreka CA 96097

MSHA says an address of record "does not represent the actual mine location."

Every field in the address record

Address

Business nameBUSINESS_NAME
Custom Crushing Industries Inc
Contact titleCONTACT_TITLE
President
CityCITY
Yreka
StateSTATE_ABBR
CA
State nameSTATE
California
ZIP codeZIP_CD
96097
CountryCOUNTRY
USA
FIPS state codeFIPS_STATE_CD
06

Mine

Mine IDMINE_ID
0405495
Mine name in this fileMINE_NAME
Portable #1 Big Plant
Nearest townNEAREST_TOWN
various
Mine typeMINE_TYPE_CD
Surface
Mine statusMINE_STATUS
Intermittent
Status sinceMINE_STATUS_DT
Jan 20, 2023
Primary commodity (SIC)PRIMARY_SIC_CD
Construction Sand and Gravel
Coal or Metal/Non-MetalCOAL_METAL_IND
M

Not recorded by MSHA (4)

StreetSTREET, PO boxPO_BOX, ProvincePROVINCE, Foreign postal codePOSTAL_CD

Sources. MSHA open government data files: Mines, Inspections, Violations, AssessedViolations, ContestedViolations, 107(a)OrdersIssued, Accidents, MinesProdYearly, ControllerOperatorHistory, AddressOfRecord. Field labels are shortened from MSHA's definition files, with MSHA's column name beside each. MSHA Mine Data Retrieval System·MSHA fatality report search·MSHA open government data

These are U.S. Department of Labor, Mine Safety and Health Administration records, reproduced as published. Citations can be contested, modified or vacated, and records that are contested or not yet final are included. SafetyRecord.org is not a consumer reporting agency. MSHA records as of Nov 13, 2026. Data and methodology