Macklin Mine
MSHA status: Intermittent since Feb 19, 2026
- Mine ID
- 2902576
- Mine type
- Metal/Non-Metal, Surface
- Commodity
- Construction Sand and Gravel
- County and state
- San Miguel, New Mexico
- Operator
- Northeastern Construction Company
- Controller
- Not shown
- MSHA field office
- Albuquerque NM Field Office
- Nearest town
- Las Vegas
MSHA records as of Oct 23, 2026. Having MSHA inspection records is common for operating mines.
Mine profile as reported to MSHA
- Days worked per week
- 5
- Hours per shift
- 8
- Production shifts per day
- 1
- Maintenance shifts per day
- 0
- Employees, current record
- 2
- Tailing ponds
- 0
- 103(i) spot inspection status
- Never Had 103I Status
- Safety committee
- N
- Portable operation
- N
Every field in MSHA's mine record
- MINE_ID
- 2902576
- CURRENT_MINE_NAME
- Macklin Mine
- COAL_METAL_IND
- M
- CURRENT_MINE_TYPE
- Surface
- CURRENT_MINE_STATUS
- Intermittent
- CURRENT_STATUS_DT
- Feb 19, 2026
- CURRENT_CONTROLLER_ID
- 0198121
- CURRENT_CONTROLLER_NAME
- Not recorded
- CURRENT_OPERATOR_ID
- 0207234
- CURRENT_OPERATOR_NAME
- Northeastern Construction Company
- STATE
- NM
- BOM_STATE_CD
- 29
- FIPS_CNTY_CD
- 047
- FIPS_CNTY_NM
- San Miguel
- CONG_DIST_CD
- Not recorded
- COMPANY_TYPE
- Corporation
- CURRENT_CONTROLLER_BEGIN_DT
- Feb 18, 2026
- DISTRICT
- M5
- OFFICE_CD
- M5641
- OFFICE_NAME
- Albuquerque NM Field Office
- ASSESS_CTRL_NO
- 000644601
- PRIMARY_SIC_CD
- 144200
- PRIMARY_SIC
- Construction Sand and Gravel
- PRIMARY_SIC_CD_1
- 1442
- PRIMARY_SIC_CD_SFX
- 00
- SECONDARY_SIC_CD
- Not recorded
- SECONDARY_SIC
- Not recorded
- SECONDARY_SIC_CD_1
- Not recorded
- SECONDARY_SIC_CD_SFX
- Not recorded
- PRIMARY_CANVASS_CD
- 5
- PRIMARY_CANVASS
- SandAndGravel
- SECONDARY_CANVASS_CD
- Not recorded
- SECONDARY_CANVASS
- Not recorded
- CURRENT_103I
- Never Had 103I Status
- CURRENT_103I_DT
- Not recorded
- PORTABLE_OPERATION
- N
- PORTABLE_FIPS_ST_CD
- Not recorded
- DAYS_PER_WEEK
- 5
- HOURS_PER_SHIFT
- 8
- PROD_SHIFTS_PER_DAY
- 1
- MAINT_SHIFTS_PER_DAY
- 0
- NO_EMPLOYEES
- 2
- PART48_TRAINING
- Y
- AVG_MINE_HEIGHT
- Not recorded
- MINE_GAS_CATEGORY_CD
- Not recorded
- METHANE_LIBERATION
- Not recorded
- NO_PRODUCING_PITS
- Not recorded
- NO_NONPRODUCING_PITS
- Not recorded
- NO_TAILING_PONDS
- 0
- PILLAR_RECOVERY_USED
- N
- HIGHWALL_MINER_USED
- N
- MULTIPLE_PITS
- N
- SAFETY_COMMITTEE_IND
- N
- MILES_FROM_OFFICE
- 130
- NEAREST_TOWN
- Las Vegas
Source: MSHA Mines.txt
Employment and hours worked
What the operator reported to MSHA for the most recent year, one row per part of the mine, as MSHA files them. Rows are not added together.
Year: 2026Part of mine: OFFICE WORKERS AT MINE SITEAverage employees: 1Hours worked: 20
- MINE_ID
- 2902576
- CURR_MINE_NM
- Macklin Mine
- STATE_ABBR
- NM
- SUBUNIT_CD
- 99
- SUBUNIT_DESC
- OFFICE WORKERS AT MINE SITE
- CALENDAR_YR
- 2026
- ANNUAL_HRS
- 20
- ANNUAL_COAL_PROD
- 0
- AVG_ANNUAL_EMPL
- 1
- AVG_EMPLOYEE_HOURS
- 20
- C_M_IND
- M
Year: 2026Part of mine: STRIP, QUARY, OPEN PITAverage employees: 2Hours worked: 160
- MINE_ID
- 2902576
- CURR_MINE_NM
- Macklin Mine
- STATE_ABBR
- NM
- SUBUNIT_CD
- 03
- SUBUNIT_DESC
- STRIP, QUARY, OPEN PIT
- CALENDAR_YR
- 2026
- ANNUAL_HRS
- 160
- ANNUAL_COAL_PROD
- 0
- AVG_ANNUAL_EMPL
- 2
- AVG_EMPLOYEE_HOURS
- 80
- C_M_IND
- M
Source: MSHA MinesProdYearly.txt
Inspections
3 inspections and other MSHA visits since Feb 18, 2026. Activity names are MSHA's own text.
Began: May 26, 2026Ended: Jun 3, 2026Activity: Regular Safety and Health InspectionInspectors: 1Hours on site: 7
- EVENT_NO
- F026ED8
- MINE_ID
- 2902576
- INSPECTION_BEGIN_DT
- May 26, 2026
- INSPECTION_END_DT
- Jun 3, 2026
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- OPERATOR_ID
- 0207234
- OPERATOR_NAME
- Northeastern Construction Company
- CAL_YR
- 2026
- CAL_QTR
- 2
- FISCAL_YR
- 2026
- FISCAL_QTR
- 3
- INSPECT_OFFICE_CD
- M5641
- ACTIVITY_CODE
- E01
- ACTIVITY
- Regular Safety and Health Inspection
- ACTIVE_SECTIONS
- 0
- IDLE_SECTIONS
- 0
- SHAFT_SLOPE_SINK
- 0
- IMPOUND_CONSTR
- 0
- BLDG_CONSTR_SITES
- 0
- DRAGLINES
- 0
- UNCLASSIFIED_CONSTR
- 0
- CO_RECORDS
- N
- SURF_UG_MINE
- N
- SURF_FACILITY_MINE
- N
- REFUSE_PILES
- N
- EXPLOSIVE_STORAGE
- N
- OUTBY_AREAS
- N
- MAJOR_CONSTR
- N
- SHAFTS_SLOPES
- N
- IMPOUNDMENTS
- N
- MISC_AREA
- N
- PROGRAM_AREA
- M/NM--Regular Safety and Health Inspection
- SAMPLE_CNT_AIR
- 0
- SAMPLE_CNT_DUSTSPOT
- 0
- SAMPLE_CNT_DUSTSURVEY
- 0
- SAMPLE_CNT_RESPDUST
- 0
- SAMPLE_CNT_NOISE
- 0
- SAMPLE_CNT_OTHER
- 0
- NBR_INSPECTOR
- 1
- SUM_TOTAL_INSP_HOURS
- 18
- SUM_TOTAL_ON_SITE_HOURS
- 7
- COAL_METAL_IND
- M
- SUM_TOTAL_INSP_HRS_SPVR_TRAINEE
- Not recorded
- SUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE
- Not recorded
Began: May 26, 2026Ended: May 27, 2026Activity: Verbal Hazard Complaint InspectionsInspectors: 1Hours on site: 1.5
- EVENT_NO
- F026ED7
- MINE_ID
- 2902576
- INSPECTION_BEGIN_DT
- May 26, 2026
- INSPECTION_END_DT
- May 27, 2026
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- OPERATOR_ID
- 0207234
- OPERATOR_NAME
- Northeastern Construction Company
- CAL_YR
- 2026
- CAL_QTR
- 2
- FISCAL_YR
- 2026
- FISCAL_QTR
- 3
- INSPECT_OFFICE_CD
- M5641
- ACTIVITY_CODE
- E04
- ACTIVITY
- Verbal Hazard Complaint Inspections
- ACTIVE_SECTIONS
- 0
- IDLE_SECTIONS
- 0
- SHAFT_SLOPE_SINK
- 0
- IMPOUND_CONSTR
- 0
- BLDG_CONSTR_SITES
- 0
- DRAGLINES
- 0
- UNCLASSIFIED_CONSTR
- 0
- CO_RECORDS
- N
- SURF_UG_MINE
- N
- SURF_FACILITY_MINE
- N
- REFUSE_PILES
- N
- EXPLOSIVE_STORAGE
- N
- OUTBY_AREAS
- N
- MAJOR_CONSTR
- N
- SHAFTS_SLOPES
- N
- IMPOUNDMENTS
- N
- MISC_AREA
- N
- PROGRAM_AREA
- M/NM--Verbal Hazard Complaint Inspections
- SAMPLE_CNT_AIR
- 0
- SAMPLE_CNT_DUSTSPOT
- 0
- SAMPLE_CNT_DUSTSURVEY
- 0
- SAMPLE_CNT_RESPDUST
- 0
- SAMPLE_CNT_NOISE
- 0
- SAMPLE_CNT_OTHER
- 0
- NBR_INSPECTOR
- 1
- SUM_TOTAL_INSP_HOURS
- 2.25
- SUM_TOTAL_ON_SITE_HOURS
- 1.5
- COAL_METAL_IND
- M
- SUM_TOTAL_INSP_HRS_SPVR_TRAINEE
- Not recorded
- SUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE
- Not recorded
Began: Feb 18, 2026Ended: Feb 19, 2026Activity: Verbal Hazard Complaint InspectionsInspectors: 1Hours on site: 3
- EVENT_NO
- F026EC4
- MINE_ID
- 2902576
- INSPECTION_BEGIN_DT
- Feb 18, 2026
- INSPECTION_END_DT
- Feb 19, 2026
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- OPERATOR_ID
- 0207234
- OPERATOR_NAME
- Northeastern Construction Company
- CAL_YR
- 2026
- CAL_QTR
- 1
- FISCAL_YR
- 2026
- FISCAL_QTR
- 2
- INSPECT_OFFICE_CD
- M5641
- ACTIVITY_CODE
- E04
- ACTIVITY
- Verbal Hazard Complaint Inspections
- ACTIVE_SECTIONS
- 0
- IDLE_SECTIONS
- 0
- SHAFT_SLOPE_SINK
- 0
- IMPOUND_CONSTR
- 0
- BLDG_CONSTR_SITES
- 0
- DRAGLINES
- 0
- UNCLASSIFIED_CONSTR
- 0
- CO_RECORDS
- N
- SURF_UG_MINE
- N
- SURF_FACILITY_MINE
- N
- REFUSE_PILES
- N
- EXPLOSIVE_STORAGE
- N
- OUTBY_AREAS
- N
- MAJOR_CONSTR
- N
- SHAFTS_SLOPES
- N
- IMPOUNDMENTS
- N
- MISC_AREA
- N
- PROGRAM_AREA
- M/NM--Verbal Hazard Complaint Inspections
- SAMPLE_CNT_AIR
- 0
- SAMPLE_CNT_DUSTSPOT
- 0
- SAMPLE_CNT_DUSTSURVEY
- 0
- SAMPLE_CNT_RESPDUST
- 0
- SAMPLE_CNT_NOISE
- 0
- SAMPLE_CNT_OTHER
- 0
- NBR_INSPECTOR
- 1
- SUM_TOTAL_INSP_HOURS
- 12
- SUM_TOTAL_ON_SITE_HOURS
- 3
- COAL_METAL_IND
- M
- SUM_TOTAL_INSP_HRS_SPVR_TRAINEE
- Not recorded
- SUM_TOTAL_ON_SITE_HRS_SPVR_TRAINEE
- Not recorded
Source: MSHA Inspections.txt
Citations and orders
11 records in MSHA's violations file since Feb 18, 2026: 11 issued to the operator and 0 to contractors working at the mine.
Issued: May 27, 2026Type: CitationStandard: 50.30(a)S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $151.00
- EVENT_NO
- F026ED8
- INSPECTION_BEGIN_DT
- May 26, 2026
- INSPECTION_END_DT
- Jun 3, 2026
- VIOLATION_NO
- 5007393
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- May 27, 2026
- VIOLATION_OCCUR_DT
- May 27, 2026
- CAL_YR
- 2026
- CAL_QTR
- 2
- FISCAL_YR
- 2026
- FISCAL_QTR
- 3
- VIOLATION_ISSUE_TIME
- 1150
- SIG_SUB
- N
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 50.30(a)
- SECTION_OF_ACT_1
- 104(a)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Citation
- ORIG_TERM_DUE_DT
- May 27, 2026
- ORIG_TERM_DUE_TIME
- 1500
- LATEST_TERM_DUE_DT
- May 27, 2026
- LATEST_TERM_DUE_TIME
- 1500
- TERMINATION_DT
- May 27, 2026
- TERMINATION_TIME
- 1400
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- NoLikelihood
- INJ_ILLNESS
- NoLostDays
- NO_AFFECTED
- 0
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- Aug 15, 2026
- PROPOSED_PENALTY
- 151
- AMOUNT_DUE
- 151
- AMOUNT_PAID
- 151
- BILL_PRINT_DT
- Jul 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- Jul 22, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
Issued: May 27, 2026Type: CitationStandard: 56.9300(a)S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $151.00
- EVENT_NO
- F026ED8
- INSPECTION_BEGIN_DT
- May 26, 2026
- INSPECTION_END_DT
- Jun 3, 2026
- VIOLATION_NO
- 5007391
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- May 27, 2026
- VIOLATION_OCCUR_DT
- May 27, 2026
- CAL_YR
- 2026
- CAL_QTR
- 2
- FISCAL_YR
- 2026
- FISCAL_QTR
- 3
- VIOLATION_ISSUE_TIME
- 0916
- SIG_SUB
- N
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 56.9300(a)
- SECTION_OF_ACT_1
- 104(a)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Citation
- ORIG_TERM_DUE_DT
- May 27, 2026
- ORIG_TERM_DUE_TIME
- 1500
- LATEST_TERM_DUE_DT
- May 27, 2026
- LATEST_TERM_DUE_TIME
- 1500
- TERMINATION_DT
- May 27, 2026
- TERMINATION_TIME
- 1012
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- Unlikely
- INJ_ILLNESS
- Fatal
- NO_AFFECTED
- 1
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- Aug 15, 2026
- PROPOSED_PENALTY
- 151
- AMOUNT_DUE
- 151
- AMOUNT_PAID
- 151
- BILL_PRINT_DT
- Jul 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- Jul 22, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
Issued: May 27, 2026Type: CitationStandard: 56.4402S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $151.00
- EVENT_NO
- F026ED8
- INSPECTION_BEGIN_DT
- May 26, 2026
- INSPECTION_END_DT
- Jun 3, 2026
- VIOLATION_NO
- 5007390
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- May 27, 2026
- VIOLATION_OCCUR_DT
- May 27, 2026
- CAL_YR
- 2026
- CAL_QTR
- 2
- FISCAL_YR
- 2026
- FISCAL_QTR
- 3
- VIOLATION_ISSUE_TIME
- 0910
- SIG_SUB
- N
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 56.4402
- SECTION_OF_ACT_1
- 104(a)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Citation
- ORIG_TERM_DUE_DT
- May 27, 2026
- ORIG_TERM_DUE_TIME
- 1200
- LATEST_TERM_DUE_DT
- May 27, 2026
- LATEST_TERM_DUE_TIME
- 1200
- TERMINATION_DT
- May 27, 2026
- TERMINATION_TIME
- 0912
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- Unlikely
- INJ_ILLNESS
- LostDays
- NO_AFFECTED
- 1
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- Aug 15, 2026
- PROPOSED_PENALTY
- 151
- AMOUNT_DUE
- 151
- AMOUNT_PAID
- 151
- BILL_PRINT_DT
- Jul 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- Jul 22, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
Issued: May 27, 2026Type: CitationStandard: 47.31(a)S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $151.00
- EVENT_NO
- F026ED8
- INSPECTION_BEGIN_DT
- May 26, 2026
- INSPECTION_END_DT
- Jun 3, 2026
- VIOLATION_NO
- 5007394
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- May 27, 2026
- VIOLATION_OCCUR_DT
- May 27, 2026
- CAL_YR
- 2026
- CAL_QTR
- 2
- FISCAL_YR
- 2026
- FISCAL_QTR
- 3
- VIOLATION_ISSUE_TIME
- 1151
- SIG_SUB
- N
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 47.31(a)
- SECTION_OF_ACT_1
- 104(a)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Citation
- ORIG_TERM_DUE_DT
- May 28, 2026
- ORIG_TERM_DUE_TIME
- 1200
- LATEST_TERM_DUE_DT
- May 28, 2026
- LATEST_TERM_DUE_TIME
- 1200
- TERMINATION_DT
- May 27, 2026
- TERMINATION_TIME
- 1427
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- Unlikely
- INJ_ILLNESS
- LostDays
- NO_AFFECTED
- 1
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- Aug 15, 2026
- PROPOSED_PENALTY
- 151
- AMOUNT_DUE
- 151
- AMOUNT_PAID
- 151
- BILL_PRINT_DT
- Jul 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- Jul 22, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
Issued: May 27, 2026Type: CitationStandard: 56.23002(a)S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $151.00
- EVENT_NO
- F026ED8
- INSPECTION_BEGIN_DT
- May 26, 2026
- INSPECTION_END_DT
- Jun 3, 2026
- VIOLATION_NO
- 5007395
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- May 27, 2026
- VIOLATION_OCCUR_DT
- May 27, 2026
- CAL_YR
- 2026
- CAL_QTR
- 2
- FISCAL_YR
- 2026
- FISCAL_QTR
- 3
- VIOLATION_ISSUE_TIME
- 1152
- SIG_SUB
- N
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 56.23002(a)
- SECTION_OF_ACT_1
- 104(a)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Citation
- ORIG_TERM_DUE_DT
- Jun 1, 2026
- ORIG_TERM_DUE_TIME
- 1000
- LATEST_TERM_DUE_DT
- Jun 1, 2026
- LATEST_TERM_DUE_TIME
- 1000
- TERMINATION_DT
- Jun 3, 2026
- TERMINATION_TIME
- 1651
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- Unlikely
- INJ_ILLNESS
- LostDays
- NO_AFFECTED
- 1
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- Aug 15, 2026
- PROPOSED_PENALTY
- 151
- AMOUNT_DUE
- 151
- AMOUNT_PAID
- 151
- BILL_PRINT_DT
- Jul 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- Jul 22, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
Issued: May 27, 2026Type: CitationStandard: 56.14132(a)S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $151.00
- EVENT_NO
- F026ED8
- INSPECTION_BEGIN_DT
- May 26, 2026
- INSPECTION_END_DT
- Jun 3, 2026
- VIOLATION_NO
- 5007392
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- May 27, 2026
- VIOLATION_OCCUR_DT
- May 27, 2026
- CAL_YR
- 2026
- CAL_QTR
- 2
- FISCAL_YR
- 2026
- FISCAL_QTR
- 3
- VIOLATION_ISSUE_TIME
- 0925
- SIG_SUB
- N
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 56.14132(a)
- SECTION_OF_ACT_1
- 104(a)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Citation
- ORIG_TERM_DUE_DT
- Jun 1, 2026
- ORIG_TERM_DUE_TIME
- 1100
- LATEST_TERM_DUE_DT
- Jun 1, 2026
- LATEST_TERM_DUE_TIME
- 1100
- TERMINATION_DT
- Jun 3, 2026
- TERMINATION_TIME
- 1649
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- Unlikely
- INJ_ILLNESS
- LostDays
- NO_AFFECTED
- 1
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- Aug 15, 2026
- PROPOSED_PENALTY
- 151
- AMOUNT_DUE
- 151
- AMOUNT_PAID
- 151
- BILL_PRINT_DT
- Jul 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- Jul 22, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
Issued: May 27, 2026Type: CitationStandard: 47.41(a)S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $151.00
- EVENT_NO
- F026ED8
- INSPECTION_BEGIN_DT
- May 26, 2026
- INSPECTION_END_DT
- Jun 3, 2026
- VIOLATION_NO
- 5007389
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- May 27, 2026
- VIOLATION_OCCUR_DT
- May 27, 2026
- CAL_YR
- 2026
- CAL_QTR
- 2
- FISCAL_YR
- 2026
- FISCAL_QTR
- 3
- VIOLATION_ISSUE_TIME
- 0907
- SIG_SUB
- N
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 47.41(a)
- SECTION_OF_ACT_1
- 104(a)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Citation
- ORIG_TERM_DUE_DT
- May 27, 2026
- ORIG_TERM_DUE_TIME
- 1000
- LATEST_TERM_DUE_DT
- May 27, 2026
- LATEST_TERM_DUE_TIME
- 1000
- TERMINATION_DT
- May 27, 2026
- TERMINATION_TIME
- 0909
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- Unlikely
- INJ_ILLNESS
- LostDays
- NO_AFFECTED
- 1
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- Aug 15, 2026
- PROPOSED_PENALTY
- 151
- AMOUNT_DUE
- 151
- AMOUNT_PAID
- 151
- BILL_PRINT_DT
- Jul 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- Jul 22, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
Issued: Feb 18, 2026Type: CitationStandard: 56.1000S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $151.00
- EVENT_NO
- F026EC4
- INSPECTION_BEGIN_DT
- Feb 18, 2026
- INSPECTION_END_DT
- Feb 19, 2026
- VIOLATION_NO
- 5007327
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- Feb 18, 2026
- VIOLATION_OCCUR_DT
- Feb 18, 2026
- CAL_YR
- 2026
- CAL_QTR
- 1
- FISCAL_YR
- 2026
- FISCAL_QTR
- 2
- VIOLATION_ISSUE_TIME
- 1540
- SIG_SUB
- N
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 56.1000
- SECTION_OF_ACT_1
- 104(a)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Citation
- ORIG_TERM_DUE_DT
- Mar 11, 2026
- ORIG_TERM_DUE_TIME
- 1000
- LATEST_TERM_DUE_DT
- Mar 11, 2026
- LATEST_TERM_DUE_TIME
- 1000
- TERMINATION_DT
- Mar 10, 2026
- TERMINATION_TIME
- 1233
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- NoLikelihood
- INJ_ILLNESS
- NoLostDays
- NO_AFFECTED
- 0
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- May 17, 2026
- PROPOSED_PENALTY
- 151
- AMOUNT_DUE
- 151
- AMOUNT_PAID
- 151
- BILL_PRINT_DT
- Apr 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- May 9, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 0
Issued: Feb 18, 2026Type: CitationStandard: 41.11S&S: NNegligence: ModNegligenceIssued to: OperatorProposed penalty: $151.00
- EVENT_NO
- F026EC4
- INSPECTION_BEGIN_DT
- Feb 18, 2026
- INSPECTION_END_DT
- Feb 19, 2026
- VIOLATION_NO
- 5007328
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- Feb 18, 2026
- VIOLATION_OCCUR_DT
- Feb 18, 2026
- CAL_YR
- 2026
- CAL_QTR
- 1
- FISCAL_YR
- 2026
- FISCAL_QTR
- 2
- VIOLATION_ISSUE_TIME
- 1542
- SIG_SUB
- N
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 41.11
- SECTION_OF_ACT_1
- 104(a)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Citation
- ORIG_TERM_DUE_DT
- Mar 11, 2026
- ORIG_TERM_DUE_TIME
- 1001
- LATEST_TERM_DUE_DT
- Mar 11, 2026
- LATEST_TERM_DUE_TIME
- 1001
- TERMINATION_DT
- Feb 18, 2026
- TERMINATION_TIME
- 1701
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- NoLikelihood
- INJ_ILLNESS
- NoLostDays
- NO_AFFECTED
- 0
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- May 17, 2026
- PROPOSED_PENALTY
- 151
- AMOUNT_DUE
- 151
- AMOUNT_PAID
- 151
- BILL_PRINT_DT
- Apr 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- May 9, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 0
Issued: Feb 18, 2026Type: CitationStandard: 46.3(a)S&S: YNegligence: ModNegligenceIssued to: OperatorProposed penalty: $398.00
- EVENT_NO
- F026EC4
- INSPECTION_BEGIN_DT
- Feb 18, 2026
- INSPECTION_END_DT
- Feb 19, 2026
- VIOLATION_NO
- 5007329
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- Feb 18, 2026
- VIOLATION_OCCUR_DT
- Feb 18, 2026
- CAL_YR
- 2026
- CAL_QTR
- 1
- FISCAL_YR
- 2026
- FISCAL_QTR
- 2
- VIOLATION_ISSUE_TIME
- 1545
- SIG_SUB
- Y
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 46.3(a)
- SECTION_OF_ACT_1
- 104(a)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Citation
- ORIG_TERM_DUE_DT
- Mar 11, 2026
- ORIG_TERM_DUE_TIME
- 1003
- LATEST_TERM_DUE_DT
- Mar 11, 2026
- LATEST_TERM_DUE_TIME
- 1003
- TERMINATION_DT
- Mar 2, 2026
- TERMINATION_TIME
- 1227
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- Reasonably
- INJ_ILLNESS
- Fatal
- NO_AFFECTED
- 2
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- May 17, 2026
- PROPOSED_PENALTY
- 398
- AMOUNT_DUE
- 398
- AMOUNT_PAID
- 398
- BILL_PRINT_DT
- Apr 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- May 9, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 0
Issued: Feb 18, 2026Type: OrderStandard: 46.5(a)S&S: YNegligence: ModNegligenceIssued to: OperatorProposed penalty: $443.00
- EVENT_NO
- F026EC4
- INSPECTION_BEGIN_DT
- Feb 18, 2026
- INSPECTION_END_DT
- Feb 19, 2026
- VIOLATION_NO
- 5007330
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_TYPE
- Surface
- COAL_METAL_IND
- M
- CONTRACTOR_ID
- Not recorded
- VIOLATION_ISSUE_DT
- Feb 18, 2026
- VIOLATION_OCCUR_DT
- Feb 18, 2026
- CAL_YR
- 2026
- CAL_QTR
- 1
- FISCAL_YR
- 2026
- FISCAL_QTR
- 2
- VIOLATION_ISSUE_TIME
- 1551
- SIG_SUB
- Y
- SECTION_OF_ACT
- Not recorded
- PART_SECTION
- 46.5(a)
- SECTION_OF_ACT_1
- 104(g)(1)
- SECTION_OF_ACT_2
- Not recorded
- CIT_ORD_SAFE
- Order
- ORIG_TERM_DUE_DT
- Not recorded
- ORIG_TERM_DUE_TIME
- Not recorded
- LATEST_TERM_DUE_DT
- Not recorded
- LATEST_TERM_DUE_TIME
- Not recorded
- TERMINATION_DT
- May 27, 2026
- TERMINATION_TIME
- 1255
- TERMINATION_TYPE
- Terminated
- VACATE_DT
- Not recorded
- VACATE_TIME
- Not recorded
- INITIAL_VIOL_NO
- Not recorded
- REPLACED_BY_ORDER_NO
- Not recorded
- LIKELIHOOD
- Reasonably
- INJ_ILLNESS
- Fatal
- NO_AFFECTED
- 2
- NEGLIGENCE
- ModNegligence
- WRITTEN_NOTICE
- N
- ENFORCEMENT_AREA
- Not recorded
- SPECIAL_ASSESS
- N
- PRIMARY_OR_MILL
- Primary
- RIGHT_TO_CONF_DT
- Not recorded
- ASMT_GENERATED_IND
- N
- FINAL_ORDER_ISSUE_DT
- May 17, 2026
- PROPOSED_PENALTY
- 443
- AMOUNT_DUE
- 443
- AMOUNT_PAID
- 443
- BILL_PRINT_DT
- Apr 9, 2026
- LAST_ACTION_CD
- Paid
- LAST_ACTION_DT
- May 9, 2026
- DOCKET_NO
- Not recorded
- DOCKET_STATUS_CD
- Not recorded
- CONTESTED_IND
- N
- CONTESTED_DT
- Not recorded
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 0
Proposed penalty is MSHA's original proposed amount, before any change from a contested case. Citations can be contested, modified or vacated.
Source: MSHA Violations.txt
Imminent danger orders, section 107(a)
No imminent danger orders for this mine in MSHA's list, which starts July 1, 2010.
Source: MSHA 107(a)OrdersIssued.csv
Penalties as assessed
11 assessed citations and orders. Amounts are MSHA's per-citation values; case status is MSHA's own (Closed, Invalid, Printed or Received).
Issued: May 27, 2026Citation number: 5007395Standard: 56.23002(a)Proposed penalty: $151.00Current assessment: $151.00Paid against proposed penalty: $151.00Case status: Closed
- EVENT_NBR
- F026ED8
- VIOLATION_NO
- 5007395
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000644601
- PRIMARY_ACTION_CD
- 104(a)
- SIG_SUB_IND
- N
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- Y
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 56.23002(a)
- CITATION_TYPE_CD
- Citation
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- Jul 22, 2026
- OCCURRENCE_DT
- May 27, 2026
- ISSUE_DT
- May 27, 2026
- FINAL_ORDER_DT
- Aug 15, 2026
- BILL_PRINT_DT
- Jul 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 151.00
- CURRENT_ASSESSMENT_AMT
- 151.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 151.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 36
- GRAVITY_PERSONS_POINTS
- 1
- GRAVITY_INJURY_POINTS
- 5
- GRAVITY_LIKELIHOOD_POINTS
- 10
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- Aug 15, 2026
- HISTORY_START_DT
- Feb 18, 2026
- HISTORY_END_DT
- May 26, 2026
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Issued: May 27, 2026Citation number: 5007390Standard: 56.4402Proposed penalty: $151.00Current assessment: $151.00Paid against proposed penalty: $151.00Case status: Closed
- EVENT_NBR
- F026ED8
- VIOLATION_NO
- 5007390
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000644601
- PRIMARY_ACTION_CD
- 104(a)
- SIG_SUB_IND
- N
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- Y
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 56.4402
- CITATION_TYPE_CD
- Citation
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- Jul 22, 2026
- OCCURRENCE_DT
- May 27, 2026
- ISSUE_DT
- May 27, 2026
- FINAL_ORDER_DT
- Aug 15, 2026
- BILL_PRINT_DT
- Jul 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 151.00
- CURRENT_ASSESSMENT_AMT
- 151.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 151.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 36
- GRAVITY_PERSONS_POINTS
- 1
- GRAVITY_INJURY_POINTS
- 5
- GRAVITY_LIKELIHOOD_POINTS
- 10
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- Aug 15, 2026
- HISTORY_START_DT
- Feb 18, 2026
- HISTORY_END_DT
- May 26, 2026
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Issued: May 27, 2026Citation number: 5007392Standard: 56.14132(a)Proposed penalty: $151.00Current assessment: $151.00Paid against proposed penalty: $151.00Case status: Closed
- EVENT_NBR
- F026ED8
- VIOLATION_NO
- 5007392
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000644601
- PRIMARY_ACTION_CD
- 104(a)
- SIG_SUB_IND
- N
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- Y
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 56.14132(a)
- CITATION_TYPE_CD
- Citation
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- Jul 22, 2026
- OCCURRENCE_DT
- May 27, 2026
- ISSUE_DT
- May 27, 2026
- FINAL_ORDER_DT
- Aug 15, 2026
- BILL_PRINT_DT
- Jul 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 151.00
- CURRENT_ASSESSMENT_AMT
- 151.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 151.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 36
- GRAVITY_PERSONS_POINTS
- 1
- GRAVITY_INJURY_POINTS
- 5
- GRAVITY_LIKELIHOOD_POINTS
- 10
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- Aug 15, 2026
- HISTORY_START_DT
- Feb 18, 2026
- HISTORY_END_DT
- May 26, 2026
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Issued: May 27, 2026Citation number: 5007389Standard: 47.41(a)Proposed penalty: $151.00Current assessment: $151.00Paid against proposed penalty: $151.00Case status: Closed
- EVENT_NBR
- F026ED8
- VIOLATION_NO
- 5007389
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000644601
- PRIMARY_ACTION_CD
- 104(a)
- SIG_SUB_IND
- N
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- Y
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 47.41(a)
- CITATION_TYPE_CD
- Citation
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- Jul 22, 2026
- OCCURRENCE_DT
- May 27, 2026
- ISSUE_DT
- May 27, 2026
- FINAL_ORDER_DT
- Aug 15, 2026
- BILL_PRINT_DT
- Jul 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 151.00
- CURRENT_ASSESSMENT_AMT
- 151.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 151.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 36
- GRAVITY_PERSONS_POINTS
- 1
- GRAVITY_INJURY_POINTS
- 5
- GRAVITY_LIKELIHOOD_POINTS
- 10
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- Aug 15, 2026
- HISTORY_START_DT
- Feb 18, 2026
- HISTORY_END_DT
- May 26, 2026
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Issued: May 27, 2026Citation number: 5007393Standard: 50.30(a)Proposed penalty: $151.00Current assessment: $151.00Paid against proposed penalty: $151.00Case status: Closed
- EVENT_NBR
- F026ED8
- VIOLATION_NO
- 5007393
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000644601
- PRIMARY_ACTION_CD
- 104(a)
- SIG_SUB_IND
- N
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- Y
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 50.30(a)
- CITATION_TYPE_CD
- Citation
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- Jul 22, 2026
- OCCURRENCE_DT
- May 27, 2026
- ISSUE_DT
- May 27, 2026
- FINAL_ORDER_DT
- Aug 15, 2026
- BILL_PRINT_DT
- Jul 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 151.00
- CURRENT_ASSESSMENT_AMT
- 151.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 151.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 20
- GRAVITY_PERSONS_POINTS
- 0
- GRAVITY_INJURY_POINTS
- 0
- GRAVITY_LIKELIHOOD_POINTS
- 0
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- Aug 15, 2026
- HISTORY_START_DT
- Feb 18, 2026
- HISTORY_END_DT
- May 26, 2026
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Issued: May 27, 2026Citation number: 5007394Standard: 47.31(a)Proposed penalty: $151.00Current assessment: $151.00Paid against proposed penalty: $151.00Case status: Closed
- EVENT_NBR
- F026ED8
- VIOLATION_NO
- 5007394
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000644601
- PRIMARY_ACTION_CD
- 104(a)
- SIG_SUB_IND
- N
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- Y
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 47.31(a)
- CITATION_TYPE_CD
- Citation
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- Jul 22, 2026
- OCCURRENCE_DT
- May 27, 2026
- ISSUE_DT
- May 27, 2026
- FINAL_ORDER_DT
- Aug 15, 2026
- BILL_PRINT_DT
- Jul 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 151.00
- CURRENT_ASSESSMENT_AMT
- 151.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 151.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 36
- GRAVITY_PERSONS_POINTS
- 1
- GRAVITY_INJURY_POINTS
- 5
- GRAVITY_LIKELIHOOD_POINTS
- 10
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- Aug 15, 2026
- HISTORY_START_DT
- Feb 18, 2026
- HISTORY_END_DT
- May 26, 2026
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Issued: May 27, 2026Citation number: 5007391Standard: 56.9300(a)Proposed penalty: $151.00Current assessment: $151.00Paid against proposed penalty: $151.00Case status: Closed
- EVENT_NBR
- F026ED8
- VIOLATION_NO
- 5007391
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000644601
- PRIMARY_ACTION_CD
- 104(a)
- SIG_SUB_IND
- N
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- Y
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 56.9300(a)
- CITATION_TYPE_CD
- Citation
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- Jul 22, 2026
- OCCURRENCE_DT
- May 27, 2026
- ISSUE_DT
- May 27, 2026
- FINAL_ORDER_DT
- Aug 15, 2026
- BILL_PRINT_DT
- Jul 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 151.00
- CURRENT_ASSESSMENT_AMT
- 151.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 151.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 51
- GRAVITY_PERSONS_POINTS
- 1
- GRAVITY_INJURY_POINTS
- 20
- GRAVITY_LIKELIHOOD_POINTS
- 10
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 1
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- Aug 15, 2026
- HISTORY_START_DT
- Feb 18, 2026
- HISTORY_END_DT
- May 26, 2026
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Issued: Feb 18, 2026Citation number: 5007329Standard: 46.3(a)Proposed penalty: $398.00Current assessment: $398.00Paid against proposed penalty: $398.00Case status: Closed
- EVENT_NBR
- F026EC4
- VIOLATION_NO
- 5007329
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000639105
- PRIMARY_ACTION_CD
- 104(a)
- SIG_SUB_IND
- Y
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- Y
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 46.3(a)
- CITATION_TYPE_CD
- Citation
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- May 9, 2026
- OCCURRENCE_DT
- Feb 18, 2026
- ISSUE_DT
- Feb 18, 2026
- FINAL_ORDER_DT
- May 17, 2026
- BILL_PRINT_DT
- Apr 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 398.00
- CURRENT_ASSESSMENT_AMT
- 398.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 398.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 72
- GRAVITY_PERSONS_POINTS
- 2
- GRAVITY_INJURY_POINTS
- 20
- GRAVITY_LIKELIHOOD_POINTS
- 30
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 0
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- May 17, 2026
- HISTORY_START_DT
- Not recorded
- HISTORY_END_DT
- Not recorded
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Issued: Feb 18, 2026Citation number: 5007330Standard: 46.5(a)Proposed penalty: $443.00Current assessment: $443.00Paid against proposed penalty: $443.00Case status: Closed
- EVENT_NBR
- F026EC4
- VIOLATION_NO
- 5007330
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000639105
- PRIMARY_ACTION_CD
- 104(g)(1)
- SIG_SUB_IND
- Y
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- N
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 46.5(a)
- CITATION_TYPE_CD
- Order
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- May 9, 2026
- OCCURRENCE_DT
- Feb 18, 2026
- ISSUE_DT
- Feb 18, 2026
- FINAL_ORDER_DT
- May 17, 2026
- BILL_PRINT_DT
- Apr 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 443.00
- CURRENT_ASSESSMENT_AMT
- 443.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 443.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 72
- GRAVITY_PERSONS_POINTS
- 2
- GRAVITY_INJURY_POINTS
- 20
- GRAVITY_LIKELIHOOD_POINTS
- 30
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 0
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- May 17, 2026
- HISTORY_START_DT
- Not recorded
- HISTORY_END_DT
- Not recorded
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Issued: Feb 18, 2026Citation number: 5007327Standard: 56.1000Proposed penalty: $151.00Current assessment: $151.00Paid against proposed penalty: $151.00Case status: Closed
- EVENT_NBR
- F026EC4
- VIOLATION_NO
- 5007327
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000639105
- PRIMARY_ACTION_CD
- 104(a)
- SIG_SUB_IND
- N
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- Y
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 56.1000
- CITATION_TYPE_CD
- Citation
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- May 9, 2026
- OCCURRENCE_DT
- Feb 18, 2026
- ISSUE_DT
- Feb 18, 2026
- FINAL_ORDER_DT
- May 17, 2026
- BILL_PRINT_DT
- Apr 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 151.00
- CURRENT_ASSESSMENT_AMT
- 151.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 151.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 20
- GRAVITY_PERSONS_POINTS
- 0
- GRAVITY_INJURY_POINTS
- 0
- GRAVITY_LIKELIHOOD_POINTS
- 0
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 0
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- May 17, 2026
- HISTORY_START_DT
- Not recorded
- HISTORY_END_DT
- Not recorded
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Issued: Feb 18, 2026Citation number: 5007328Standard: 41.11Proposed penalty: $151.00Current assessment: $151.00Paid against proposed penalty: $151.00Case status: Closed
- EVENT_NBR
- F026EC4
- VIOLATION_NO
- 5007328
- MINE_ID
- 2902576
- VIOLATOR_ID
- 0207234
- VIOLATOR_NAME
- Northeastern Construction Company
- VIOLATOR_TYPE_CD
- Operator
- COAL_METAL_IND
- M
- OFFICE_CD
- M5641
- ASSESS_CASE_NO
- 000639105
- PRIMARY_ACTION_CD
- 104(a)
- SIG_SUB_IND
- N
- MINE_ACT_SECTION_CD
- Not recorded
- GOOD_FAITH_IND
- Y
- EXCESSIVE_HISTORY_IND
- N
- CFR_STANDARD_CD
- 41.11
- CITATION_TYPE_CD
- Citation
- ASSESS_TYPE_CD
- Regular
- ASSESS_CASE_STATUS_CD
- Closed
- ASSESS_CASE_STATUS_DT
- May 9, 2026
- OCCURRENCE_DT
- Feb 18, 2026
- ISSUE_DT
- Feb 18, 2026
- FINAL_ORDER_DT
- May 17, 2026
- BILL_PRINT_DT
- Apr 9, 2026
- BILL_PRINT_FISCAL_YR
- 2026
- PROPOSED_PENALTY_AMT
- 151.00
- CURRENT_ASSESSMENT_AMT
- 151.00
- MINEACT_INTEREST_AMT
- 0.00
- EXLATE_INTEREST_AMT
- 0.00
- PAID_PROPOSED_PENALTY_AMT
- 151.00
- PAID_MINEACT_INTEREST_AMT
- 0.00
- PAID_EXLATE_INTEREST_AMT
- 0.00
- PENALTY_POINTS
- 20
- GRAVITY_PERSONS_POINTS
- 0
- GRAVITY_INJURY_POINTS
- 0
- GRAVITY_LIKELIHOOD_POINTS
- 0
- NEGLIGENCE_POINTS
- 20
- CONTRACTOR_SIZE_POINTS
- 0
- GOOD_FAITH_POINTS
- 0
- VIOLATOR_VIOLATION_CNT
- 0
- VIOLATOR_INSPECTION_DAY_CNT
- 0
- VPID
- 0
- VIOLATION_PER_INSP_DAY_POINTS
- 0
- VIOLATOR_REPEATED_VIOL_CNT
- 0
- RPID
- 0
- VIOLATOR_REPEATED_VIOL_POINTS
- 0
- VIOLATOR_MINE_HRS
- 0
- VIOLATOR_PRODUCTION_AMT
- 0
- SIZE_OF_MINE
- 0
- MINE_SIZE_POINTS
- 0
- CONTROLLER_HRS
- 0
- CONTROLLER_PRODUCTION_AMT
- 0
- SIZE_OF_CONTROLLING_ENTITY
- 0
- CONTROLLER_SIZE_POINTS
- 0
- DELINQUENT_DT
- May 17, 2026
- HISTORY_START_DT
- Not recorded
- HISTORY_END_DT
- Not recorded
- VIOLATOR_START_DT
- Feb 18, 2026
- VIOLATOR_END_DT
- Sep 9, 9999 (as recorded by MSHA, after the file date)
Source: MSHA AssessedViolations.txt
Contested citations and decisions
No contested citations for this mine in MSHA's contested violations file.
Source: MSHA ContestedViolations.txt
Reported injuries, illnesses and accidents
No accident, injury or illness reports for this mine in MSHA's accident file, which starts in January 2000.
Source: MSHA Accidents.txt
Operator and controller history
As MSHA records it, newest operator first.
Operator: Northeastern Construction CompanyFrom: Feb 18, 2026To: No end dateController: Not shownFrom : Feb 18, 2026To : No end date
- CONTROLLER_ID
- 0198121
- CONTROLLER_NAME
- Not recorded
- CONTROLLER_START_DT
- Feb 18, 2026
- CONTROLLER_END_DT
- Not recorded
- CONTROLLER_TYPE
- PERSON
- COAL_METAL_IND
- M
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- MINE_STATUS
- Intermittent
- OPERATOR_ID
- 0207234
- OPERATOR_NAME
- Northeastern Construction Company
- OPERATOR_START_DT
- Feb 18, 2026
- OPERATOR_END_DT
- Not recorded
Source: MSHA ControllerOperatorHistory.txt
Address of record
- Business
- Northeastern Construction Company
- Contact title
- General Manager
- Address
- Street not shown, Las Vegas NM 87701
MSHA says an address of record "does not represent the actual mine location."
Every field in the address record
- MINE_ID
- 2902576
- MINE_NAME
- Macklin Mine
- CONTACT_TITLE
- General Manager
- NEAREST_TOWN
- Las Vegas
- BUSINESS_NAME
- Northeastern Construction Company
- STREET
- Not recorded
- PO_BOX
- Not recorded
- CITY
- Las Vegas
- STATE_ABBR
- NM
- FIPS_STATE_CD
- 35
- STATE
- New Mexico
- ZIP_CD
- 87701
- COUNTRY
- USA
- PROVINCE
- Not recorded
- POSTAL_CD
- Not recorded
- MINE_TYPE_CD
- Surface
- MINE_STATUS
- Intermittent
- MINE_STATUS_DT
- Feb 19, 2026
- PRIMARY_SIC_CD
- Construction Sand and Gravel
- COAL_METAL_IND
- M
Source: MSHA AddressOfRecord.txt
Full record lists for this mine: MSHA Mine Data Retrieval System.
Official sources and disclaimer
These are U.S. Department of Labor, Mine Safety and Health Administration records, reproduced as published. Citations can be contested, modified or vacated, and records that are contested or not yet final are included. Having MSHA inspection records is common for operating mines. SafetyRecord.org is not a consumer reporting agency. MSHA records as of Oct 23, 2026. Data and methodology